Karangahape CLG Presentation 9 December 2021

Page 1

Karangahape Station

CLG - A Year in Review

9 December 2021


3:00 – Brief welcome – Simon Mitchell, Community Manager 3:05 – A Year in Review - Jonathan Hill, Project Manager 3:15 – Environment – Kate Gullery, Environmental Advisor How we manage noise and vibration 3:20 – Sustainability - Anna Guise, Sustainability Advisor What are the sustainability considerations for this construction 3:25 - Beresford Square – Michael Coup, Senior Project Engineer, Beresford What's coming next year 3:30 – Mercury Lane - Eva Brosius, Project Engineer Mercury Lane What's coming next year 3:35 – Tunnels - Cam Butcher, Construction Manager Mined Tunnels What's coming next year 3:40 – The End Results - Jonathan Hill, Station Manager Karangahape Station Overview of what we can look forward to Site safety over the holidays 3:45 - Discussion and questions Subject matter experts will be available to answer questions

2

4:00 – End

CLG Agenda


Key milestones Jonathan Hill, Karangahape Project Manager • This year we reached many milestones even with the COVID delays. They included: • The Mercury Lane Station box reached grade level (its deepest point) and most recently Beresford Square reached B4. • The mined tunnel breakthrough - now all of the tunnels connect through Mercury Lane. • The TBM Dame Whina Cooper arrived and has already moved on towards Aotea Station where she is expected to arrive early in the new year • We also said farewell to our two road headers - Jean Batten and Dame Valerie Adams – which excavated the mined tunnels, together removing approximately 84,000 tonnes of sandstone.

3


In the Community • • •

A lot of new artwork has appeared around the site making the neighbourhood quite bright The custom designed hoardings and art has been done all by local artists and is reflective of the community Local artists involved include photographer Mark Barber and artists Margarita Vovna, Misery, Paul Walsh to name a few.

Click to add text

4


If you would like a copy of the brochure send us an email and we can send you the link

5

Take some time and enjoy the art located around the site


Beresford Square Entrance • Although it looks calm above ground, beneath we have been very busy.

6


The station crew are working on drainage and the start of the slab construction with a concrete pour completed midDecember.

Once the slab is poured, the team can start the bottom-up wall construction in the western section of the station.

The excavation of B3 was completed in mid-November and this completes the excavation in the western half of the station.


Excavation to B4

To date we have poured over 3100m3 of structural concrete, fixed over 900t of reinforcing steel and excavated 25000m3 of soil / rock


Mercury Lane Entrance

9



Now that the bottom of the bulk excavation has been reached, we have started to installed the drainage 11


Another big milestone for Karangahape Station was the mined tunnel breakthrough, which has now joined all the tunnels back to Mercury Lane

12

Mined Tunnel


Mined tunnel has excavated 50,000m3. Temporary supports within the platform caverns and connecting adits has involved the installation of 7,000 rockbolts and spraying 6,000 m3 of shotcrete.

MERCURY LANE

From MT EDEN

To AOTEA Beresford Connection

Mercury Connection

BERESFORD SQUARE

13


A total length of 534 metres of tunnel have been mined at Karangahape Station.14


The TBM, Dame Whina Cooper passed through Karangahape Station and started the journey to Aotea Station where she is

15


TBM progress – nearly halfway to Aotea from Karangahape and anticipated to arrive there early in the new year

16


Kate Gullery, Environmental Advisor

Environment


Noise and Vibration Receiver Type

We monitor noise and vibration 24/7 at Beresford Square and Mercury Lane to comply with the standards – Attended monitoring by Aecom

Noisy activities such as hydrovac trucks, rock breaking, vibration rollers, concrete saw cutting are planned in advance, notified and occur during construction hours

Controls and mitigation measures for noise include:

Occupied commercial and industrial buildings (including offices

Sensitive Noise and Vibration Receivers (excluding offices) Early childhood Education Centres (whilst occupied during normal opening hours)

Monday to Saturday 0700 - 2200

Sundays and Pub lic Holidays 0700-2200

At all other times 2200-0700

75 dB LAeq

75 dB LAeq

75 dB LAeq

75 dB LAeq 90 dB LAFmax

60 dB LAeq 75 dB LAFmax

60 dB LAeq 75 dB LAFmax

35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas

Construction noise limits

– Noise mats – Eliminating unnecessary noise such as shouting, engines, dropping/banging and scraping digger buckets, tonal reversing alarms choosing quieter machinery – Late weekend start times on/off instead of continuous noise

Noise monitor

Noise Mats

Attended noise monitoring

18


Anna Guise, Sustainability Advisor

Sustainability


Sustainability in 2021 • Materials • Reduced carbon footprint of concrete used at KRD by 19% • Couplers to reduce steel used

• Recycling and reuse • Construction and demolition at KRD – 88% diversion, 3% of this is reused • Glove recycling

• Construction energy

Click to add text

• Using mains power where possible to power plant and equipment e.g. Roadheader, tower crane, gantry crane

• Water use • Recycled water used during hydro-excavation by subcontractor - Southeys • Water treatment plants installed at the sites to treat water prior to discharge

20


Spoil So far at KRD we have excavated over 204,000 tonnes of spoil. That is the same weight as 10 Sky Towers! Final destination of spoil 80,000

77,317

Tonnes

60,000

40,000

35,313 27,517

20,000

0

Envirofill South Winstones - 3 Kings

Woodhill

Final destination

21


Michael Coup, Senior Project Engineer, Beresford

Beresford Square - What’s coming next year


What Comes Next?

• Dec 2021 - Feb 2022 - Complete Top Down Construction

23


What Comes Next?

• Construct B7 to B4 Level March 2022 – June 2022 • Construct B3 to L0 West Walls

24


What Comes Next?

• Construct Remaining Structure July 2022 – January 2023 Ready for Fitout

25


Eva Brosius, Section Engineer

Mercury Lane – What’s coming next year


What's next? • Pour B7 slab – shown in blue at the bottom of the station

27


What's next? • Pour B7 – B4 walls & columns

28


What’s next? • Pour B3 & B4 slabs • Pour walls B4 – B2 • Complete Bottom Up Construction

29


What's next? • Construction of the superstructure at the Mercury Lane Entrance

30


Cam Butcher, Construction Manager Mined Tunnel

Mined Tunnels - What’s coming next year


What is the focus for 2022 • Next year will be a very busy year for the Mined Tunnel Team. • Now that the excavation is completed the focus will go on the Permanente structures for the platform tunnels and intersections. • Steel formwork that has been procured from China, Italy and Turkey will make its way to New Zealand in the new year. It will be fabricated inside the excavated tunnel, and a concrete lining will be poured up to 600mm thick. • Work will also continue with the tunnel waterproofing and reinforced bar instillation. Every junction inside the station requires reinforced steel to strengthen the intersection of the Adits and station entrances. • The TBM will once again pass through the station on its second trip towards Aotea Station. This will be the last time we see the TBM. The tunnel team will come in behind the TBM and build the 4 cross passages that will link the two tunnels together.

32


What is the focus for 2022

Water proofing in MC22

Adit A2 sidewall formwork and reinforcement

33


Jonathan Hill, Station Manager Karangahape Station

The End Results


January 2022 – December 2022 Next year will be an exciting year for Karangahape Station • We will be building each of the levels for the station in Mercury Lane and Beresford Square • This will be done bottom up – Starting at B7 and heading upwards to street level • We will also start the construction of the superstructures above ground • This will set us up for 2023 when we start the fit out works for the superstructures • We are still on track for a completion date of 2024.

35


GENERAL ARRANGEMENT – BERESFORD SQUARE

36


GENERAL ARRANGEMENT – MERCURY LANE

MERCURY LANE STATION

37


Beresford Square

38


Beresford Square

39


Hopetoun Entrance

40


Mercury Lane Arrival

41


Mercury Lane Entrance

42


Mercury Lane Entrance

43


Site safety over the holidays • Security guards will be onsite 24/7 throughout the holidays • They will conduct site inspections on foot and by vehicle • CCTV cameras are active in the area around Mercury Lane and Beresford Square and are monitored 24/7 from the Link Alliance security control room • If you see or hear anything disruptive call the 0800 number as it will be directed to the security team who will be able to respond quickly

Call: 0800 275 8255 and press 4 Email: karangahape@linkalliance.co.nz

AND Merry Christmas

44



Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.