TWH CLG Presentation 13 June 2023

Page 1

Te Waihorotiu Station / Midtown Community Liaison Group

13 June 2023, 4.00-5.30pm

Caffe Greco

Wyndham Street

1
1. Station construction update 2. Streetscape upgrades are underway 3. Small Business Support Programme 2023 4. Auckland Transport update 5. Q&A

Safety & Security

Station construction update

Matt

Wellesley Entrance Building

Multiple stairs, lifts and escalators throughout the site to ensure inclusiveness and accessibility for NZ’s busiest station

Back of house service piping complete!

Passenger Concourse Level

Passenger Concourse Level digital render

Lifts frames are currently being installed from Concourse to Platform levels.

Escalators will be installed very soon

Milestone recently reached – Final Platform concrete poured!

Milestone recently reached – Final Platform concrete poured!

This platform will eventually be where passengers step on and off the trains on either side

Can you guess what this is for?

Western entrance structure

Streetscape construction update

Patrick Gibbs – Project Engineer Nicole Borland – Development Response Manager

Indicative LA programme of works

2023-25

2023

Victoria Street

• Vector enabling works Dec 2022 / Jan 2023 – COMPLETE

• early works - utilities Q1 2023 – COMPLETE

• first concrete base poured Q1 2023 – COMPLETE

• first footpath paver laid Q3 2023

• road asphalt reseal Q3/Q4 2023 (aim to re-open to traffic by approx. end 2023)

Phase one of construction works in conjunction with Te Hā Noa Victoria St

Project (Elliott St to Kitchener St)

Kingston Street above-ground ventilation structure and streetscape early works

Bluestone wall reconstruction starts

2023-2025 (detail tbc)

Albert St, from Victoria to Wyndham St

Albert St, from Victoria to Wellesley St

Wellesley Street in conjunction with Wellesley St Bus Improvements Project

Mayoral Drive in conjunction with The Symphony Centre development

Current constraints

-

Resource availability

- Utilities provider coordination (‘Dig once’ approached is preferred)

- Completing underground and above-ground works

Usual Construction Working Hours

Monday – Saturday– 7am - 7pm

Nightworks and early morning works will be required at certain times – we work with

Five stages of footpath construction

Stage 1 - Utility Connections

Stage 2 – Kerb install & granular base prep

Stage 3 – Concrete base pour

What's next?

• Stage 4 – Cutting and laying

pavers

• Stage 5 – Street furniture & tree planting

Pedestrian diversion plan

• We will continue to work with each individual business when we move the works to right up to the property boundary / shop door.

• Access to businesses will be maintained, however several pedestrian diversions / new accessways will be required due to the close proximity of the works to the businesses, and for safety reasons.

• Not all businesses will be diverted simultaneously – we work in a staged approach to minimise pedestrian confusion/overwhelm.

• All of our usual construction effects mitigation measures will be in place and we will continue to work with the shop owners on wayfinding, signage and business support.

• Please bear with us – we are now on the home stretch.

Community and business support

We want to hear from you!

Have ideas?

Come talk to us

Small Business Support Programme

William Keung Independent Business Connector

APPLICATIONS NOW OPEN

• Free independent business advice

• $3,000 Microgrant to enhance your business

“William the SBSP independent business connector has been very helpful in giving encouraging business advice as well as taking care of the application process from start to finish.”
- Sam Shum, Pepper’s Cafe

“Using the SBSP I was able to reach a wider audience, increasing my turnover.

Sponsorship opportunities have also opened up for the shop which includes events, music and so on because more people are aware of my business through advertising.”

- Daniel Jones, Howlin’ Wolf Cuts and Coffee
•William Keung •Independent Business Connector •0274908501 •william@werkits.com

LOADING & SERVICING

Te Waihorotiu Station CLG

13 June 2023

CHALLENGES

•High density of residents and businesses leads to high demand for loading zones

•Changing demand profile: deliveries, contractors, pick-up/drop-off

•Loading zones must be close enough to businesses, to account for heavy goods, business operators, and residents, as well as those with mobility needs

•Competition for space will increase as the City Centre grows with street space being redesigned to support this growth

3 4

CAUSES

Limited kerb space & design decisions

• Loading and servicing competes with other uses of road corridor: pedestrians, public transport, cycle lanes

• We must find a balance between footpaths vs bus efficiency vs loading zones – we cannot have them all everywhere.

• Albert Street is planned to be run as a 24/7 clearway to ensure bus efficiency and reliability, meaning no loading zones (LZ) can be installed.

Enforcement challenges

• Multiple incidents of physical and verbal abuse against AT Parking Officers in Midtown has led to limited patrols in the area.

• Parking fines may be too low to be a disincentive and may need to be increased to see behaviour change.

3 5

STRATEGIC PLANS

Region-wide Parking Strategy (refresh awaiting endorsement)

Midtown Loading & Servicing Study (2022)

City Centre Comprehensive Parking Management Plan (from Jan 2025)

• Delivered January 2025

• Aligns parking and kerbside space management with strategies to deliver on objectives while responding to changing land uses and needs

• Engagement with stakeholders

January 2024

City Centre Interim Management Plan (refreshed annually)

• The MLSS is complete, and recommendations are being implemented as opportunities and funding become available

• The city centre is governed by the Interim Management Plan until 2025 when the Comprehensive Parking Management Plan will supersede it

3 6

TACTICALIMPROVEMENTS

AucklandTransport is seeking to make quicker tactical interventions ahead of the larger strategic refresh:

• Approximately 6 new loading zones will be delivered as projects like Te Hā Noa complete

• Investigation of further 5 LZ on and aroundAlbert Street

• Increasing enforcement through CCTV to deliver higher turnover and utility

• 16 sites for CCTV installation confirmed for FY23

• 18 sites for CCTV installation to be investigated FY24

Under review Not feasible LZ confirmed 3 7
Albert Albert Bus Lanes Albert Bus Lanes Albert footpath Federal Albert (Victoria-Wellesley) slip lane Albert (Swanson-Victoria) slip lane Victoria footpath Federal Albert Wellesley Elliott Victoria Durham St West Wyndham
3 8
Darby Kingston St

VICTORIAFOOTPATH

• Southern side: CRLportal and cycleway

• Northern side: footpath would need narrowing to fit LZ, and loading zone would be under canopy

• Bus and coach services must be able to traverse this area, with stops outside the SkyTower

• No LZ feasible in this location

3 9

FEDERALSTREET

• 6 existing LZ

• CCTV enforcement to be installed at 65-72 Federal Street

• Improvements in usage should be seen in this location

• Potential to convert parking into more LZ in the future, subject to performance of CCTV

Wyndham Victoria Albert Federal Kingston Hobson
4 0
LZ LZ LZ LZ

KINGSTON STREET

• Western side of courthouse was proposed for Police parking plus 1 LZ

• An additional LZ has been added instead of yellow lines

• New total of 2 LZ

Wyndham Victoria Albert
Federal Kingston 4 1
Hobson LZ LZ

ALBERT(VICTORIA-WELLESLEY) SLIPLANE

Pre-CRL

• 6 parking spaces on slip lane

Albert Street Slip lane

Post-CRL

• Slip lane narrowed

• Future NRG development may require access from slip lane

• No LZ feasible in this location

Albert Street Slip lane

Victoria
4 2

ALBERT(SWANSON-VICTORIA) SLIPLANE

Pre-CRL

• Parking spaces on slip lane

Post-CRL

• Slip lane narrowed

• Design has been changed to add 1 LZ

Albert Slip lane Albert Wyndham Durham Durham Slip lane
4 3
LZ

ALBERTSTREETFOOTPATHS

• CRLdesign has street furniture and planting with wide footpath

• Anticipating very high pedestrian volumes from CRLstation

• Indented LZ being investigated

• May not be feasible due to design and/or pedestrian volumes

Victoria Victoria Durham Slip lane Slip lane
4 4
Albert

ALBERTSTREETBUS LANES

• Important corridor for high volume of buses, including new frequent Western Express service

• Planned as 24/7 bus lanes

• May be scope to add LZ for after-hours use

• Subject to bus operating patterns in 2025 onwards

4 5

QUESTIONS?

Programme Director, City CentreTransport Integration

graeme.gunthorp@at.govt.nz

4 6

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.