CLG Karangahape Road Presentation 26 August 2021

Page 1

Community Liaison Group Karangahape Station 26 August 2021


CLG agenda 3:00 – Brief welcome – Simon Mitchell, Community Manager 3:35 – Project update - Jonathan Hill, Station Manager Karangahape Station 3:45 – Mercury Lane update – Eva Brosius, Section Engineer Mercury Lane 3:50 –Tunnels update – Cam Butcher, Construction Manager Mined Tunnel 3:55 – Beresford Square update – Michael Coup, Senior Project Engineer Beresford 4:00 – Questions 4:10– End

2


Community Mural installs on Mercury Lane and East Street (Moana Wall)

Click to add text

3


Community – First Thursdays

4


Programme and Progress Jonathan Hill • The Karangahape Station site, along with all City Rail Link sites, have ceased construction for a minimum of seven days (from 17 August 11:59pm).

• In this update we will provide you with the latest – pre-lockdown - construction news from Beresford Square, Mercury Lane and the mined tunnels.

5


Highlights • Excavation has been continuing at both Mercury Lane and Beresford Square.

• In Mercury Lane we hit a major milestone with the breakthrough from the station box to the mined pilot tunnel. • The southbound tunnel (MC30) profile is complete, and work is now directed to the northbound tunnel (MC20). It is expected to be completed year end. • Key milestones for Beresford Square were the two concrete pours for B2 and the commencement of excavation from B2 to B3.

6


Station boxes and mined tunnels

7


Mercury Lane • The image shows the entire surface area of the station platform

• The location of the noise enclosoure to the left, will be returned to the property owners when we have completed the station

• The highlighted opening through which we are digging below B2 into the pilot tunnel. This will eventually become the escalator location.

8


Mercury Lane • The image shows the entire surface area of the station platform

• The excavation cavern where we are digging at level B3. This cavern will eventually become the escalator location.

9


Beresford Square • The image shows the entire surface area of the station platform

• The excavation cavern where we are digging at level B3. This cavern will eventually become the escalator location.

10


Beresford Square • In this foreground you can see the temporary openings for our ongoing excavation to level B3.

11


Mercury Lane Eva Brosius, Section Engineer


Key Milestone - breakthrough

13


Key Milestone - breakthrough

14


Key Milestone - breakthrough

15


We have completed L0 / B1 / B2 now and are excavating / rockbolting / shotcreting down to B7

16


17


18


Mined Tunnels Nina Tropina, Engineer Mined Tunnel


Mined tunnels - Excavation work is now complete on the southbound tunnel closest to Mercury Lane

20


Mined tunnels

21


Mined tunnels – Adit 5 with excavation complete to beneath Beresford Square

22


23


24


25


26


Beresford Square Michael Coup, Senior Project Engineer, Beresford


Beresford Square B2 steel fixing

28


29


Key milestone - first two concrete pours for the B2 level and the excavation from B2 to B3 starts

30


Excavation has now begun from B2 to B3

31


32


Beresford B3 Excavation and Blinding

33


Thanks for attending

Please email us if you have further questions Karangahape@linkalliance.co.nz