Community Liaison Group Karangahape Station 26 August 2021
CLG agenda 3:00 – Brief welcome – Simon Mitchell, Community Manager 3:35 – Project update - Jonathan Hill, Station Manager Karangahape Station 3:45 – Mercury Lane update – Eva Brosius, Section Engineer Mercury Lane 3:50 –Tunnels update – Cam Butcher, Construction Manager Mined Tunnel 3:55 – Beresford Square update – Michael Coup, Senior Project Engineer Beresford 4:00 – Questions 4:10– End
2
Community Mural installs on Mercury Lane and East Street (Moana Wall)
Click to add text
3
Community – First Thursdays
4
Programme and Progress Jonathan Hill • The Karangahape Station site, along with all City Rail Link sites, have ceased construction for a minimum of seven days (from 17 August 11:59pm).
• In this update we will provide you with the latest – pre-lockdown - construction news from Beresford Square, Mercury Lane and the mined tunnels.
5
Highlights • Excavation has been continuing at both Mercury Lane and Beresford Square.
• In Mercury Lane we hit a major milestone with the breakthrough from the station box to the mined pilot tunnel. • The southbound tunnel (MC30) profile is complete, and work is now directed to the northbound tunnel (MC20). It is expected to be completed year end. • Key milestones for Beresford Square were the two concrete pours for B2 and the commencement of excavation from B2 to B3.
6
Station boxes and mined tunnels
7
Mercury Lane • The image shows the entire surface area of the station platform
• The location of the noise enclosoure to the left, will be returned to the property owners when we have completed the station
• The highlighted opening through which we are digging below B2 into the pilot tunnel. This will eventually become the escalator location.
8
Mercury Lane • The image shows the entire surface area of the station platform
• The excavation cavern where we are digging at level B3. This cavern will eventually become the escalator location.
9
Beresford Square • The image shows the entire surface area of the station platform
• The excavation cavern where we are digging at level B3. This cavern will eventually become the escalator location.
10
Beresford Square • In this foreground you can see the temporary openings for our ongoing excavation to level B3.
11
Mercury Lane Eva Brosius, Section Engineer
Key Milestone - breakthrough
13
Key Milestone - breakthrough
14
Key Milestone - breakthrough
15
We have completed L0 / B1 / B2 now and are excavating / rockbolting / shotcreting down to B7
16
17
18
Mined Tunnels Nina Tropina, Engineer Mined Tunnel
Mined tunnels - Excavation work is now complete on the southbound tunnel closest to Mercury Lane
20
Mined tunnels
21
Mined tunnels – Adit 5 with excavation complete to beneath Beresford Square
22
23
24
25
26
Beresford Square Michael Coup, Senior Project Engineer, Beresford
Beresford Square B2 steel fixing
28
29
Key milestone - first two concrete pours for the B2 level and the excavation from B2 to B3 starts
30
Excavation has now begun from B2 to B3
31
32
Beresford B3 Excavation and Blinding
33