Communication and Consultation Plan - Addendum

Page 1


Mt Eden Station and Public Realm Reinstatement

Communication and Consultation Plan - Addendum

CRL-MTE-RME-LKA-PLN-800048

Revision: A01

Date: 16 December 2021

Mount Eden Station and Public Realm Reinstatement –Communication and Consultation Plan - Addendum

CRL-MTE-RME-LKA-PLN-800048

Approval Status

1. Introduction

The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line (NAL) in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and the redevelopment of the station at Mt Eden (refer to Figure 1.1). The design and construction of the CRL infrastructure between the Aotea and Mt Eden Stations is being delivered by the Link Alliance.

This addendum to the Mt Eden Station Main Works Communication and Consultation (CCP)1 has been prepared to provide a framework for communications and consultation with stakeholders and the general public during the public realm reinstatement (PRR) phase of the construction works. The same general processes outlined in the Main Works apply to the PRR phase. Accordingly, this addendum should be read in conjunction with the Mt Eden Station Main Works CCP. Where project details, protocols and frameworks are directly applicable to the PRR works, reference is made to the appropriate section of the Mt Eden Station Main Works CCP.

1Mt Eden Main Works Communication and Consultation Plan, prepared by the Link Alliance, Rev 001, dated 29/06/2021, reference CRL-MTE-RME-LKA-PLAN-800033

Figure 1.1 CRL Route and Location

2. Mt Eden Station Public Realm Reinstatement Works

2.1 Overview of works

The extent of the PRR works is shown in Figure 2.1 and includes the Mt Eden Precinct and eastern and western facing connections. An oversite development (OSD) masterplan has been developed for the CRL construction site at Mt Eden which is expected to be delivered by CRLL and Eke Panuku after the works being undertaken by Link Alliance have been completed. The scope of the works being delivered by the Link Alliance, excludes the OSD area (shaded white in Figure 2.1).

Figure 2 1: Extent of the public realm works showing stages of construction reflected in Table 2.1

Generally, the works will consist of:

• Construction of new stormwater

• Installation of utilities

• Construction of tree pits

• Installation of new road pavement

• Installation of new footpath pavements

• Landscaping works

• Installation of street furniture

The PRR works are divided into ‘stages’ (based on activity for the Mt Eden Precinct, and locations for the NAL area) as illustrated in Table 2.1.

Table 2.1. Overview of Construction Works and Staging

North Auckland Line

Stage/Location

Stage 1

Boston Road/Nugent Street/Normanby Road

(East facing connection)

Stage 2

Fenton Street/Wynyard Street

(West facing connection)

Services installation, road reinstatement and landscaping

Footpath/road reinstatement and landscaping

Stage 3A Drainage Drainage works along the roads connecting to existing stormwater network

Stage 3B and 3E Roading works

Stage 3C

works

Stage 3D

pavement, footpath, road furniture and road signals

like LV line for lighting and fiber

paving and way finding installation

A detailed description of the PRR works is provided in the Mt Eden Station and Public Realm Reinstatement Construction Environmental Management Plan (CEMP) Addendum. Detail on the PRR design is provided in the Mt Eden Station and Public Realm Reinstatement Urban Design Delivery Work Plan (Urban Design DWP).

3. Overarching Strategies and Methodologies

There is no change to the overarching strategies and methodologies outlined in Section 3 of the Main Works CCP.

4. Consultation and Communication Strategy

There is no change to the consultation and communication strategy outlined in Section 4 of the Main Works CCP.

Key project messages relating to the PRR works will be developed closer to works implementation.

Mt Eden Precinct

5. Roles and Responsibilities

The key personal responsible for the implementation of the CCP during the PRR works are identified in Table 5.1 below. Contact details for the Mt Eden Station Project Manager, NAL Construction Managers and Communication and Engagement Advisors are provided in Table 5.2.

NAL Construction Manager

Mt Eden Station Project Manager

Systems Manager

NAL Deputy Construction Manager

WFC Project Manager

NAL – EFC2 Project Manager

Utilities Manager

Community Manager

Table 5.2: Link Alliance Contact details

Dale Burtenshaw

Thibaut L’Hopital

Laurent Illoz

Nick Adams

Oscar Reindler

Francois Pageron

Mark Anderson

Helga Sonier

Table 5.1: Key Personnel

6. Communication

Approach

There is no change to the communication approach outlined in Section 6 of the CCP.

The OSD is expected to be delivered after the works being undertaken by Link Alliance have been completed. Stakeholder engagement during the public realm works will ensure there is an aligned communication approach with the parties delivering the OSD In addition to communication channels identified in Section 6.3, the Link Alliance now use QR codes extensively linking to a current calendar of works on the website. This communication channel will continue to be used during the PRR works.

7. Protocols, Processes and Contact Details

There is no change to the protocols and processes as outlined in Section 7 of the CCP.