CRL Connection Newsletter Jan 2016

Page 1

CRL Connection

Looking south along Queen Street from corner of Customs Street showing Auckland’s trams. (Sir George Grey Special Collections, Auckland Libraries, 1-W519)

Early works reveal Auckland’s past

January 2016

Auckland’s old tramway network revealed in Victoria St West. Japanese

もし、 このファクトシートを理解する必要があれば、 下 記のメール経由で我々にご連絡ください。

Russian

While most of Auckland was on holiday enjoying summer, the CRL team were busy locating and shifting services in preparation for the pipejack shafts going in on Swanson and Victoria Streets.

Если Вам необходима помощь в разъяснении содержимого в данном бюллетене, просим адресовать Ваши вопросы на нижеуказанную электронную почту.

Simplified Chinese 如果您对这简报有任何疑问请以下的邮箱联系我们

Working through layers of power and telecommunications services, they came across an unexpected piece of Auckland’s transport history – a section of the city’s old tramway network in Victoria Street West that connected back to Customs Street. “These services are always very dense at the corners of intersections where most are located, so you can never be certain what you’ll find underground,” says Mark Anderson, utilities engineer with the Connectus Consortium, undertaking the work. “Even though we used ground penetrating radar and searched

Korean

본 자료표에 관한 더 많은 정보를 원하시면 하단의 이메일 주소로 연락 주시기 바랍니다.

Arabic ‫ةرشنلا اذه مهف يف ةدعاسم ىلإ ةجاحب تنك اذإ‬، ‫ىجري‬ ‫هاندأ ينورتكلإلا ديربلا ناونع ربع انب لاصتالا‬.

visit our Facebook page www.facebook.com/cityraillink Funding partner:

email CRLproject@aucklandtransport.govt.nz

CRL Newsletter | Page 1


Return to front page

Early works reveal Auckland’s past (continued)

through the city’s service records, we didn’t expect to uncover the old tramway network.” Auckland’s electric trams ran from 1902 to 1956, when they were replaced by trolley buses. Running from downtown at the Waitemata Harbour and across to Onehunga on the Manukau Harbour, they were then the world’s only ‘coast to coast’ tramway system. The tramway section’s discovery on Victoria Street West meant an additional two weeks work, with the pipejack shaft hoardings now being installed late February. Shifting the services is made more complex by the need to ensure 900mm ground between the services and the roof of the future Aotea Station,

which will be just 1200mm from the surface. “It’s a very thin layer in which to fit everything,” says Anderson. The trenching needed at Swanson and Victoria Streets’ intersections with Albert Street was completed during the Christmas holiday period when traffic was quiet. Noise protection reduced the decibel level by 10 to 15 percent and noise monitoring will continue until work is finished. Now that people are returning to work, congestion is increasing on Victoria Street West where the next step is to widen the traffic carriageway on the south-side to accommodate a traffic lane in each direction.

Early works construction Orakei Main Sewer strengthening Victoria Street West (Mai Thai corner) Construction hoardings up for approx. 10 months February 2016

March 2016

Service relocation / construction starts

Traffic reduced to one lane each way for the duration of the work

Final hoardings erected

Excavate shaft

July 2016

• TBM enters shaft and travels below Albert Street to Victoria Street West (Surf and Snow corner) to strengthen sewer

May – December 2016

Shaft filled

January 2017

Road re-opened to traffic

email CRLproject@aucklandtransport.govt.nz

CRL Newsletter | Page 2


Return to front page

Early works construction (continued) Stormwater pipe construction schedule (approx.) Victoria Street West (Surf and Snow corner) Construction hoardings up for approx. 14 months •

Service relocation / construction starts

Traffic reduced to one lane each way for the duration of the work

March – May 2016

Hoardings, gantry and acoustic shed erected

June – July 2016

Excavate shaft

September – November 2016

TBM enters shaft and travels below Albert Street to Swanson Street

November 2016 – January 2017

TBM re-enters shaft and travels below Albert Street to Wellesley Street

December 2016 – May 2017

Shaft filled

Hoardings removed

Road re-opens to traffic

January – February 2016

May 2017

Swanson Street (New Zealand Trade Centre corner) Construction hoardings up for approx. 4.5 months (split; 1.5 months and 3 months) February – March 2016 September 2016

October 2016 December 2016 January 2017

Hoardings erected

Excavate shaft

Shaft closed up and hoardings removed

Road partially re-opens to traffic

Hoardings re-erected

Road closed, footpath remains open to pedestrians

TBM removed from shaft

Shaft filled

Hoardings removed

Road re-opens to traffic

Wellesley Street West (Central City Hotel corner) Construction hoardings up for approx. 11 months •

Road cones placed for investigation work

Electronic traffic signs warn of lane changes

Hoardings erected

Excavate shaft

December 2016

TBM received and removed from shaft

March 2017

Shaft filled

Hoardings removed

Road re-opens to traffic

March 2016 April 2016

April 2017

email CRLproject@aucklandtransport.govt.nz

CRL Newsletter | Page 3


Return to front page

Connectus Consortium Bob Mawdsley, engineering manager with the Connectus Consortium delivering Contract 2 of the City Rail Link, has a strong connection to the city’s rail network. Roll back the clock 15 years and he was managing the engineering on Britomart Station for Downer Engineering. In the early 2000s, Britomart was Auckland’s largest transport project ever, just as the CRL is today. Connectus, a joint venture of McConnell Dowell Construction and Hawkins Infrastructure Limited, are constructing the cut and cover tunnels under and along Albert St from Customs St to Wyndham St.

Newmarket Rail Station, a Hawkins Infrastructure project

“Between our two companies we have enormous expertise and capacity in civil engineering and building as well as micro-tunnelling,” says Bob. Bob has worked with the Well-Connected Alliance as Temporary Works Design Manager on the Waterview Connection motorway tunnels. The $1.4billion project tunnelled 4.8km of motorway underground using ‘Alice’, a 3,600 ton, 14.5 m diameter tunnel boring machine (TBM). The twin tunnels, at depths between 10m and 45m, are the largest diameter tunnels to be built in Australasia, and the 11th largest TBM used to date worldwide. McConnell Dowell also designed and constructed the Rosedale Waste Water Treatment Ocean Outfall, a 3km marine pipeline that discharges highly treated effluent into the Rangitoto Channel. Stretching from the treatment plant to Mairangi Bay, it runs deep beneath streets, parks, reserves and properties before going under the seabed 2.8km out into the channel. By simplifying and straightening the route for the western part of the outfall, McConnell Dowell enabled the land-based portion to be at least 25 metres underground, making it much less disruptive to Mairangi Bay residents and businesses.

Water sprays out of the Alice TBM as it breaks through into the tunnel portal.

Hawkins Infrastructure, and their company Harker Underground who are pipejacking the new stormwater line along Albert Street, are also leading experts in underground tunnelling, pipelines and shaft construction. Employing a range of specialist skills, from general earthworks and civil engineering to geotechnical engineering, their projects include the Auckland Rail Electrification Project, Newmarket Rail Station, and the Point Resolution Bridge crossing Tamaki Drive. “It’s great to see the City Rail Link becoming a reality, and to know the early works we are doing now will lay the essential foundation for its construction,” says Bob.

email CRLproject@aucklandtransport.govt.nz

CRL Newsletter | Page 4


Return to front page

Signals go green for 2018 start

The Government has confirmed it intends to commit to funding for the City Rail Link. Auckland Council says this would allow construction of the main works to start in 2018. The Government’s

announcement has been driven by strong growth in rail patronage and the need to provide investment certainty for large-scale developments in the CBD.

Please sign me up to the CRL Early Works Newsletter email list.

email CRLproject@aucklandtransport.govt.nz

CRL Newsletter | Page 5


Return to front page

Traffic delays ahead, make a travel plan

The Build is On campaign starts in February with extensive advertising in newspapers and radio, Google videos and a travel planning website. For motorists coming into the city, there’ll be road works, fewer on-street car parks and traffic flows will be slower. Now is the time to think smart about how to travel into the city. Consider carpooling, catching the bus, train or ferry, walking or cycling. You could even think about changing the hours you work, or work from home some days. AT has reconfigured bus routes and created new bus lanes, with more changes happening from April 17th when buses are moved out of Lower Queen Street in preparation for the CRL early works.

Auckland Bike Challenge – Fit in Feb Auckland workplaces are embracing a bike friendly Auckland and staff well-being with the Auckland Bike Challenge – a fun online event. 102 workplaces and more than 1,000 employees, are already on board with numbers rising daily. Open to all businesses in Auckland, it’s especially relevant to those affected by the CRL early works. Bike anytime, anywhere for at least 10 minutes during February and encourage others to do the same. Register at www.lovetoride.net/auckland (there’s a nifty app to download too). Check out the AT Great Rides for some inspiration or try an AT Summer Cycle Course.

Consider carpooling AT has made 15 car park spaces available to carpoolers on Level 8 of the Downtown Carpark. These spaces can be leased from AT for 10% less than a regular car park space if three or more people share the car (1 driver plus 2 passengers carpool) to the CBD. For more information about how to lease a carpool space visit www.at.govt.nz/carpoolspaces

email CRLproject@aucklandtransport.govt.nz

CRL Newsletter | Page 6


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.