CRL Connection
May 2016
Britomart Station. Image by Taylor Cullity Lethlean and Boffa Miskell
New station designs showcased
Japanese
もし、 このファクトシートを理解する必要があれば、下記のメール経由で我々にご連絡ください。
Russian
The latest CRL station and public realm concepts are being showcased on Lower Queen Street’s western side for the next month. They will provide an attractive backdrop to the street’s activation programme, which is starting gradually and expected to build to a peak by early summer. Over the next few weeks we are gradually ‘dressing’ the street with flexible infrastructure – in the transition from construction to our activation programme.
Если Вам необходима помощь в разъяснении содержимого в данном бюллетене, просим адресовать Ваши вопросы на нижеуказанную электронную почту.
Simplified Chinese 如果您对这简报有任何疑问请以下的邮箱联系我们
Korean
본 자료표에 관한 더 많은 정보를 원하시면 하단의 이메일 주소로 연락 주시기 바랍니다.
Arabic ةرشنلا اذه مهف يف ةدعاسم ىلإ ةجاحب تنك اذإ، هاندأ ينورتكلإلا ديربلا ناونع ربع انب لاصتالا ىجري.
Recording the CRL for posterity Most large infrastructure projects are digitally recorded for future generations, and the CRL is no exception. We have engaged a company to produce time-lapse photography of the construction, and will later produce a series of videos. Keep an eye on our Facebook page to see its journey recorded: www.facebook.com/cityraillink
Image of Victoria Street West pipejack works by Big Fish
Funding partner:
website AT.govt.nz/CRL email CRLproject@AT.govt.nz
visit our Facebook page www.facebook.com/cityraillink
CRL Newsletter | Page 1
Return to front page
CRL: Britomart to Wyndham St Pedestrian and cyclist access always maintained.
Mid-late May •
Main piling machine arrives on site
•
Billboard skins installed on hoardings
•
Project signage goes up on the pedestrian side
•
ignage supporting local businesses goes up with: “Victoria Street shops open for S business as usual” panels on the hoardings
•
Piling starts to construct the vertical shaft
Victoria Street West (adjacent to Mai Thai)
•
Piling completed
•
Shaft excavation work begins
Wellesley Street West
•
Utility diversions complete
(corner Albert Street)
•
Re-establishment at shaft late June
•
Utilities works for Chorus starts
•
Re-establishment at shaft in July
•
Utility diversions affecting some lanes
•
Trading closes 29 May
•
Ongoing clearance work in QE Square
•
I n early July, construction starts on a large acoustic shed, over the lower Victoria Street site to minimise noise from the vertical shaft. It remains in place for the duration of drilling until mid-2017
•
In June, demolition of DSC commences.
Victoria Street West (adjacent to bungy site)
Swanson Street East
Customs Street Intersection
Downtown Shopping Centre (DSC)
Looking ahead
Barnes dance AT has changed the traffic crossing to a Barnes Dance at the Customs and Albert Street intersection. This allows pedestrians to cross diagonally, creating safer pedestrian movement and more efficient crossing times, which also improves traffic flows.
website AT.govt.nz/CRL