Waitemata Station Presentation December 2022

Page 1

Waitematā Station (Britomart) Community Liaison Group

December 2022
2 Agenda • Welcome + Intro – Nicole Lawton, CRL Stakeholder Communications Manager • Neighbouring projects – Oliver Smith, Auckland Council Delivery Programmes Manager • Milestones & Updates – Aruna Mylvaganam, Link Alliance Construction Manager • Milestones & Updates – Nigel Lambourne, Martinus Project Manager • Britomart Place programme – Jonathan Dudman, CRL Construction Manager • Rail Network Shutdowns – Ed Newbigin, Auckland Transport Principal Planner Customer Engagement • Neighbouring projects – Jeremy Hansen, Britomart Group Ccommunications and Community Director
Introduction
4 Introduction
MC30 Tunnel MC20 Tunnel Introduction

Neighbouring projects

Upcoming Quay Street works Complete Dec 2020 Complete May 2021 Urban Realm Deferred Plaza Works Deferred
- Auckland Council • Galway Street shared space redevelopment • Te Wānanga planter •
Milestones – Link Alliance Top milestones completed 2022 • Station Control Room constructed and made available for Link Alliance as scheduled - April 2022 • B1 rooms (Station managers room, operators room, kitchen and quiet room ), temporary operations room, and B2 toilets constructed and handed over to AOR - April 2022 • Demo completed on MC 30 and MC 20 and handed over to Link Alliance to commence concreting and track installation – MC 30 in Sept 2022 and MC 20 in July 2022 • Laying of the skeleton track – MC20 - September 2022 • Completed track MC20 – October 2022 • Completed Laying and concreting track MC30 – November 2022 Top milestones for 2023 • Complete base build and make all west (B2) end rooms available for systems fitout - January 2023 • Complete smoke screen at West end, base build civil/architectural for east end rooms - March 2023 • Complete base build and make all east end rooms available for systems fitout - August 2023 • Complete OHLE in MC20 and MC30 – December 2023 • Connect Waitematā and Te Waihorotiu rail way track – July 2023

Britomart Station Control Room (SCR)

Update
Link Alliance
Britomart Basement 1 works – completed in 2022 Basement 1 works that have been completed and handed over to AOR (Auckland One Rail): • Station Control Room (SCR), • Station managers room • Train crew management room
Kitchen
Quiet room
Operations room

Update – Link Alliance

Bluestone work on South wall Preparation for Terrazzo pour Britomart Phase 2 works Bluestone work on South wall

Alliance

Britomart East works

Preparation for floor 1 Preparation for floor concreting Scupper drain in LRT Update – Link
Update – Link Alliance (systems works) Works planned for 2022 • Stage 2 track in MC20 & MC30 tunnels is now largely complete • Installation for overhead Line electrification in MC20 nearly complete • Installation for overhead Line electrification in MC30 will be complete by Dec 2022 • Primary cable containment Works planned for early next year in tunnels • Connect Waitematā and Te Waihorotiu Stations railway track • Concrete (stage 3) for walkways and outside drainage channels between Jan and April 2023 • Cable running, secondary containment and fire systems later in the year, connecting into systems rooms • Systems fit-out signalling, traction power, communications and lighting/power • Complete OHLE in MC20 and MC30 – in readiness for energisation

Milestones - Martinus

Top

milestones completed 2022

• Completed the construction of the new south wall to Britomart tunnel.

• Installed temporary structures to ensure stability of the old wall during the demolition period.

• Excavated down through the existing surface area on the corner of Scene Lane/Britomart Place.

• Installed beam and wall strengthening, and re-established structure; installed panels; precast lid placed over surface works pit.

• With over 50,000 manhours on this project, it’s all been carried out to date with no safety incidents.

Top milestones for

2023

• Complete all surface works up to ground level, and commence with final landscaping finishes at Britomart Place.

• Demolish the old south wall during the Christmas rail network shutdown (Block of Line).

• Complete the final completion items of the new south wall once demolition is complete.

• Commence track improvement works from Platform 1.

• And of course, continue with an excellent standard of safety management and control.

Surface Works - Progress last 3 months

Excavating down to the tunnel lid
Excavation complete exposing existing waste-water line Wall strengthening works complete

Surface Works - Progress last 3 months

Lifting precast concrete slabs into placeachieved on time, despite delays occurred earlier in project

Reinforcing

being placed for slab pour

Concrete topping slab complete

South Wall - Progress last 3 months

Completion of New South wall structure

South wall scaffold removed, preparing to install tie beams Last tie beam installed

South Wall Progress - last 3 months

Drilling old wall for bolting of stabilisation plates Installing further stabilisation plates, trackside during Block of Line

Torquing several hundred bolts to engineer’s requirements

SAFETY STOP, REFLECT AND RESET

• Approaching the busiest time for rail. Every day we make sure our Martinus whānau gets home safely to their families.

• Our new “What’s your Reason?” initiative further reinforces safety as a key focus.

• Hazard identification refresher session: stopping, reflecting and resetting. Feedback safety improvement suggestions.

Britomart Place programme – Jonathan Dudman

Martinus Rail and Link Alliance have been occupying part of Britomart Place and Scene Lane for works to:

• Strengthen the roof of the underlying railway tunnel (enabling rearrangement of walls and tracks within the tunnel)

• Reconfigure underground equipment rooms at the eastern end of Waitematā Station (Britomart)

Works in Britomart Place / Scene Lane

• The above ground works (excluding the streetscape reinstatement) will be completed by early April 2023.

• During the latter stages of the works, and as Martinus and the Alliance progressively demobilise (removal of construction support areas, hoardings etc.), permanent reinstatement of the Britomart Place/Scene Lane streetscape will commence.

• The streetscape reinstatement is programmed to be completed by the end of May 2023.

The following slides illustrate the sequence of events:

Britomart Place / Scene Lane – End of May 2023 to January 2024

• Streetscape reinstatement completed (end of May).

• Martinus continues to occupy former ‘China Restaurant’ premises as a site office.

• Construction worker access (as shown).

• Intermittent concrete deliveries expected throughout the year.

Rail Network Shutdowns

• The whole rail network will be closed during this period. • No commuter trains will be operating.

Auckland Transport & KiwiRail 26 December 2022 to 15 January 2023
• Extra buses will be added to enable travel. Christmas shutdown – Regular Holiday Maintenance

Rail Network Rebuild

January 2023 - 2025

• Replacing the aging foundations under Auckland’s rail tracks and improving drainage

• This vital upgrade will be completed one section at a time over the next three years.

• While one section is being worked on, the rest of the train network will keep running.

Rail Network Rebuild

Stage 1: 16 January - 19 March 2023

• Remuera, Greenlane, Ellerslie, Penrose, Te Papapa, Onehunga stations will be closed

• All other stations remain open

• All trains to South Auckland will run via Glen Innes and Panmure

• Extra buses will be added to enable travel

Next stages March to late 2023: (yellow section): • Ōrākei, Meadowbank, Glen Innes, Panmure, Sylvia Park closed 2024: Western Line and sections for Southern Line • Details to be confirmed 26 Rail Network
Rebuild

Neighbouring projects

Questions?