Waitematā Station CLG Agenda • Welcome + Intro – Alex Vaineritua, Senior Stakeholder and Communications Advisor

• Works update from Link Alliance – Aruna Mylvaganam, Construction Manager • Works update from Martinus – Simon Lough, Design Manager Urban Realm

• Waitematā Station Plaza - Alex and Simon • Any questions?


City Rail Link Project Update • Project on track to achieve practical completion in November 2025, and opening to the public expected in 2026 • There will be a significant period of testing and commissioning before opening, with little disruption above ground • Currently, the project is in architectural elements, station fitouts, streetscapes and systems installation phase

• The first of the two 3.45km tracks has been laid through the City Rail Link, connecting Waitematā Station (Britomart) with Maungawhau Station


Waitematā West • Platform, lift & bluestone modifications in the final stages – to be completed by Q1 2024

• After this, all handover documentation will be complete

Waitematā East • All Appendix 26 works are complete, except installation of the fire ceiling (completed by midDecember) • Handover documentation underway with final Auckland Council inspection & sign-off by January 2024 • Signalling cabling now being installed by Siemens


Tunnels between Waitematā and Te Waihorotiu stations • Lots of low voltage & communications cables being pulled


Waitematā Station Works Milestones achieved in last 3 months • • •

New overhead lines installed Completing cable containment works, signal ducting and inspection pits in the tunnels During BOLs (Block of Lines): • removal and installation of new track • removal of ballast • realignment of track and overhead power • installing new hoardings and barrier rails between track 4 and 5 • concrete pour to the new track 5 • and extension to Platform 5. Continued with an excellent standard of safety management and control with over 100,000 safe working hours in the last year

Removal of Track 5 and ballast during the Block of Line

Overhead track power alignment on track four


Waitematā Station Works Planned for the next 3 months • • • • • • •

Complete platform extension to Platform 5 Complete track and slab to Road 5 for handover (end of December) Continue track improvement works for the Waitematā tunnel Complete cable containment and ducting works for the new signalling system Commence new traction power works requirements Civil works to allow the installation of the new points machines Realignment works to Roads 1, 3 and 4

Track install to Road 5



Waitematā Station Plaza Temporary station deconstruction and reinstatement

Share designs and discuss construction process with neighbours and stakeholders

Nov–Dec. 2023

CRL deconstructs temporary structure and vacates the plaza

Dec–Jan 2023

Jan–Mar 2024

Auckland Transport prepare the site for deconstruction e.g. capping services

Apr 2024 – early/mid 2025

Auckland Council undertake physical works to reinstate the station plaza and upgrade Tyler Street


Sequence of Work General site layout from 22/1/24

Questions?


General layout plan Logistics control • The site area will be fully fenced to all boundaries using block and mesh type temporary fencing with debris scrim attached • Scaffolding will be provided for access to remove cladding sheets to both East and West elevations. The scaffolding will be covered in debris scrim to protect both public and adjacent buildings from the materials being removed • Crane access to the site will mainly be from Tyler Street, but about 30% will need to be accessed from Galway Street. • Majority of materials will be loaded out through Tyler St side, except single storey building on Galway street.


Site cleared for handover to streetscaping From 1/4/2024 • The existing building will be removed down to the existing paving surface level. Leaving the entrance canopy intact, ready for any follow-on works. (1/4/24) • Existing ventilation shafts and stair egress buildings are to remain in place • The site temporary fencing around the site will also remain in place for the following streetscape contractor works.