Karanga-a-Hape CLG presentation December 2022

Page 1

Community Liaison Group

Karanga-a-Hape Station (Karangahape)

15
December 2022

Meeting Agenda

5:30

Welcome and community engagement update – Simon Mitchell, Community Manager

5:40

5:50

Mercury Lane – Jonathan Hill, Project Manager, Karanga-a-HapeStation

Mined Tunnels – Jonty Duncan, Project Engineer, Mined Tunnels

BeresfordSquare – Emmanuel Chatoux, Project Engineer, Beresford Square 6:10

6:00

Progressin 2022 and a look ahead

Jonathan Hill, Project Manager, Karanga-a-Hape Station 6:20

2
Discussionand questions 6:30
End

Community Engagement

3

Community Engagement Jan – March (while still in lockdown...

4
)

Community Engagement April - June

5

Community Engagement July – Sep

6

Community Engagement Oct – Dec

7
8
Engagement – year in review figures Compliments: 180 Complaints: 29 Number of events: 143 Small Business Support Package: 100% (15/15)
Community

Mercury Lane

9
Jonathan Hill, Station Manager, Karanga-a-Hape Station

Mercury Lane – Dec '22

View from B7 Looking Northwest.

View from B7 showing internal walls, perimeter walls and columns supportingthe completed B4 Suspendedslab.

Steel columns are temporary and due to be removed Q1 2023.

10

B7 Track Slab looking South. Drainage complete reo started.

From B7 looking up with Superstructure visible above.

11
Mercury Lane – Dec '22

Mercury Lane

Dec '22

View from B2 looking west, Showing completed B4 slab, and "stadium"columns with steel fixing underway.

12
13
– Dec
Mercury Lane
'22 View from B4 – RC Connections to B2 ongoing Block Walls from B1 to L0.

Mined Tunnels

Jonty Duncan, Project Engineer, Mined Tunnels

14

Mined Tunnels – MC32

15
Sept 22 Secondary lining and headwall complete.

Mined Tunnels – MC32

3 different profile types, 3 form modifications

16

Mined Tunnels – MC30

Sept 22 Looking North to Te Wai Horotiu Station (Aotea)

17

Mined Tunnels – MC30

OTE slab construction

18
19 Mined Tunnels – MC30 Looking South to Maungawhau / Mt Eden Station Sept 22 1 more PT1 pour (Friday), Modify form, two PT2 pours
20
Sept 22 Drainage, B7 StructuralSlab, Service Conduits
Mined Tunnels – Adit 3
21
Sept 22 Drainage, B7 StructuralSlab, Service Conduits
Mined Tunnels
Adit 4
22
Tunnels – MC20 Drainage, B7 StructuralSlab, OTE Slab Construction
Mined

Mined Tunnels – Adit 2

23
Sept 22

Mined Tunnels – MC31

Two pours after Christmas to complete secondary lining.

24

Mined Tunnels – Adit 1

Secondary Lining complete for east, ongoing in the west

August 22

25

Mined Tunnels – Cross Passages

Saw cut openings to MC20 for all XP's. Portals remaining.

26

Beresford Square

Emmanuel Chatoux, Project Engineer, Beresford Square

27

Beresford

28
intoAdit 4 Ducts installation under concourse level Preparation of the train track and platform area
Square – General View

Beresford Square – General

29
Spine wall construction Spine wall construction Tunnel portals
30
– Formwork Lift wall formwork Lift pit shoring Letterboxes
Beresford Square

Progress in 2022 and a look ahead

31

Progress – TBM at Karanga-a-Hape July 2022

32

Progress in Mercury Lane

33
February – B7 March
Dec
Dec
2022
2021 May 2022
2022

Progress in Mercury Lane continued

34
May 2022 December 2022
35 Superstructure – Level 2 and Level 3 L2 Steel fixing, pour before Christmas L3 Composite Flooring installation, pour after Christmas

Superstructure – December 2021 vs. December 2022

36

Progress highlights Beresford Square

39
April 2022 - B7 Dec 2021 – B4 excavation August 2022 December 2022

December 2021 vs. December 2022

40
41

Discussion and questions

44
45 Please email us if you have further questions Karangahape@linkalliance.co.nz and Merry Christmas! Thank you for attending

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.