Community Liaison Group
Karanga-a-Hape Station (Karangahape)
15
December 2022
Meeting Agenda
5:30
Welcome and community engagement update – Simon Mitchell, Community Manager
5:40
5:50
Mercury Lane – Jonathan Hill, Project Manager, Karanga-a-HapeStation
Mined Tunnels – Jonty Duncan, Project Engineer, Mined Tunnels
BeresfordSquare – Emmanuel Chatoux, Project Engineer, Beresford Square 6:10
6:00
Progressin 2022 and a look ahead
Jonathan Hill, Project Manager, Karanga-a-Hape Station 6:20
2
–
–
–
–
–
–
–
–
Discussionand questions 6:30
End
Community Engagement
Simon Mitchell, Community Manager
3
Community Engagement Jan – March (while still in lockdown...
4
)
Community Engagement April - June
5
Community Engagement July – Sep
6
Community Engagement Oct – Dec
7
8
Engagement – year in review figures Compliments: 180 Complaints: 29 Number of events: 143 Small Business Support Package: 100% (15/15)
Community
Mercury Lane
9
Jonathan Hill, Station Manager, Karanga-a-Hape Station
Mercury Lane – Dec '22
View from B7 Looking Northwest.
View from B7 showing internal walls, perimeter walls and columns supportingthe completed B4 Suspendedslab.
Steel columns are temporary and due to be removed Q1 2023.
10
B7 Track Slab looking South. Drainage complete reo started.
From B7 looking up with Superstructure visible above.
11
Mercury Lane – Dec '22
Mercury Lane
Dec '22
View from B2 looking west, Showing completed B4 slab, and "stadium"columns with steel fixing underway.
12
–
13
– Dec
Mercury Lane
'22 View from B4 – RC Connections to B2 ongoing Block Walls from B1 to L0.
Mined Tunnels
Jonty Duncan, Project Engineer, Mined Tunnels
14
Mined Tunnels – MC32
15
Sept 22 Secondary lining and headwall complete.
Mined Tunnels – MC32
3 different profile types, 3 form modifications
16
Mined Tunnels – MC30
Sept 22 Looking North to Te Wai Horotiu Station (Aotea)
17
Mined Tunnels – MC30
OTE slab construction
18
19 Mined Tunnels – MC30 Looking South to Maungawhau / Mt Eden Station Sept 22 1 more PT1 pour (Friday), Modify form, two PT2 pours
20
Sept 22 Drainage, B7 StructuralSlab, Service Conduits
Mined Tunnels – Adit 3
21
–
Sept 22 Drainage, B7 StructuralSlab, Service Conduits
Mined Tunnels
Adit 4
22
Tunnels – MC20 Drainage, B7 StructuralSlab, OTE Slab Construction
Mined
Mined Tunnels – Adit 2
23
Sept 22
Mined Tunnels – MC31
Two pours after Christmas to complete secondary lining.
24
Mined Tunnels – Adit 1
Secondary Lining complete for east, ongoing in the west
August 22
25
Mined Tunnels – Cross Passages
Saw cut openings to MC20 for all XP's. Portals remaining.
26
Beresford Square
Emmanuel Chatoux, Project Engineer, Beresford Square
27
Beresford
28
intoAdit 4 Ducts installation under concourse level Preparation of the train track and platform area
Square – General View
Beresford Square – General
29
Spine wall construction Spine wall construction Tunnel portals
30
– Formwork Lift wall formwork Lift pit shoring Letterboxes
Beresford Square
Progress in 2022 and a look ahead
Jonathan Hill, Station Manager, Karanga-a-Hape Station
31
Progress – TBM at Karanga-a-Hape July 2022
32
Progress in Mercury Lane
33
February – B7 March
Dec
Dec
2022
2021 May 2022
2022
Progress in Mercury Lane continued
34
May 2022 December 2022
35 Superstructure – Level 2 and Level 3 L2 Steel fixing, pour before Christmas L3 Composite Flooring installation, pour after Christmas
Superstructure – December 2021 vs. December 2022
36
Progress highlights Beresford Square
39
April 2022 - B7 Dec 2021 – B4 excavation August 2022 December 2022
December 2021 vs. December 2022
40
41
Discussion and questions
44
45 Please email us if you have further questions Karangahape@linkalliance.co.nz and Merry Christmas! Thank you for attending