Community Liaison Group Karangahape Station 24 March 2022
Meeting Agenda 3:00 – Welcome and Community Engagement – Simon Mitchell, Community Manager 3:10 – Mercury Lane – Eva Simpson, Project Engineer, Mercury Lane 3:20 – Mined Tunnels – Jonty Duncan, Project Engineer, Mined Tunnels 3:30 – Beresford Square – Michael Coup, Senior Project Engineer, Beresford Square 3:40 – The Year Ahead – Jonathan Hill, Project Manager, Karangahape Station 3:50 – Discussion and questions 4:00 – End 2
Community Engagement Simon Mitchell, Community Manager
3
Quarterly Stakeholder Satisfaction Survey Report Our quarterly survey measures things such as preferred communication channels, helpfulness and engagement.
The satisfaction rate from February was recorded at 79%, up 1% from the survey in November 2021.
4
Community Engagement – December / January 2022
5
Community Engagement – February / March 2022
6
Community Engagement – Upcoming events Return of First Thursdays and the Beresford Square market
7
Mercury Lane Eva Simpson, Project Engineer, Mercury Lane
8
Mercury Lane - Completion of Drainage - Dec '21
9
Mercury Lane - Construction of B7 Slab – Jan / Feb '22
B7 – Eastern Phase
10
Mercury Lane - Construction of B7 Slab – Jan / Feb '22 B7 – Central Phase
Reinforcing Install
Concrete Complete
11
Mercury Lane – Commence Wall Construction – March '22
12
Mercury Lane – Continue Wall Construction – March '22
13
Mined Tunnels Jonty Duncan, Project Engineer, Mined Tunnels
14
Mined Tunnels – Completion of excavation works in December 2021
15
Mined Tunnels – MC30 TBM False Segment Removal, Drainage, Permanent Lining
16
Mined Tunnels – Adit 2 Waterproofing, Reinforcement, Permanent Lining
17
Mined Tunnels – Adit 3/Adit 4 Waterproofing, Reinforcement, Permanent Lining
18
Mined Tunnels – Adit 5 Waterproofing, Reinforcement, Permanent Lining, Formwork Assembly
19
Mined Tunnels – MC20 Waterproofing, Permanent Lining, Formwork Assembly
20
Mined Tunnels – MC21 Waterproofing, Reinforcement, Permanent Lining
21
Mined Tunnels – MC21 Waterproofing, Reinforcement, Permanent Lining
22
Beresford Square Michael Coup, Senior Project Engineer, Beresford Square
23
Beresford Square – January '22 2
- Western Section of the station slabs complete
1
- Wall Construction Underway
1 – B3 Ventilation Room
2 – Blockwalls at B1
24
Beresford Square – February '22 - B4 Slab Complete
3
- B5 to B7 Excavation, Bolting and Shotcrete begins 3 – B5-B7 Excavation
4
4 – B5-B7 Rockbolting
25
Beresford Square – March '22 - Breakthrough from station box to mined tunnels - Breakthrough from station box to MC20 tunnel
Mined tunnel breakthrough 10 March
MC20 tunnel breakthrough 14 March
26
The Year Ahead Jonathan Hill, Station Manager
27
Look ahead – Mercury Lane - Construction of Mercury Lane Superstructure to commence in May 2022
28
Look ahead – Tunnelling - Transit of the Tunnel Boring Machine through Karangahape Station in mid-2022 on its journey to Aotea Station - Tunnel fit out
29
Look ahead – Beresford Square - Complete excavation of Beresford Square entrance and commence internal structures; MEFH, ventilation stack - Towards the very end of the year
30
Discussion and questions
31
Thank you for attending Please email us if you have further questions