Maungawhau CLG Link Alliance meeting March 2023

Page 1

1 March 2023
Maungawhau / Mount Eden Station Community Liaison Group Meeting

1. Communications & Engagement

– Community events & initiatives

2. Construction updates

– Maungawhau / Mount Eden Station Main Site and Mined Tunnels

– Architecture –

North Auckland Line and Tunnels Fit-out

– Systems and Track

3. Questions & Answers

2
Agenda

Helga Sonier

Maungawhau/Mount Eden Station

3
Community Manager

Communications and Engagement Update

Events & initiatives

• Successful Christmas Block of Line with C&E initiatives: Mr Whippy, coffee carts, and movies in Te Manawa supporting significant construction outcomes.

• Upcoming Videos – Escalator install, Station building waterwall, Aroha in Uptown, and January Drone footage is live.

• Revised ArtWalk brochures now in the CRL Visitor Centre at Te Manawa.

• Info Hub and Perimeter tours

• Aroha in Uptown Festival 2023 – Working with Uptown.

• 2023 Eating and Social guide in production.

4

Thibaut L'Hopital

Maungawhau/Mount Eden Station

Project Manager

5

Maungawhau/Mount Eden Site - Construction Update

• Fenton Street Bridge span was successfully lifted over the Christmas Block of Line.

• Station Building concrete panels are all installed for the 'Front' and 'Back of House'.

• Roof structure for the Ventilation Building is being installed.

• First set of escalators for the Station have been installed on the Western Line platform.

• Installed the stairs and lift shaft structure for CRL platform and will begin installing the overpass structure.

• Concreting work continues in the MC50 tunnel.

6

Maungawhau/Mount Eden Site - Construction Update

7

Maungawhau/Mount Eden Site - Construction Update

8

Maungawhau/Mount Eden Station - Construction Update

9

Maungawhau/Mount Eden Station Site - Construction Update

10

Mined Tunnels Update

• Mined Tunnelling team have completed work in the MC30 tunnel.

• Team are working in the MC20/50 cavern with concreting works, formworks, and waterproofing works.

• All mined tunnelling activity is expected to be completed in May 2023.

11
12
Nicholas Powell Maungawhau/Mount Eden Station Architecture Project Manager -

What do we do?

• The team delivers Architectural scope for the Maungawhau Station Building and Ventilation Building, as well as the North Auckland Line and City Rail Link platforms.

13
Intro
Maungawhau/Mount Eden Architecture –

Maungawhau/Mount Eden Architecture - Update

• Glass façade panels have been installed on the Western Line platform canopy and Station Building overpass.

• The installation of the Waterwall feature in the Station Building has commenced.

• All 53 lava coloured glass triangles have been created and will be placed into the waterwall feature at the end of this year.

14

Maungawhau/Mount Eden Architecture - Update

15

Maungawhau/Mount Eden Station Architecture - Update

16
17
Nick Adams Construction Manager – North Auckland Line & Tunnels

North Auckland Line (NAL) - Construction Update

• Normanby Road Bridge is complete and opened to the public at the end of December 2022.

• Remaining works within Boston Road (west)/Normanby Road currently being completed then follow-on with Boston Road (east) works.

• Mt Eden Road drainage installation to be completed end of March then reinstatement works along eastern side of road. • Porters Avenue Bridge elevators installed; outstanding works being completed.

• Porters Avenue streetscapes are progressing including work on new footpaths, kerbing, and road resurfacing.

• Haultain Street/Fenton Street streetscape works to follow-on once Porters Avenue completed.

18

North Auckland Line (NAL) - Construction Update

19

North Auckland Line (NAL) - Construction Update

20

Tunnels Fit-out Update

• Fit-out works consist of pouring 'foundation' concrete for rail track along with installing cable support brackets and emergency walkways.

• Fit-out works for MC30/60 (Maungawhau to Karangahape) largely complete and track installation underway.

• Fit-out teams working in various areas of the tunnels.

21

Tunnels Fit-out Update

22
23
Laurent Illoz Systems Manager – North Auckland Line & Tunnels

Systems and Track Building - Update

• Over Christmas Block of Line, completed work on the overhead lines and tracks for the second Western Line track (MC40).

• Once signal installation and repair work is complete, MC40 track will be comissioned in Easter Block of Line. Dual line running will restart soon after

• Track building in the MC60 tunnel towards Karanga a Hape, including deliveries of rail and blocks.

• Upcoming Blocks of Line are 4 & 11 March, 1-3 April, Easter 6-11 April.

24

Systems and Track Building - Update

25

Systems and Track Building - Update

26

Questions & Answers

27

Stay in touch with questions or feedback

• Email the Maungawhau / Mount Eden Station team at mteden@linkalliance.co.nz

• 0800 CRL TALK – choose option 5 for Maungawhau / Mount Eden Station

• City Rail Link website www.cityraillink.co.nz