Maungawhau CLG Presentation August 2023

Page 1

Maungawhau Station

Meeting
August 2023
Community Liaison Group
23

1. Communications & engagement update

2. Construction updates – Architecture – Maungawhau Station –

North Auckland (Western) Line – Systems and Track

3. Social Impact & Business Disruption Annual Report

4. Fenton Street Bridge

5. Questions & answers

3
Agenda

Communications & Engagement

• Return to dual tracks on the Western Line -

10 July

• New mural and scrim around site

• Site tours, perimeter tours and information hub

• New renders with local icons

• Mined Tunnels celebration

• Building structures celebration

4

New station renders

5
6
7

Communications & Engagement

Coming up:

• North Auckland Line completion

• Special event – September 24th

• Information Hub & launch of new station brochure -

September

• Branch Out Festival with Uptown Business Association –

7 October

• Backfill celebration - November

8

Maungawhau Station Architecture

Project Manager

9
Nicholas Powell

Maungawhau architecture update

• CRL Platform glass curtain wall installation complete

• Station Building atrium skylight installed

• NAL & CRL Platform canopy (roofing and bullnose)

• Internal building fit-out – SGCC control room, walls being built with services being installed in the walls. Service rooms on the NAL platform being installed

• NAL overpass bridge Lift to platform - Painting of the steel, glass install

• Ventilation building – floor paint is being undertaken before plant is installed in the rooms.

10

CRL Platform glass curtain wall

11

Station Building – bird cage scaffolding for the skylight install

12

Lift installation progress

13

SGCC control room

14

Station Building fit out – level 1

15

CRL Platform canopy

16

Thibaut L'Hopital

Maungawhau Station Project Manager

17

Maungawhau site construction progress

• Civil scope of Station Building & Ventilation Buildings complete

• City Rail Link platform

• North Auckland Line platform and pedestrian

overpass

• Mined tunnelling complete

• Cut and cover tunnel progress

• Backfill progress

• Fenton Street Bridge – stairs and lift shafts installed, glass barrier works in August & October

18

Maungawhau site

19
20

Maungawhau Station Building

21
22

Ventilation Building

23

CRL & NAL Platforms

24

Cut & cover tunnels

25

Site backfill

26

C&E Advisor - NAL

27
Jennifer Charteris Senior

North Auckland Line (NAL) construction update

• Return to dual track running in July. A major project milestone!

• NAL completion October 2023

• Streets update:

o Porters Avenue and Haultain Street completed

o Fenton Street and Wynard Road streetscaping works taking place

o Mt Eden Road Bridge barriers & footpath installation commenced

o Boston Road returns to two-way traffic this week.

28

Return to dual tracks

29

Fenton to Haultain Street

30

Haultain Street

31

Boston Road to Mt Eden Road Bridge

32

Boston Road

33

Mt Eden Road Bridge

34
35
Laurent Illoz Systems – Linear Asset Installation Manager

Systems and track building update

• First full CRL track connecting the Western Line to Britomart to be complete in September

• Second CRL tunnel fit out currently underway

• Majority of works will move into the second CRL tunnels from September (MC50, 20)

• Track building towards the CRL platform and tunnel portal from the west ongoing

• Track building currently near Normanby Road Bridge into the tunnels (ballast and tamping)

• Block of Line October Labour weekend (tamping CRL connections to the Western Line)

36
37

Tunnel fit out & tracks

38

Tunnel fit out

39

Tunnel fit out

40

Track building

41

Kate Symington Senior Planner AECOM

42

Social Impact & Business Disruption (SIBD) overview

Designation condition 61.2.

How disruption to businesses, residents can be avoided, remedied, mitigated.

Specific issues:

• Disruption to traffic and access

• Loss of customers

• Loss of amenity

• Impacts to community facilities

43

Annual Report overview

Condition 61.8

The Requiring Authority shall prepare an annual report on the identification, monitoring, evaluation and management of the effects outlined in the Social Impact and Business Disruption DWP together with a summary of matters raised by the community, and how these have been responded to. The report shall be presented to the Community Liaison Groups.

44

Development Response

• Ongoing involvement in Uptown community.

• Supporting local events e.g. Aroha in Uptown, Branch Out - Uptown Spring Festival, Heritage

Festival tours

• Updated Art Guide and Second Edition Dining Guide a guide to eating and socialising around

Uptown

45

Development Response

• Increased number of perimeter tours and providing a tour on Saturday

• New neighbour pack provided to residents within 50m of the site including any new development

• New QR codes around the site to make accessing information easier

46

Complaint - statistics

36% decrease in complaints between 2021/22 and 2022/23

47

Complaints – who and how

Method of receipt 2021/22 2022/23 email 69.5% 55.6% phone 29.1% 42.3% informal meeting 0.8% 1.3% in person 0.0% 0.0%
Stakeholder 2021/22 2022/23 resident 65.5% 37.7% business 31.5% 55.6% member of the public 2.8% 4.2% other 0.0% 2.5%

Complaints - Link Alliance response

• Complaints investigated to ensure compliance with designation conditions

• Monitoring to confirm compliance (e.g. noise and vibration monitoring)

• Implementation of mitigation measures including noise mats, dust suppression

• Other construction solutions e.g. smaller roller for less vibration.

• Where possible, noisy or disruptive works delayed / undertaken at different times

49

Complaints - Link Alliance response

• Reminding contractors not park in business parking.

• Printing signs to deter staff and contractors from parking in private carparks.

• Information for AT enforcement provided

• Incentives to encourage workers to take alternative transport e.g. carpooling, providing AT Hop cards.

• Alternative parking provided to residents and businesses when parking has been required.

• Communicated to key stakeholders and public about upcoming works

50

• Are there any additional key issues and concerns?

• Is there any mitigation that have worked well?

• What can the Link Alliance do to further mitigate the disruptive impacts being experienced due to construction activities?

51
Questions

Simon Lough

Design & Delivery Manager

52

Fenton Street Bridge – recap of final designs

53
54
55

Stair installation

56

Lift shaft installation

57

Lift design & privacy

• The two sides of the lift cart will be solid, which means no one can see into the apartments when using the lifts.

• The red, white and black part of the lift’s glass will be opaque with the blue part being clear

58

Bridge lighting

7 Light posts will be positioned along the length of the bridge

• Lighting into the apartments was considered in the design process

• Light posts have been designed to face down, away from the apartments.

59

Bridge design & privacy

• The barriers along the main span of the bridge are 1.8m tall

• The barriers are however taller at both ends of the bridge, nearest to the elevators to provide additional privacy

• Opacity of the bridge glass increases the closer you reach the end of the bridge (around 90% opacity) – this is for privacy, so there is no direct view into the apartment.

60
61

Questions & Answers

62

Stay in touch with questions or feedback

• Email the Maungawhau Station at mteden@linkalliance.co.nz

• 0800 CRL TALK – choose option 5 for Maungawhau Station

• City Rail Link website www.cityraillink.co.nz

63

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.