Mt Eden Community Liaison Group Meeting November 2021

Page 1

Mt Eden Community Liaison Group Meeting 10 November 2021


Helpful hints for this virtual meeting • During this meeting, the presenters will not be able to see or hear you, but you’ll be able to watch and listen to them

• On the right hand-side of your screen there is a question panel. We encourage you to write questions or comments for our presenters as the meeting progresses • We’d appreciate it if you could use your name and possibly which local street you live or work on when you submit your question or comment • Please note that your comment won’t appear to all viewers until we publish it •

If you’re asking a question about a specific slide in tonight’s presentation, it would be helpful if you could take note of that slide number so we can bring it back up on screen to refer to if need be.

2


Agenda • Communications & Engagement update • Basque Park

• Mt Eden Station • TBM and Mined Tunnelling progress

• North Auckland Line (NAL) • Q&A

3


Communications and Engagement Update

• Welcome to our new CLG Members! • Initiatives to help our stakeholders stay up to date and connected with us during lockdown

• Online construction calendar launched • Wellness Pilot Programme has continued online offering 6 sessions each week

• An increase in upcoming weekend and night work that we are actively communicating

• Bespoke respite solutions to support our stakeholders through this work.

4


Annabelle Wrigley Communications & Engagement Advisor

5


Basque Park Update •

Last month we held a dawn karakia with representatives from Mana Whenua. This was to bless the park and the workers before construction began.

Site set up works have begun for the Basque Park pipe diversion works.

Only 3 trees rather than 5 initially planned were removed as part of our works. These are 3 will be replaced like for like along the hill. 4 other trees have been relocated into temporary spots until construction is complete.

Last month we asked residents to fill out a survey to find out how they currently use the park and what they would like to see during construction. •There was a strong preference for installing art and hosting community events during our time in the park.

•Coming up we will be installing artwork on the hoardings, additional lighting and seating.

•Directional drilling for the pipe diversion to begin December 2021. With all works expected to be complete by August 2022.

6


Thibaut L'Hopital Mt Eden Station Project Manager

7


Mt Eden Station Site - Construction Update • • • • • •

Huia 2 cut over now complete – Nikau Street reopened this week Station Building overpass installation from 17th November Western trough progress North Auckland Line platform progress Eastern cut and cover tunnels Ventilation building

8


9


10


11


12


13


Derek Whelan TBM Tunnels Construction Manager

14


Tunnel Boring Machine Update • Our Dame Whina Cooper TBM has now reached Karangahape Station!

• To date she has travelled 840 metres, installed 519 concrete rings and excavated 74,000 tonnes of spoil

• The TBM left Karangahape last weekend and now continues its drive to Aotea Station (the final stop on its first tunnel drive)

• This means supporting activities such as the spoil conveyor have now resumed and are running 24/7 on the Mt Eden Station site

• The TBM is anticipated to return to Mt Eden early next year ahead of its drive for the second City Rail Link tunnel.

15


16


17


18


19


Mined Tunnel update MC20 Stub Tunnel

TBM currently excavating this tunnel

MC30/60 Cavern

MC20/50 Cavern

MC50 Tunnel

Completed Work in progress 20


21


Nick Adams Deputy Construction Manager – North Auckland Line

22


North Auckland Line (NAL) - Construction Update Key upcoming NAL works for stakeholders to be aware of: • Blocks of Line o Saturday 20 – Sunday 21 November o Saturday 4 – Sunday 5 December o Sunday 26 December – Sunday 23 January • Construction works o Nightworks in rail corridor throughout November and December. • This weekend and night-work is crucial in the lead up to commissioning the new rail track for the single line running switch in January.

23


North Auckland Line (NAL) - Construction Update Key updates: • Track formation is well underway along the corridor. • Installation of new track at either end of the corridor has been completed. • Construction of foundations for southern abutment of Normandy Road over-rail bridge commenced earlier this month. • Construction of two grade separation structures nearing completion. • Installation of stormwater drainage within Boston Road and Nugent Street has commenced. • Diversion of Huia watermain in Fenton Street completed and road reinstatement underway. • Construction of southern pier of Porters Ave footbridge to commence shortly.

24


North Auckland Line (NAL) - Construction Update

25


North Auckland Line (NAL) - Construction Update

26


North Auckland Line (NAL) - Construction Update

27


Questions & Answers

28


Stay in touch with questions or feedback • Email the Mt Eden Station team at mteden@linkalliance.co.nz • 0800 CRL TALK – choose option 5 for Mt Eden Station • City Rail Link website www.cityraillink.co.nz

29