Mt Eden Community Liaison Group Meeting 2 March 2022


Helga Sonier Mt Eden Community Manager

2


Helpful hints for this virtual meeting • During this meeting, the presenters will not be able to see or hear you, but you’ll be able to watch and listen to them

• On the right hand-side of your screen there is a question panel. We encourage you to write questions or comments for our presenters as the meeting progresses • We’d appreciate it if you could use your name and possibly which local street you live or work on when you submit your question or comment • Please note that your comment won’t appear to all viewers until we publish it •

If you’re asking a question about a specific slide in tonight’s presentation, it would be helpful if you could take note of that slide number so we can bring it back up on screen to refer to if need be.

3


Agenda 1. Communications & Engagement 2. Construction updates – Basque Park – Mt Eden Station Main Site – Tunnelling – North Auckland Line

3. Urban Realm updates – Link Alliance urban realm scope – Eke Panuku Development Auckland – Auckland Transport Connecting Communities

4. Questions & Answers

4


Communications and Engagement Update

• Te Manawa Visitor Information Centre open

• 'Quiet Space' now open again 3 days per week • New water tank art and chalk 'jam wall' installed • Mr Whippy activations • Name the crane competition - 'Tui' • Significant works in the west

5


Annabelle Wrigley Communications & Engagement Advisor

6


Basque Park Update

• This month we also had one of our smallest tunnel breakthrough on site.

• Drill rig now successfully drilled underneath New North Road from Basque Park to our main site. With the micro tunnel now in place, the team are getting ready to pull a 5.6 metre wide pipeline through the tunnel using a pully system.

• Next step is small extension on the hoarding to connect pipes. This extension will be in place for approx. 3 weeks.

• Newly installed art on our hoardings has gathered positive feedback from the surrounding community.

• Coming up: pop up info day in the park late March.

7


Thibaut L'Hopital Mt Eden Station Project Manager

8


Mt Eden Station Site - Construction Update • • • • • • •

Site preparation for TBM's second drive Painting of the North Auckland Line pedestrian overpass Piling taking place for Station building foundations City Rail Link platform Ventilation building Cut and cover tunnels North Auckland Line platform progress

9


Mt Eden Station Site - Construction Update

10


11


12


13


Derek Whelan TBM Tunnels Construction Manager

14


Tunnel Boring Machine (TBM) Update • Front section of the TBM has returned from Aotea Station and is being reassembled near the tunnel portal

• Gantries (rest of the machine) have been transported back through the tunnel into the Mt Eden site

• Preparation for track installation begins this week with concrete pours for the tunnel floor

• 24/7 tunnelling night works continue in preparation for the next tunnel drive

• Current night works include welding the TBM front section back together • Second tunnel drive to commence in May, when the TBM's conveyor belt, spoil removal and other associated activities on site will all commence again 24/7.

15


16


17


Mined Tunnels Update MC20 Stub Tunnel

Excavation Completed First tunnel completed by the TBM in 2021

Waterproofing progress

MC30/60 Cavern

Second tunnel to be completed by the TBM in 2022

MC20/50 Cavern

MC50 Tunnel

18


Mined Tunnels Milestone

19


Nick Adams Deputy Construction Manager – North Auckland Line

20


North Auckland Line (NAL) - Construction Update • New Down Main fully operational

• Roof of Eastern Grade Separation (EGS) now complete • Excavation beneath EGS roof progressing well and 'daylighted' • 1000 bore piles installed to date • Piling progressing well at both ends of rail corridor

• Precast beams for southern span of Normanby Road bridge to be installed in early March

• Porters Ave footbridge piers completed and main span to be installed late March.

21


22


23


24


25


Simon Lough Interface Design Manager

26


Scope of Link Alliance's Urban Design Delivery Works Plan (DWP)

27


Link Alliance scope – immediate station surrounds

28


29


30


Link Alliance Urban Realm Scope – Planting on Boston Road

31


Kate Cumberpatch Eke Panuku Development Auckland

33


N

CRL Maungawhau and Karangahape precinct development programme


Basque Park

N

Maungawhau development sites Potential development opportunity ▪ CRL land – 3.2 ha

▪ Kāinga Ora land – 0.47ha ▪ 700+ new homes

Boston Road

▪ 25,000sqm commercial

LEGEND

CRLL landholding Kāinga Ora land CRLL station & rail

Mt Eden Station


Underway

Programme business case: CRL Project Sponsors are reviewing the draft.

Infrastructure assessments: To understand the three waters, transport and social infrastructure needed in the area.

NPS-UD: Waiting to understand the proposed changes through the NPSUD to have more clarity on the development capacity in the area.

Public realm investigation: Following infrastructure assessments, we will analyse potential public realm projects to improve the area.

Development outcomes: Analysis underway on best development approach to achieve foundation outcomes, in particular affordable housing.


Anthony Pearse & Angelene Burn Auckland Transport

37


New North Road and Symonds Street upgrade Project Update

Public engagement on 3 approaches is open until April 8th 2022



Questions & Answers

40


Stay in touch with questions or feedback • Email the Mt Eden Station team at mteden@linkalliance.co.nz • 0800 CRL TALK – choose option 5 for Mt Eden Station • City Rail Link website www.cityraillink.co.nz