Waitemata CLG Presentation September 2024

Page 1


September Community Liaison Group

Alex Vaineritua – City Rail Link

Catherine Edmeades – Auckland

Council

Sally Logan – JFC

Agenda

- City Rail Link Project Update

- Waitematā Station plaza and Tyler Street programme update

- Waitematā Station plaza and Tyler Street construction update

- Questions?

CRL Update

• CRL continues to be on track for opening in 2026

• Over the Matariki long weekend, the CRL signals were successfully integrated with those already in operation across the Auckland network

• All of the stations sky elements are completed

• CRL Ltd’s Chief Executive is changing in September

• Our next project phase is starting - testing and commissioning

CRL Update

• First fan has been energised

• All high voltage rooms have been energised

• Traction power has been enabled from both ends

• Almost all overhead line equipment is in place

• LA has begun training hundreds of AT, AOR and KR on CRL’s new systems –including the test train drivers

Waitematā Station (Britomart)

• Most work is completed

• Short section of overhead line to be installed in September

• Plaza being delivered by Auckland Council on CRL Ltd’s behalf behind the station building

Waitematā Station Plaza & Tyler Street Upgrade – Overview

CONSTRUCTION UPDATE

Waitematā Station Plaza & Tyler Street Upgrade – Programme Update

• JFC Ltd awarded the construction contract.

• Construction commenced 22 July.

• Main focus for the first ten months is Tyler Street, while also continuing works in the plaza.

• All construction anticipated to be complete by late 2025.

Waitematā Station Plaza & Tyler Street Upgrade –

Construction Update

New stormwater manholes

Ducting for underground services

New tree pits

Waitematā Station Plaza & Tyler Street Upgrade –Construction Update

• The section of Tyler Street between Commerce Street and Te Komititanga is for access by authorised vehicles only. The street will be narrower at times during construction, so vehicle access is limited to residents, tenants and deliveries to businesses in Waitematā Station, Endeans Building, 152 Quay Street and 148 Quay Street.

• Increased enforcement of parking on Tyler Street has been implemented to help resolve illegal parking and provide easier access to 152 Quay Street and Endeans Building.

• Working hours are generally 7am to 6pm, Monday to Friday, and 7am to late afternoon on Saturday (if required).

• For any construction related queries, please contact Sally LoganSally.Logan@jfcltd.co.nz or 021 420 794.

Any Questions?