ODU 7 Wilson’s Boat Yard to Fishery Creek

Page 1


ODU7:WilsonsBoatYardtoFisheryCreek

Overview

ODU7islocatedbetweenWilsonsBoatYardandFisheryCreek.Thefrontage comprisesalargeextentofresidentialpropertiesandavarietyofcommercial landuses,includingWilson’sBoatYard,MenghamRytheSailingClubanda numberofholiday/touringparks.

Environment

TheintertidalHarbourareaborderingthisfrontageisenvironmentally designatedasSSSI,Ramsar,SPA,SACand,alongwiththelandwardeastern fringe,fallswithintheChichesterHarbourNationalLandscape.Twoareasof formerlandfillarealsolocatedalongthemorevulnerablesectionoffrontage, whereriskoferosionisprobableinthenearfuture.

Defences

Defencesvaryalongthefrontage.Alongthenorth-easternsectionconcrete revetmentsandquaysareadjacenttotheEnvironmentAgency’sSelsmore andMenghamCoastalDefenceschemewhichconsistsofrockrevetment andwascompletedin2012.Defencesalongthissectionareprivately ownedbutmaintainedbytheEnvironmentAgencyandhaveresiduallives oftypically10to20plusyears.

Tothesouth,thereisashortsectionofrockfilledgabionbasketswhichare ingoodcondition,againprivatelyowned,butmaintainedbythe EnvironmentAgency.However,theremainingfrontageextendingtowards FisheryCreekconsistsofanaturalearthvergewithnoharddefences.The vergeisinpoorcondition,hasashortresiduallifeoflessthan10yearsand isactivelyerodinginplaces.

ShorelineManagementPlanPolicy

HoldtheLineforthenext100years.

WilsonsBoatYard

Risk

Themainriskalongthenorth-eastfrontageisfromtidalflooding.Herethereisacontinuousfloodcellwhere approximately302propertiesareatriskoverthenext100years,withoutdefencesinplace.Alongthesouth-east coastthemainriskisfromerosionwherethereisformercoastallandfillatrisk.

Themapsbelowshowthemodelledextentanddepthsofanextremetidalfloodevent(1in200year,0.5%annual probability),withoutanydefences,todayandin100years,allowingforsealevelrise.

Erosionrisk

Numberofpropertiesatrisk,withnodefences

Tidalfloodrisk

Numberofpropertiesatrisk,withnodefences

£10,888,000 PresentValue

StrategicIntent

Thestrategicintentfortheunitistoreducefloodanderosionrisk topropertiesoverthenext100yearsbutalsopreventformer landfillfromeroding/leachingintotheHarbour.Thiswillrequire constructionofnewdefencesinaphasedapproachovertime.

NextSteps

AFloodandCoastalErosionRiskManagementSchemeforthe frontagehasbeenproposedintheStrategy’sshorttermactionplan. Subjecttosecuringfunding,thiswillstartwithafeasibilitystudyto appraiseappropriatecoastalmanagementoptionsandalignments alongthisfrontage.