Irish Construction News May 2021

Page 34

CASE STUDY

Radharc An tSaile, Kinsale, County Cork .

M M D C o ns tr u c tio n d e liv e r s 4 0 NZ E B h o m e s in Kinsale for C lúid Housing Despite Covid-19 lockdowns, MMD Construction delivered the Radharc An tSaile housing scheme in Kinsale for Clúid Housing just one week behind schedule.

M

MD Construction was the main contractor and Project Supervisor Construction Stage for Radharc An tSaile, a 40 unit Nearly Zero Energy Building (NZEB) standard social housing scheme in Kinsale, County Cork, for approved housing body Clúid Housing. The project was a collaboration between Clúid, Cork County Council, the Department of Housing, Local Government and Heritage, the Housing Finance Agency (HFA) and MMD Construction. It had been 10 years in the pipeline and was eventually completed in 2020. Radharc An tSaile comprises 18 twostorey, two-bed houses; 20 two-storey, threebed houses; and two single-storey two-bed accessible dwellings. The ultra-efficient A-rated dwellings incorporate the latest mechanical and electrical services. The houses were built to an A2 BER rating and achieved an airtightness of under 3 m3/hr/m2. Adding an air-to-water heating system brought them to NZEB standard.

CHALLENGES

Kevin O’Leary, Director, MMD Construction, says several substantial challenges were faced on the build, including the Covid-19 shutdown. But the contractor still managed to achieve substantial

32 irishconstructionnews May 2021

completion only one week behind programme. The first challenge the MMD Construction team faced was in relation to the excavation works. “The scheme is constructed into the side of a hill,” explains Kevin O’Leary. “There was a lot of rock to be cleared, which proved challenging and more time consuming than expected due to its density, particularly when it came to foundations and services. But we were able to bring in the large enough machinery from our plant stock to be able to get on with the job.”

ADDRESSING COVID-19

Cormac Smith, Director, MMD Construction, outlines how Covid-19 impacted the project, “The Covid-19 shutdown and introduction of new Covid-19 operating procedures required major changes for those working on the site and the whole MMD Construction organisation,” Cormac Smith explains. “The first shutdown hampered us, and when we reopened, it took a couple of weeks to get the site moving smoothly. During the first shutdown, we put a lot of work into preparing new procedures for how the overall company would operate, including enabling those who could work remotely to do so, and setting up our IT


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Construction well placed to help government meet its greenhouse gas

21min
pages 64-72

Mercury renews carbon-reduction pledge

2min
page 63

James Golden, Director, Quigg Golden Irish construction has still not realised the full potential of MMC – Michael O’Reilly, Director, O’Connor Sutton Cronin

6min
pages 52-53

Housebuilders need to act now to take the lead in addressing embodied carbon in future developments – Susan McGarry, Managing Director

10min
pages 57-59

Ecocem Ireland for Ireland and Europe, John Sisk & Son Ecoplant: Leading the way in the green plant hire revolution – Sean Breen. Managing Director, Ecoplant

7min
pages 60-62

It is imperative we use this time to renew and refocus

3min
page 55

Female students need to know they have a place in engineering

3min
page 54

Enterprise Ireland’s Ready for a Green Future campaign features Irish construction innovators

2min
page 56

Adjudication decision enforced: The courts signal support for adjudication

5min
pages 50-51

Quintain, Vision Contracting, Clancy ‘The Sisk Living business model is different to that of a traditional builder

13min
pages 24-27

John FFF O’Brien, Principal Consultant, John Farage O’Brien Professional indemnity insurance: Navigating through the storm

7min
pages 48-49

Monami scheme one of the first to be completed under Covid-19 Return to Work Safely Protocol – Poplar Row apartments

5min
pages 32-33

Radharc An tSaile Construction Gas Networks Ireland and Cosgrave Group partner to reduce emissions on Dublin scheme – Bridgefield and Pappan Grove

9min
pages 40-43

Off-site solutions facilitate timely completion of luxury residential scheme

6min
pages 28-31

Delivering housing now and in the future

13min
pages 18-23

The time is now for our nation’s Public Works Contracts to evolve

13min
pages 44-47

MMD Construction delivers 40 NZEB homes in Kinsale for Clúid Housing

12min
pages 34-39
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.