Early Adopter Experience BIM Level 2 in Public Sector
Section Two BIM “Lessons learnt”
for CITA
BIM “Lessons learnt” CERC, University Hospital Limerick June 2017
for CITA
BIM “Lessons learnt” CERC, University Hospital Limerick June 2017
Agenda • Project overview • Design Team appointment • Design stages • Tender production • Procurement & Contractor appointment • Construction stage
• FM
• What are the lessons learnt?
Design Stage - objectives • Improve Design Development • Early Client Approvals
• Improve Design Team Coordination (BIM Level 2) • Resolve clashes prior to tender • Improve quality of tender information • PAS 1192-2:2013 guidance adopted • Employers Information Requirements (EIR) established • Project Information Manager/ BIM Coordinator
• Design Stage BIM Execution Plan (BEP)
Aerial photo – existing site
Aerial photo – existing site
Site Plan – overlay of existing and DCP Masterplan
Masterplan Options - Review
Existing Site
Masterplan Options - Review
Masterplan Options - Review
Masterplan Options review
Site Plan
Floor Plans – to describe spaces for client
Ground Floor
Floor Plans – to describe spaces for client
Internal Spaces – for agreement with client
Internal Spaces – for client presentation – preliminary design
Tea Station
Colour Palette – Main Entrance Foyer White Painted Ceiling Panel
Grey Paint Finish
Accent Colours to Soft Furniture
Nero Acapulco Floor Tile
Circulation + Social 1st floor
Painted Plaster
Desso Carpet
Oak Doors and Linings
Grey Formica
Tender documentation / deliverables •
BS – PAS 1192-2: 2013 guidance adopted (included in information pack)
•
Works Requirements Report, Section 14 sets out the BIM requirements and BIM protocol for the project (included in Volume A)
•
Employers Information Requirements (EIR), incl Model Production and Delivery Table and
Information Requirements (Appendix A1) •
Project Information Manager (PIM) scope of services (Appendix A1)
•
Project Document/ Data Management System (PDMS) & Digital Safety file specification (Appendix A1)
•
Works Requirements Documents: Drawings, Schedules, Specifications are derived from the BIM model (3d and 2d elements) (Appendices A3-A6)
•
‘As Built’ BIM and Safety File requirements defined, including COBie format
Structure / Services Coordination
Structure / Services Coordination
Tender Documents
Tender Documents
Tender Documents
Construction Stage - objectives • Reduce on site changes • Early identification of issues
• Improve construction team’s project understanding • Improve site coordination • Improve project planning and work sequencing (BIM 4d) • Provide ‘Data Rich’ as built model to improve FM post completion • Project Information Manager/ BIM Coordinator • Construction Stage BIM Execution Plan (BEP)
• Common Data Environment to manage information transfer
BIM Level 2 – On-site Co-ordination Meetings
BIM Level 2 – On-site Co-ordination Meetings
BIM Level 2 – On-site Co-ordination Meetings
Key issues • Brief • Clear Client requirements • What is the driver • Design to tender • Leverage coordination benefits • Allow sufficient resource hours • De-risk construction stage
• Construction stage • Capable contractors • Ongoing use and monitoring • FM
• Asset register • Future development