CONSTRUCTION UPDATE NOV 2017 On behalf of the developer, we bring to you the following updates from the construction site of Lygon 8 in Melbourne, as of November 2017.

Structure is complete up to level 8.

Façade work is in progress and joinery fit-out has commenced.

Works on the level 8 communal facility is underway.

Completion and settlement is anticipated for March/April 2018

Details of the façade facing Park Street.

Building on Brunswick Street.


Building from Park Street side

Rooftop of level 8 residents communal space.