Construction Update – Aura (April 2019)

Page 1

AURA Student Accommodation

Student Accommodation

Progress Update April 2019

Progress Update April 2019


AURA

Progress Update April 2019

Student Accommodation

Dear Investor, On behalf of the developer, we provide you with the latest updates as of January 2019 from the Aura construction site.

Following the demise of the original contractor, Forrest Ltd, the replacement contractor, Vermont, has now been engaged to complete the works and have commenced on site. A summary of the works to date are as follows: • Foundations complete (all phases) • Phase 1 lift core base, retaining wall works and concrete lift shaft works complete • Phases 1 & 2 steel work installation complete to level 9 and part way to level 11 • Drainage installations underway • Bathroom pods delivered for phase 1 • Phase 2 lift core base works ongoing Completion is now anticipated to be: Phase 1 Q2 2020 Phase 2 Q3 2020 Phase 3 Q3 2020


AURA Student Accommodation

Progress Update April 2019


AURA Student Accommodation

Progress Update April 2019


AURA Student Accommodation

Progress Update April 2019


AURA Student Accommodation

Progress Update April 2019


AURA Student Accommodation

Progress Update April 2019


AURA Student Accommodation

Progress Update April 2019


AURA

Progress Update April 2019

Student Accommodation

Level 3, North Block, Wisma GER,142D Jalan Ampang, 50450 Kuala Lumpur +03-2162 2260 www.csiprop.com

info@csiprop.com www.youtube.com/csiprop

www.facebook.com/csiprop


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.