Progress Update January 2018
www.csiprop.com
Student Accommodation
AURA
Progress Update January 2018
Student Accommodation
Dear Investor, Demolition has progressed well on the Aura site. Detailed updates are found below: • Site fully secured and hoarded • Hoarding signage installed • Strip out and demolition and removal of foundations to former units 90% complete • Phase 1 site stripped, and marked out ready for ground works to commence Key dates for construction: • Mobilisation & site set-up – January 2018 • Start on site – January 2018
www.csiprop.com
On behalf of the developer, we present to you the latest information from the Aura Construction site.
Student Accommodation
Progress Update January 2018
www.csiprop.com
AURA
Student Accommodation
Progress Update January 2018
www.csiprop.com
AURA
Student Accommodation
Progress Update January 2018
www.csiprop.com
AURA
Student Accommodation
Progress Update January 2018
www.csiprop.com
AURA
Student Accommodation
Progress Update January 2018
www.csiprop.com