Dear Investor,

Work is continuing well on the Aura site, and please see an update of works taken place below:

We are pleased to provide you with the information from the Aura construction site.

• Site fully secured and hoarded • Contractor site set-up is complete • Strip out and demolition and removal of foundations to former units complete to Phase 1 and ongoing to Phase 2 • Site strip and reduced level excavations / rock break out to Phase 1 complete • Phase 1 foundations, lift core, and retaining walls commenced • Phase 1 steelwork installation due to commence mid May 2018 The key dates for construction are: Phase 1 • Demolition Complete • Practical Completion Q3 2019 Phases 2+3 • Demolition April 2018 • Practical Completion Q1 2020


AURA Student Accommodation

Progress Update March 2018


AURA Student Accommodation

Progress Update March 2018


AURA Student Accommodation

Progress Update March 2018


AURA Student Accommodation

Progress Update March 2018