Dear Investor, On behalf of the developer, We provide you with the latest updates as of September 2018 from the Aura construction site.

Work is continuing well on the Aura site. Please see a summary of the works that have taken place below: • Phase 1 +2 foundations complete, lift base and retaining walls ongoing • Phase 1 lift core complete, retaining wall works complete & lift shaft works ongoing • Phase 2+3 Lift core base ongoing • Phase 1 steelwork installation complete to Level 9 • Phase 1 metal decking and concrete upper floor works complete to Level 6 • Drainage installations to Phase 1 ongoing • Tower crane 1 & 2 installed and both operational The key dates for construction are: Phase 1 • Demolition • Practical Completion

Complete Q3 2019

Phase 2 + 3 • Demolition • Practical Completion

Complete Q1 2020

www.csiprop.com

Student Accommodation

AURA

Progress Update September 2018


AURA

Student Accommodation

Progress Update September 2018

www.csiprop.com

AURA


AURA

Student Accommodation

Progress Update September 2018

www.csiprop.com

AURA


AURA

Student Accommodation

Progress Update September 2018

www.csiprop.com

AURA


AURA

Student Accommodation

Progress Update September 2018

www.csiprop.com

AURA


AURA

Progress Update September 2018

Level 3, North Block, Wisma Selangor Dredging,142D Jalan Ampang, 50450 Kuala Lumpur +03-2162 2260 www.csiprop.com

info@csiprop.com www.youtube.com/csiprop

GPS: 3.1597131272736787, 101.70924246311189

www.facebook.com/csiprop

www.csiprop.com

AURA

Student Accommodation


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.