AURA Student Accommodation
Progress Update September 2018
Progress Update September 2018
www.csiprop.com
Student Accommodation
AURA
Dear Investor, On behalf of the developer, We provide you with the latest updates as of September 2018 from the Aura construction site.
Work is continuing well on the Aura site. Please see a summary of the works that have taken place below: • Phase 1 +2 foundations complete, lift base and retaining walls ongoing • Phase 1 lift core complete, retaining wall works complete & lift shaft works ongoing • Phase 2+3 Lift core base ongoing • Phase 1 steelwork installation complete to Level 9 • Phase 1 metal decking and concrete upper floor works complete to Level 6 • Drainage installations to Phase 1 ongoing • Tower crane 1 & 2 installed and both operational The key dates for construction are: Phase 1 • Demolition • Practical Completion
Complete Q3 2019
Phase 2 + 3 • Demolition • Practical Completion
Complete Q1 2020
www.csiprop.com
Student Accommodation
AURA
Progress Update September 2018
AURA
Student Accommodation
Progress Update September 2018
www.csiprop.com
AURA
AURA
Student Accommodation
Progress Update September 2018
www.csiprop.com
AURA
AURA
Student Accommodation
Progress Update September 2018
www.csiprop.com
AURA
AURA
Student Accommodation
Progress Update September 2018
www.csiprop.com
AURA
AURA
Progress Update September 2018
Level 3, North Block, Wisma Selangor Dredging,142D Jalan Ampang, 50450 Kuala Lumpur +03-2162 2260 www.csiprop.com
info@csiprop.com www.youtube.com/csiprop
GPS: 3.1597131272736787, 101.70924246311189
www.facebook.com/csiprop
www.csiprop.com
AURA
Student Accommodation