The Lightbox Project Monthly Update Report
October 2
NOBLE DESIGN AND BUILD Authored by: Christopher Clark
1
ACHIEVEMENTS UPTO AND INCLUDING AUGUST • • • • • • •
The second part of the Site Investigation was completed Gas monitoring (Condition 3) was completed and submitted to Sheffield council The Site was back Filled after Archeological Dig All Existing Perimeter Walls were removed in Preparation for the Piling Contractor The Pile Matting was installed in Preparation for the Piling Contractor Installed temporary Services (electric and Water) Obtained Party wall awards
ACHEIVEMENTS IN SEPTEMBER • • • • • • • •
Completed the Piling Design Completed the Basement Design Submitted Piling and Basement Design to Highways Appointed Contractor to remove lamp Posts Appointed Piling Contractor Signed off Undercroft car Park Works Obtained Party wall awards for the Adjoining Car Park Appointing Lift Contractor
2
STARTED WORKS ON SITE Construction works has finally commenced on the 1st October 2018, now we have obtained the Party Wall agreement with the Neighbouring car park. Figure 1 below shows the Hoarding being erected in the Neighbouring Car park and Plant being delivered to take down the retaining walls.
FIGURE 1 – A PHOTOS OF WORKS STARTED – HOARDING CAR PARK TO REMOVE THE PARTY WALL The adjoining Party Walls in figure 2 below will be demolished and replaced with Piles and a Concrete retaining wall.
FIGURE 2 – A PHOTO OF THE EXISTING RETAINING WALLS TO BE REMOVED 3
PILING Once the wall is taken down the Piling will commence on the 15th October 2018, we have two large Piling Rigs scheduled in to carry out the 472 Piles. The Piling works are estimated to take between Four to Five weeks. Figure 3 below shows the Piling Design previously approved by Highways and Utility Companies.
FIGURE 3 – PILING LAYOUT The Piling Contractor used for this project has established a reputation for delivering high quality piling and ground engineering solutions throughout the British Isles and overseas. Steady year-on-year growth further confirmed their position as the largest and most successful geotechnical contractor in the UK. Noble design and Build have partnered with this Contractor on numerous other Developments and confidence in them delivering on this project. The piles selected for this project is the Continuous Flight Auger (CFA) technique, this is one of the quietest piling solutions available and is virtually vibration free, making it ideal for working in close proximity to existing buildings, in residential or in environmentally sensitive areas. They can also be installed without the need for casing, bentonite or polymers in both cohesive material such as clay, weak rock, non-cohesive and water bearing soils such as sand, gravels and glacial tills.
BASEMENT WORKS Following on from the Piling Contractor, Nobles Groundworkers will be carrying out the reduce level dig and specialist concrete works. Nobles Groundworkers are specialists in reinforced concrete and associated groundworks. Nobles specialty is in-situ reinforced concrete structures, sub-structures and related groundworks for commercial, industrial and public sector clients. With over 100 successfully completed projects in its portfolio, we have been awarded numerous Concrete Society Awards for quality of workmanship and technical expertise. 4
Building its reputation on the expert skills of its people, Noble uses effective, efficient and innovative solutions to successfully deliver challenging and prestigious projects to its long-standing portfolio of clients - to budget, within program and to a high-quality finish.
STEEL FRAME Following the Basement Works, our steel erectors will be visiting site and intend on erecting the Steel frame from the Car Park end of our Site. The Steel Frame has been fully designed and is currently in Fabrication, Pre-fabricating the steel frame off site will ensure the building will be built in the fastest possible way.