ONE ISLINGTON PLAZA CONSTRUCTION UPDATE JULY 2018
On behalf of the developer, we present to you updates as of July 2018 from
One Islington Plaza Devon Street, Liverpool, L3 8HA What’s new? • • • • • • • •
CP board and insulation is 90% installed Cladding and window installation has commenced The roof is 95% complete The lift shaft is complete Beam and block floor installation is complete Ground floor block walls are 30% installed Mechanical and electrical first fix works are complete on floors 6-10 Plasterboard partitions have been installed on floors 6-10
Work Scheduled • • • • • • • •
Completion of external CP board and insulation Progression of cladding and window installation Progression of ground floor block walls Commencement of lift installation Commencement of second fix mechanical and electrical works to floors 6-10 Progression of first fix mechanical and electrical works to floors 2-5 Progression of partitioning throughout