ONE ISLINGTON PLAZA CONSTRUCTION UPDATE MAY 2018


On behalf of the developer, we present to you updates as of May 2018 from

One Islington Plaza Devon Street, Liverpool, L3 8HA The latest One Islington Plaza Construction Update shows substantial progress at the site with underfloor drainage now 100% complete. Other tasks such as the installation of beam and block floors, internal plasterboards and steel portioning are also underway and due to be completed shortly amongst a busy schedule laid out for upcoming weeks.

What’s new? Underfloor drainage is now 100% complete Installation of beam and block floors is 50% complete. Mechanical and electrical works have begun across all floors. 70% of internal plasterboard is installed on floors 6 to 10. 50% of steel portioning has been successfully installed on floors 2 to 5. SFS board installation is now almost complete at 75%. There has also been significant progress on the installation of the roof.

Work Scheduled The beam and block floors are due to complete shortly. The gas membranes will also be completely finished. Works will continue to mechanics and electrics on all floors of the development Internal plasterboard will continue on floors until 100% complete. Cladding package will also undergo significant progress. www.csiprop.com


www.csiprop.com


www.csiprop.com



Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.