ONE ISLINGTON PLAZA Construction Update October 2018


One Islington Plaza Devon Street, Liverpool, L3 8HA On behalf of the developer, we provide you with the latest images and information as of October 2018 from the One Islington Plaza construction site. External Works CP board installed to 95%. Insulation installed to 90% with 10% materials on site. 40% windows installed. 50% materials on site. Pictura cladding installed 75%. Aluminium cladding materials arrives on site. 98% materials on site for roof. External envelope works have continued to progress well in the last period. Glazing has now been installed to several elevations which has allowed the commencement of Internal Works

Blockwork to lift shaft 100% complete. Internal partitions 75% installed. 35% of ceilings installed. Internal door installation 20% complete.

In the latest One Islington Plaza construction update, works are progressing well


Level 3, North Block, Wisma Selangor Dredging,142D Jalan Ampang, 50450 Kuala Lumpur +03-2162 2260 www.csiprop.com

info@csiprop.com www.youtube.com/csiprop

GPS: 3.1597131272736787, 101.70924246311189

www.facebook.com/csiprop


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.