Construction Update | Opto House Block C (Nov 2017)

Page 1

Opto House (London Spring Place) Block C

Progress Update November 2017

www.csiprop.com

UK Student Accommodation Investment


Dear Investor, On behalf of the developer, we provide you with the latest construction news and images from the Opto House construction site, Luton.

Works are progressing well on site and reported on target for completion December 2017. A summary of works to date include: • Floors concreted to all levels • SFS cladding rails complete • Cladding panel installation complete • Window installation complete • Blockwork for lift shaft complete • Mechanical + Electrical 1st fix complete • Dry lining 1st fix complete • Flat roof works complete • Furniture installation complete • Pre-hung door sets delivered and installed • Stair core extension 95% complete • External sewage connection complete • External works to the front and rear are complete

Practical completion is expected around 8th December 2017 following which the Notices to Complete are will be sent out and buyers will have 10 working days to finalise their purchase(s).

www.csiprop.com

UK Student Accommodation Investment

Progress Update November 2017

pto House Block C

Opto House (London Spring Place)


www.csiprop.com

UK Student Accommodation Investment

Progress Update November 2017

pto House Block C

Opto House (London Spring Place)


www.csiprop.com

UK Student Accommodation Investment

Progress Update November 2017

pto House Block C

Opto House (London Spring Place)


www.csiprop.com

UK Student Accommodation Investment

Progress Update November 2017

pto House Block C

Opto House (London Spring Place)


www.csiprop.com

UK Student Accommodation Investment

Progress Update November 2017

pto House Block C

Opto House (London Spring Place)


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.