Opto House (London Spring Place) Block C UK Student Accommodation Investment
Progress Update October 2017
www.csiprop.com
UK Student Accommodation Investment
Progress Update October 2017
Exclusive Marketing Agent:
pto House Block C
Opto House
UK Student Accommodation Investment
Dear Investor,
Works are progressing well on site and reported on target for completion December 2017. A summary of works to date include: • • • • • • • • • • • • •
Floors concreted to all levels SFS cladding rails complete Cladding panel installation complete Window installation 98% complete Blockwork for lift shaft complete Mechanical + Electrical 1st fix complete Dry lining 1st fix complete Flat roof works complete Furniture installation complete to Levels 1 – 4 Pre-hung door sets delivered and installed Levels 1 – 5 Stair core extension 90% complete External sewage connection complete External works to the read of courtyard are 95% complete
www.csiprop.com
On behalf of the developer, we provide you with the latest construction news and images from the Opto House construction site, Luton.
Progress Update October 2017
pto House Block C
Opto House (London Spring Place)
www.csiprop.com
UK Student Accommodation Investment
Progress Update October 2017
pto House Block C
Opto House (London Spring Place)
www.csiprop.com
UK Student Accommodation Investment
Progress Update October 2017
pto House Block C
Opto House (London Spring Place)
www.csiprop.com
UK Student Accommodation Investment
Progress Update October 2017
pto House Block C
Opto House (London Spring Place)
www.csiprop.com
UK Student Accommodation Investment
Progress Update October 2017
pto House Block C
Opto House (London Spring Place)
www.csiprop.com
UK Student Accommodation Investment
Progress Update October 2017
pto House Block C
Opto House (London Spring Place)