Dear Investor, On behalf of the developer, we are pleased to provide
Works are progressing well on site and reported on target for completion Q4 2017. A summary of works to date include:
you with the latest construction news and
- Demolition of existing buildings complete
images from the Opto House
- Sheet piling works complete
construction site, Luton.
- Concrete retaining walls and groundworks complete
- Below ground drainage complete - Steel frame erection progressing well and due for completion 12th May - Steel decking and concrete oors works to commence 18th April - Bathroom pod deliveries to commence 8th May - External sewer connection is now complete
www.csiprop.com
UK Student Accommodation Investment
pto House Block C
Progress Update March 2017
www.csiprop.com
UK Student Accommodation Investment
Progress Update March 2017
pto House Block C
Opto House