Construction Update | Phoenix Place (Oct 2017)

Page 1

Contractors Report Contractors Report Contract :

Contract No. :

Phoenix Place

1085

Prepared By : Tony Scott Report No. : Contract : Phoenix Place Contract No. : Date Prepared : 06-10-17 Site Meeting Date : Prepared By : Tony Scott Report No. : On behalf : of the Developer, we present the latest update as Distribution Date Prepared :site06-10-17 Site Meeting Date : construction of Phoenix Place. Distribution : Start Date

A

01-08-18

71

A

Start Date

Completion Date

Contract Period

27-03-17

01-08-18

71

B

Task ID

Activity

0011 1790 Task ID 0010 0011 0020 1790 0040 0010 0050 0020 0060 0040 0051 0050 0070 0060 0080 0051 0071 0070 0090 0080 0100 0071 0110 0090 0120 0100 0130 0110 0111 0120 1600 0130 0140 0111 1630 1600 0141 0140 0160 1630 0170 0141 0180 0160 0190 0170 0200 0180 0151 0190 1610 0200 0210 0151 1640 1610 0241 0210 0242 1640 0211 0241 0221 0242 0230 0211 0240 0221 0260 0230 0240 0260

Construction Period Enabling Works Activity Set Up Site Hoardings Construction Period Isolate Services Enabling Works Strip out Asbestos Set Up Site Hoardings Demolish Buildings Isolate Services Crush Stone Strip out Asbestos Groundworks Demolish Form Pile Buildings Mat CrushTest Stone CBR Groundworks Block 2 Form Pile Pile Mat CBR Crop Test Piles Block 2 Underground Services and Drains Pile Form Ground Beams Crop PilesGround Beams Concrete Underground Form Lift Pits Services and Drains FormLift Ground Cast Pits Beams Concrete Bases for Ground Steel Beams Form Lift Pits Brickwork Substructure Cast BlockLift 1 Pits Bases Pile for Steel Substructure Crop Piles Brickwork Block 1 Underground Services and Drains Pile Form Ground Beams Crop PilesGround Beams Concrete Underground Form Lift Pits Services and Drains FormLift Ground Cast Pits Beams Concrete Bases for Ground Steel Beams Form Lift Pits Brickwork Substructure Cast Lift Pits Gas Membrane Bases Steel Groundfor Floor Slabs Substructure Brickwork Superstructure Gas Membrane Steel/ Floors B2 Ground Floor Slabs Erect Steel Superstructure Place Holorib Steel/ Studs Floors B2 Shear Erect Steel Place Holorib Shear Studs

+5 days

Ahead / Behind Master Programme +5 days

Master Programme Prog. % Actual % +/- weeks 13 13 100 100Programme Master Prog. % Actual % +/- weeks 100 100 13 13 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 82 100 100 100 100 100 100 100 100 100 82 100 89 100 100 100 100 100 100 100 100 100 89 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 0 100 100 100 86 100 100 100 100 100 0 100 100 100 86 100 70 100 100 100 100 100 100 100 100 100 70 100 100 100 100 100 100 100 100 100 100 100 100 100 0 100 100 100 30 100 100 100 30 100 0 23 32 100 30 62 83 100 30 100 100 23 32 94 100 62 83 80 100 100 100 94Page 1 of 100 5 80 100

of Oct 2017 from the

06-10-17

Ahead / Behind Master

27-03-17

B

06 1085 06-10-17 06

Contract Period Programme CONTRACTOR REPORT

Completion Date

Form Number: QM-023 Rev: B Form Number: QM-023 Rev: B

Current Week Number 29

Anticipated Comp. Date 01-08-18

Current Week Number 29

Anticipated Comp. Date 01-08-18

Comments / Notes

Comments / Notes

Commencing 11/10/17

Commencing 11/10/17 Commenced 1 week remaining

Commenced 1 week remaining

B2 to be complete 2 weeks

B2 to be complete 2 weeks


Contractors Report

QM-023 Rev: B Rev: B

CONTRACTOR REPORT 0250 0250 0251 0251 0270 0270 0271 0271 0281 0281 0290 0290 0300 0300 0320 0320 0310 0310 0311 0311 0330 0330 1620 1620 0341 0341 0342 0342 0350 0350 0360 0360 0370 0370 0380 0380 0391 0391 0342 0342 0350 0350 0360 0360 0370 0370 0380 0380 0461 0461 0470 0470 0480 0480 0490 0490 0500 0500 0510 0510 0520 0520

C C

Fit Pre-Cast Stairs Fit Pre-Cast Stairs Handrails Handrails Concrete to Holorib Concrete to Holorib Screed Ground Floor Screed Ground Floor Steel/ Floors B1 Steel/Steel Floors B1 Erect Erect Steel Place Holorib Place Holorib Shear Studs Shear Studs Stairs Fit Pre-Cast Fit Pre-Cast Stairs Handrails Handrails Concrete to Holorib Concrete to Holorib Screed Ground Floor Screed Ground Floor Roof B2 Roof B2 Safety Netting Safety Netting Purlins to Upper Roof Upper Roof Purlins to Lower Purlins to LowerUpper Roof Roof Ply Membrane Upper Roof Ply Membrane Lower Ply Membrane Lower Roof Roof B1 Roof B1 Safety Netting Safety Netting Purlins to Upper Roof Purlins to Upper Lower Roof Purlins to LowerUpper Roof Roof Ply Membrane Upper Roof Ply Membrane Lower Ply Membrane Lower Roof Façade B2 Façade B2 Erect Access ErectWalls Access Clad Clad Walls Fit Windows Fit Windows Erect Access ErectWalls Access Clad Clad Walls Fit Windows Fit Windows

72 72 56 56 32 32 0 0 37 37 94 94 66 66 51 51 32 32 16 16 0 0 0 24 24 100 100 20 20 0 0 0 0 0 0 0 0 0 0 10 10 57 57 0 0 0 0 0 0

100 100 100 80 80 0 0 46 46 90 90 30 30 15 15 100 100 90 90 0 0 0 56 56 100 100 90 90 90 0 0 0 6 6 30 30 0 0 0 0 0 0 0 0 0 0 0 0

Scaffold to commence @ first lift brick Scaffold to commence @ first lift brick

Progress Summary (Overall Position) Progress Summary (Overall Position)

Temporary Services Temporary Services Electric – 1 supply to complete Electric -–Complete 1 supply to complete Water Water - Complete Substructure Substructure Underground drainage and services to be complete by 16-10-17. Underground drainage and services to be complete by 16-10-17. Superstructure Superstructure Block 2- Steel complete, Stairs installed, Holorib complete and concrete poured with 1 floor remaining. Block 2-- Steel complete, Stairs complete and concrete Purlins complete by installed, 13-10-17.Holorib Metal deck roof liner to follow. poured with 1 floor remaining. Purlins complete by 13-10-17. Metal deck roof liner to follow. - Brickwork commencing 11-10-17. Scaffold to follow. Form Number: - Brickwork commencing Contractors 11-10-17. Scaffold toReport follow. QM-023 Block 1- Steel complete in 1 week, Holorib and Easi edge is being lifted and positioned as floors progress. Rev: B Block 1- Steel complete in 1 week, Holorib and Easi edge is being lifted and positioned as floors progress. Currently 5 days ahead of programme. Currently 5 days ahead of programme.

D

Matters Affecting Progress OR Likely to Affect Progress (other than weather)

Page 2 of 5 Page 2 of 5 We have reprogrammed the drainage and ground floor slab installation due to lack of information from GJA. Reynolds & Litchfield will run 1 week over programme- Block 1 is being complete utilising 2 x cranes.

CONSTRUCTION UPDATES PHOENIX PLACE LIVERPOOL

OCTOBER 2017


F E

F

F G H H H G

G

J J J

K K K

Information / Instructions Type Weather

CONTRACTOR REPORT No. Issued to Date

Comments / Notes

3.5 x M&E day inclement winds. Final details weather due to high 19-04-17

Awaiting drawings from

Information / Instructions Architectural design

Awaiting design drawings from HLP

Type

No. Issued to Date

Comments / Notes

Final M&E details

19-04-17

Awaiting drawings from

Information / Instructions Architectural design Type Information Status

Contractors No. Issued to Date Report Contractors Contractors Report Report

Awaiting finalised Architect, Final M&E details detail drawings from19-04-17 Awaiting finalised M&E drawings from EMC Subcontractor / Labour

Awaiting design drawings from HLP Form Number: Comments / Notes QM-023 See also attached RFI Log Form Number: Form Number: Rev: B See also attached IRS QM-023 QM-023 Rev: B Awaiting drawingsRev: fromB

See attached Contract Information Directory for up-to-date list of subcontractors

Awaiting design drawings from Architectural design Subcontractor / Labour See attached Contract Information Directory up-to-date list of subcontractors HLP for Subcontractor / Labour See attached Contract Information Directory for up-to-date list of subcontractors Total Control Demolition Aarsleff PilingDemolition See also attached RFI Log Total Control Information Status Total Control Reynold’s andDemolition Litchfield See also attached IRS Aarsleff Piling Aarsleff Piling Northern Decking Reynold’s and Page 3 of 5 Reynold’s and Litchfield Litchfield Conform Groundworks Awaiting finalised detail drawings from Architect, Northern Decking Northern Decking Nationwide Fencing Awaiting finalised M&E drawings from EMC Conform Groundworks Conform Groundworks EMC Nationwide Fencing Nationwide Fencing Kelstar EMC EMC Conform Groundworks Kelstar Kelstar EMC Utilities Conform Groundworks Conform Groundworks See also attached RFI Log CB Precast Information Status EMC Utilities EMC Utilities See also attached IRS Classic Lifts CB Precast CB Precast Proven Brickwork Page 3 of 5 Classic Lifts Classic Lifts Awaiting finalised detail drawings from Architect, Atlantic Scaffold Proven Proven Brickwork AwaitingBrickwork finalised M&E drawings from EMC Atlantic Atlantic Scaffold Scaffold Material Procurement Material Procurement Material Procurement

Metal Decking Steel Frame Metal Decking Metal Decking Concrete floors Steel Frame Steel Frame Ground beam reinforcement Concrete Concrete floors floors Ground Ground beam beam reinforcement reinforcement

Page 3 of 5

Quality Quality Quality

Engineer QA ongoing Engineer Engineer QA QA ongoing ongoing

L L L

Samples & Approvals Samples & Approvals Samples & Approvals

Render- Approved Cladding RenderApproved RenderApproved BrickApproved Cladding Cladding SFS BrickApproved BrickApproved Windows SFS SFS External doors CONSTRUCTION UPDATES PHOENIX PLACE LIVERPOOL Windows Windows POD design freeze accepted by NCL External doors

OCTOBER 2017


Engineer QA ongoing

L

Samples & Approvals

L

Samples & Approvals

N M M P

CONTRACTOR REPORT

Render- Approved Cladding Render- Approved BrickCladding SFS BrickWindows Approved Contractors SFS External doors Windows POD design freeze accepted by NCL External doors POD design freeze accepted by NCL

Report

Form Number: QM-023 Rev: B

Any Other Business Health & Safety

No incidents since last report date. Health & Safety

No incidents since last report date. Appended Documents 01 02

Progress Programme Progress Photographs

Page 4 of 5 Page 4 of 5

CONSTRUCTION UPDATES PHOENIX PLACE LIVERPOOL

OCTOBER 2017


PROGRESS PHOTOGRAPHS

CONSTRUCTION UPDATES PHOENIX PLACE LIVERPOOL

OCTOBER 2017


PROGRESS PHOTOGRAPHS