ONE ISLINGTON PLAZA Construction Update November 2018
One Islington Plaza Devon Street, Liverpool, L3 8HA On behalf of the developer, we provide you with the latest images and information as of November 2018 from the One Islington Plaza construction site Works have progressed well at One Islington Plaza including the CP board which is now 98% complete. Pictura cladding and the roof are other external works due to be fully installed shortly. Internal works are also developing quickly, and the beam and block
External Works CP board is installed to 98%. Insulation is 95% installed. The windows are 55% installed. Pictura cladding is 95% installed. Aluminium cladding has been started and is 30% complete. The roof is now 98% complete. Internal Works
The lift is installed to 80%. Internal partitions are 85% in place. Ceilings have been installed to 40%. Internal doors have been progressed to 40%.
Level 3, North Block, Wisma Selangor Dredging,142D Jalan Ampang, 50450 Kuala Lumpur +03-2162 2260 www.csiprop.com
info@csiprop.com www.youtube.com/csiprop
GPS: 3.1597131272736787, 101.70924246311189
www.facebook.com/csiprop