The Residence
Progress Update January 2018
www.csiprop.com
Residential Apartments
The Residence
Progress Update January 2018
Residential Apartments
Dear Investor, • • • • • • • • •
Advertising screen and wall removed from site Archaeology works completed Pedestrian bridge removed Contractor site set-up with welfare facilities and site office at Suite 6, The Spectrum, Blackfriars Rd Contiguous piling complete Cutting tops of piles commenced Concrete capping beam works commenced Sheet piling due to complete mid February 2018 Mass basement excavation to commence end of February 2018
Completion due: Q4 2019
www.csiprop.com
Please see a summary of the works below:
he Residence
On behalf of the developer, we present you with the latest documentation from The Residence construction site.