Dear Investor, On behalf of the developer, we provide you with the latest images and information from the One Wolstenholme Square construction site.
Work is continuing at a good pace at Wolstenholme square. A summary of the works that have taken place: Block A • Complete. Block B • Practical Completion took place on 30th April 2018 • Completion packs currently being prepared by developes’s solicitors for Notices to Complete to be served Block C • Contractor snagging and cleaning to Level 4 Block D • Substructures completed • Steel frame complete • Steel decking complete and concreted • Staircases installed • Ground floor slabs complete • Metal stud partitioning commenced on Levels 1 - 5
• Weatherboarding to elevations and windows commenced to Levels 1 - 6 • Brickwork at Level 2 • First fix M+E at Level 2 Block E • Substructures due to start in June 2018 Please see below the anticipated practical completion dates for each block: Block A Block B Block C Block D Block E
December 2017 (complete) April 2018 (complete) June 2018 August 2018 March 2019
www.csiprop.com
UK Buy-to-Let Investment
ne Wolstenholme Square
Progress Update April 2018
www.csiprop.com
UK Buy-to-Let Investment
Progress Update April 2018
ne Wolstenholme Square
One Wolstenholme Square
www.csiprop.com
UK Buy-to-Let Investment
Progress Update April 2018
ne Wolstenholme Square
One Wolstenholme Square
www.csiprop.com
UK Buy-to-Let Investment
Progress Update April 2018
ne Wolstenholme Square
One Wolstenholme Square
www.csiprop.com
UK Buy-to-Let Investment
Progress Update April 2018
ne Wolstenholme Square
One Wolstenholme Square
www.csiprop.com
UK Buy-to-Let Investment
Progress Update March 2018
ne Wolstenholme Square
One Wolstenholme Square