THEME: Project Delivery
CRYOFRONT – News and Views from the Far North
Project delivery in the Far North - then and now By Ken Johnson, NTWWA Director
A century after what many consider to be the greatest ‘event’ in the far north, the Klondike Gold Rush, it is interesting to reflect on the delivery of projects during that era, and in our so-called modern age. A Gold Rush era project that is fresh in my mind, is the Yukon Ditch, which was a $3 million (1909 dollars), 115 km, flume, ditch and pipeline project designed to deliver 5,000 miner’s inches of water (3500 litres per second) for hydraulic mining. The following excerpts from a site visit in 1909 by an engineer, indicate the challenges with project delivery at the time. “The magnitude of the work accomplished by the engineers of the Yukon Gold Co. may
48 | Western Canada Water | Winter 2011
be inferred from an enumeration of the tasks completed during the three seasons since the first surveys were finished – a power-plant of 2,000 HP, with 35 miles of main (power)line, 18 miles of branch, and 8 miles of secondary lines; 64 miles of main ditch, flume, and pipe. All this has been done 3,500 miles distant from manufacturing centres, with an inadequate supply of labour. Some of the machinery that arrived had been ordered 18 months previously. During the season of 1907, over 7,000 tons of material was received, and it was inevitable that some of the parts ordered in advance, for immediate operations, should be delayed in delivery despite every effort. A sufficient stock of parts
is carried, so as to obviate delays from slowness of transport. Maintenance of a proper commissariat for labourers required some generalship. An effort was made to overcome the uncertain supply of local labour by importing 320 men from British Columbia. Of these, 20 deserted on the way.” Dawson City and in fact much of the area ‘north of 60’ remains a project delivery challenge. This has been recognized by northern practitioners for over 25 years, and the cycle for project delivery is generally laid out in a 5 year ‘plan.’ The first year of a project is utilized for project planning. This is a necessary, but often time
Click here to return to Table of Contents