Project delivery in the Arctic - a brief history

Page 1

SPECIAL FOCUS: COLD CLIMATES AND REMOTE LOCATIONS

Project delivery in the Arctic hasn’t changed much since the Klondike Gold Rush era By Ken Johnson

M

ore than a century after what many consider to be the greatest “event” in the history of the Arctic, the Klondike Gold Rush, it is interesting to compare the delivery of projects during that era to today. A Gold Rush era project of particular significance was the Yukon Ditch. It was a $3 million (1909 dollars), 115-kilometre, flume, ditch and pipeline project designed to deliver 5,000 miner’s inches of water (3,500 litres per second) for hydraulic mining in the Dawson City area. The following excerpts from a site visit in 1909 by an engineer indicate the challenges with project delivery at the time: “The magnitude of the work accomplished by the engineers of the Yukon Gold Company may be inferred from an enumeration of the tasks completed during the three seasons since the first surveys were finished. These include a power-plant of 2,000 HP, with 35 miles of main (power) line, 18 miles of branch, and 8 miles of secondary lines; 64 miles of main ditch, flume, and pipe. “All this has been done 3,500 miles distant from manufacturing centres, with an inadequate supply of labour. Some of the machinery that arrived had been ordered 18 months previously. “During the season of 1907, over 7,000 tons of material was received, and it was inevitable that some of the parts ordered in advance, for immediate operations, should be delayed in delivery despite every effort. A sufficient stock of parts is carried, so as to obviate delays from slowness of transport. “Maintenance of a proper commissariat for labourers required some generalship. An effort was made to overcome the uncertain supply of local labour by importing 320 men from British Columbia. Of these, 20 deserted on the way.” Dawson City, and in fact much of the Arctic remains a project delivery challenge. This was recognized by Arctic engi1  |  February 2021

A significant portion of the Yukon Ditch was constructed using “steam shovels.” These steam shovels were delivered in the vicinity of the project by sternwheelers and transported to the project site by horse-drawn sleds (in many pieces of course).  Photo courtesy of Dawson City Museum

neers in the 1980s, and led to the development of a five-year project delivery cycle. The first year of the project delivery cycle is utilized for project planning. This is a necessary, but often time-consuming and expensive step to establish the required lines of communication between the various stakeholders in the project, and to refine the project needs, and the project resources. Time and expenses are due to the isolation of a project site, and the time needed to invest in understanding the cultural differences and needs of the end user. A simple visit to a project site may take a day or two of travel each way and cost thousands of dollars in airfare. The consultation with the end user is an essential part of the first year because neglecting this segment of the work may delay the project delivery, and lessen the overall success of the project. The second year of a project schedule is utilized for preliminary engineer-

ing and detailed design. These technical stages of the project may be characterized by the various technical activities with typical “southern” engineering such as geotechnical engineering, topographical surveys and background studies in advance of the design. However, these activities require special consideration of the inherent conditions of the Arctic such as permafrost. The design criteria that emerge from preliminary engineering include: careful consideration of cold temperatures, ice and snow, and how these are influenced by wind, darkness, and isolation. For example, the efficiency of outdoor winter construction in the Arctic may be reduced by 50%, due to the cold, and another 50% due to the darkness. In total, this means that winter construction may advance at about 25% of the summer working efficiency. The third and potentially fourth year of a project is utilized for project con-

Environmental Science & Engineering Magazine


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.