KAISER PERMANENTE - MORENO VALLEY

Diagnostic Treatment Center

The steel structure had just been erected in February 2022 (top right). The concrete was being poured over the metal decking in March 2021 when I joined the on-site construction administration team. After beginning work I have participated in frequent site walks, design coordination, RFI responses, submittal reviews, mock-up reviews, ACD preparation and submission, NAM form preparation and review, and meetings with HCAI field staff. This is a fast pace environment where answers to RFI’s are often coordinated before the RFI is formally processed. The C.A. Team shares an office with the Kaiser/owner’s rep. Project managers, the IOR’s, contractor’s and sub-contractor’s offices are a few steps away. The design consultants are each on site at least once a week. This proximity has allowed me to work closely with each actor to provide real time solutions to construction problems as they develop. Progress to date is shown on the bottom right image (February 2023).

Advertisement

SINCE JOINING THIS TEAM IN MARCH 2022: 482 Submittals have been processed. 684 RFI’S have been returned

065 ACD’S have been approved. 003 AMC’S have been reviewed

271 NMA forms have been reviewed.

CONSTRUCTION FINAL SCHEDULED FOR: APRIL 15, 2023

Floor Plan Legend

AREA NOT IN CONTRACT; EXISTING ITEMS TO REMAIN AND EXISTING SPACE TO REMAIN UNDISTURBED; FINISHES TO BE PROTECTED DURING DEMOLITION AND CONSTRUCTION. PATCH AND REPAIR AS NECESSARY.

This article is from: