DEPARTEMEN PEKERJAAN UMUM
DIREKTORAT JENDERAL SUMBER DAYA AIR
INDUK PELAKSANA KEGIATAN PENGEMBANGAN WILAYAH SUNGAI JRATUNSELUNA
Alamat: Jl. Brigjen S. Sudiarto 375, Telp. 723212-723070, Fax. 722239, Semarang
MONTHLY MEETING FOR WORK PROGRESS AND PRESENT CONDITION OF LODAN DAM SUBPROJECT PTSL-II Lodan, November 2006
Location Map
SLIDE-2
LAYOUT OF LODAN DAM
OVERALL PROGRESS • • • •
(as of October 2006) Physical Progress: 45% (~18% behind Schedule) Financial Progress: 38.56% (Rp. 13.086 billions) Contract Cost: Rp. 33,941,596,529.19 Construction Period: 450 out of 610 days (Aug 28-Apr 2007)
SLIDE-4
Construction Schedule and Progress of Lodan Dam & Main Irrigation Works Month: October 2006 Name of Contractor Contract No. Date of Contract
PT. Wijaya Karya KU.08.08/01/SKS PPSAJ/VI/2005 03 June, 2005
Source of Fund JBIC Approval (NRC) Notice to Proceed (NTP)
JBIC Loan No. IP-505 for PTSL-II July 25, 2005 August 1, 2005
GENERAL ITEM
33,941,596,529.19
2,721,708,364.00 Target up to this period Actual up to this period Actual up to previous period
DAM
10,032,448,457.18 Target up to this period Actual up to this period Actual up to previous period
SPILLWAY
9,112,182,938.91 Target up to this period Actual up to this period Actual up to previous period
4
OTHER DAM FACILITIES
5,171,760,226.74 Target up to this period Actual up to this period Actual up to previous period
5
MAIN IRRIGATION CANAL
1,309,010,309.26 Target up to this period Actual up to this period Actual up to previous period
6
7
MAIN IRRIGATION CANAL AND RELATED STRUCTURE WORKS
SECONDARY IRRIGATION
115,735,087.97 Target up to this period Actual up to this period Actual up to previous period
3,799,940,036.91 Target up to this period Actual up to this period Actual up to previous period
8
SECONDARY IRRIGATION CANAL AND RELATED STRUCTURE WORKS
1,678,811,108.22
Original
Actual
( % )
( % )
100.00
60.52
8.02
7.69
7.33 5.26 5.26 29.56
26.73
17.48 18.65 14.86 26.85
27.91
10.27 11.10 8.88 15.24
11.57
9.23 8.40 7.17 3.86
2.80
2.80 1.73 1.73 0.34
0.31
0.31 0.10 0.10
11.20
20.45
15.80 0.00 0.00
4.95
Target up to this period Actual up to this period Actual up to previous period
0.00 0.00 0.00
Total Target up to this period
#REF!
Total Actual up to this period
#REF!
Total Actual up to previous period
#REF!
2.54
0
1
Jul
Aug
100 98 96 94 92 90 88 86 84 82 80 78 76 74 72 70 68 66 64 62 60 58 56 54 52 50 48 46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0
0.20 0.34
Year 2005 2 3 Sep
0.70 1.05
Oct
1.63 2.79
0.31 0.38
0.95
4
5
6
7
8
9
10
Nov
Dec
Jan
Feb
Mar
Apr
May
2.71
1.33
0.46
(0.06)
0.54 1.43
0.05 0.94
1.34
0.01
0.19 0.64
0.36
0.01
0.91 0.41
0.43
0.04
0.27
1.68
0.01
0.32
0.54
4.35
0.20
0.10
0.69
0.89
0.20
0.32
1.82
0.42
0.11
1.55
1.05
0.18
0.01
2.47
1.04
2.00
Year 2006 11 12 Jun
Jul
0.23
0.20
0.04
0.18
1.99
2.56
0.09
0.78
0.81
0.21
1.20
0.86
0.28
1.29
1.46
1.34
13
14
15
16
17
18
19
Aug
Sep
Oct
Nov
Dec
Jan
Feb
0.20
0.04
0.01
0.47
0.00
3.88
2.13
2.07
0.95
3.74
3.79
0.23
3.35
1.87
2.10
3.16
2.22
0.34
0.05
0.44
0.79
0.88
1.24
0.01
0.01
0.01
0.11
0.91
1.91
2.08
1.73
2.39
5.18
6.24
3.83
0.85
1.14
0.01
0.28
0.38
Year 2007 20 21 22 Mar
0.11
Apr
May
0 Maintenance Period Jun
Jun
100 98 96 94 92 90 88 86 84 82 80 78 76 74 72 70 68 66 64 62 60 58 56 54 52 50 48 46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0
0.11
1.35
1.27
0.12
0.17
0.05
0.38
0.64
0.64
0.22
` ` `
0.32
2.32
0.15 0.59
0.00
0.00
0.17
0.08
0.06
0.06
0.07
0.08
0.01
0.07
0.94
0.01 0.01
2.89
3.41
4.41
0.02
3.55
1.55
4.65
(0.02)
` Final Hand Over Financial Accomplishment (Payment Progress) Physical Accomplishment (Actual Progress) Last Revised Projection (Schedule Progress)
Billion Rupiah
0.00
6.79
0.00
0.00
2.01
0.00
0.00
0.84
0.00
0.00
1.56
0.00
0.00
0.00
0.00
(%)
0.00
20.00
0.00
0.00
5.92
0.00
0.00
2.49
0.00
0.00
4.58
0.00
0.00
0.00
0.00
0.00
Accumulated Financial Accomplishment (%)
0.00
20.00
20.00
20.00
25.92
25.92
25.92
28.40
28.40
28.40
32.99
32.99
32.99
32.99
32.99
32.99
Billion Rupiah
0.00
0.12
0.49
1.27
1.00
0.30
0.22
0.69
1.47
0.23
0.66
0.97
1.07
1.30
3.11
2.46
(%)
0.00
0.34
1.43
3.74
2.95
0.88
0.64
2.03
4.35
0.69
1.94
2.86
3.16
3.84
9.17
7.25
Accumulated Physical Accomplishment (%)
0.00
0.34
1.77
5.51
8.45
9.33
9.97
12.00
16.35
17.04
18.98
21.83
24.99
28.83
38.00
45.25
Billion Rupiah
0.00
0.07
0.24
0.66
1.10
1.09
1.07
1.08
1.05
1.06
1.15
2.11
2.60
3.07
3.09
2.01
3.08
2.93
2.96
2.18
0.77
0.56
0.00
(%)
0.00
0.20
0.70
1.94
3.25
3.21
3.15
3.18
3.10
3.11
3.40
6.21
7.67
9.06
9.10
5.93
9.09
8.62
8.72
6.43
2.27
1.66
0.00
Accumulated Last Revised Projection (%)
0.00
0.20
0.90
2.84
6.08
9.29
12.45
15.63
18.73
21.85
25.24
31.45
39.13
48.18
57.29
63.22
72.30
80.93
89.65
96.07
98.34 100.00 100.00
0.00
SLIDE-5 *)
Reference:
Schedule Chart
Financial Accomplishment
Wet Season (irrigation period)
Physical Accomplishment Progress Chart
Last Revised Projection
Dry Season (un-irrigation period)
SCALE (%)
TOTAL CONTRACT AMOUNT (Excluding VAT) :
CONTRACT PRICE (Rp.)
SCALE(%)
DESCRIPTION OF WORKS
3
Figure - LDN TIME ELAPSE
WEIGHT
2
610 Calendar Days August 29, 2005 ~ May 1, 2007 Central Java Province
15,493,637,826.0000000000000
15,493,637,826.00
1
Contract Period Contract Effectiveness Project Location
Temporary Schedule
PRESENT SITE CONDITION
Present site condition
SLIDE-6
MAIN DAM (UPSTREAM VIEW)
Main Dam (View from upstream) Main Dam ( view from upstream )
SLIDE-7
MAIN DAM (DOWNSTREAM VIEW)
Main Dam (View from downstream
Main Dam ( view from downstream )
SLIDE-8
DOWNSTREAM SLOPE ADJUSTMENT
SLIDE-9
Slope adjustment of Downstream on Main Dam
SLOPE BLANKET AT LEFT-BANK
SLIDE-10
SLOPE BLANKET AT RIGHT BANK
SLIDE-11
INSTRUMENT HOUSE
Completed Instrumentation House
SLIDE-12 Completed Monitoring Panel
SPILLWAY-SIDECHANNEL
VIEW FROM UPSTREAM
VIEW FROM DOWNSTREAM
SLIDE-13
SPILLWAY-DOWNSTREAM
CONNECTION OF SPILLWAY
EXCAVATION AROUND
WITH EXISTING RIVER
STILLING BASIN
SLIDE-14
TREATMENT OF EXISTING RIVER
EXISTING WATER-SUPPLY PIPE
Treatment of Existing River
SLIDE-15
INCLINED INTAKE
Inclined Intake and Intate Box
SLIDE-16
ACCESS ROAD BRIDGE AND DOWNSTREAM WEIR
SLIDE-17
Access Bridge and Weir in existing River
BATCHING PLANT
Batching Plant
RIGHT BANK HILL
Cliff on Right Bank
SLIDE-18
IRRIGATION SYSTEM CONCRETE LINING (UPSTREAM REACH OF MAIN CANAL
Completed Main Canal ( Concrete lining )
STONE MASONRY LINING (DOWNSTREAM REACH OF MAIN CANAL)
Completed Main Canal ( Stone masonry with Plastering )
SLIDE-19
IRRIGATION SYSTEM EXISTING STONE MASONRY LINING (MIDDLE REACH OF MAIN CANAL)
Existing Main Canal ( Not start yet )
SLIDE-20
IRRIGATION SYSTEM-SECONDARY CANAL STONE MASONRY LINING (UPSTREAM REACH OF LODAN KULON
Completed Secondary canal on Lodan Kiri
STARTING POINT OF LODAN WETAN (NOT YET STARTED)
Secondary canal on Lodan Wetan ( Not start yet )
SLIDE-21
HEAVY EQUIPMENT MONITORING
Heavy Equipment operation on September and October Operation
Broken
SLIDE-22
COMPLETED EMBANKMENT WORKS
Completed Embankment on Main Dam
Completed Embankment on Slope Blanket
SLIDE-23