City of Durham, North Carolina FY 2011 2016
Capital improvement plan FY 2018 – 2023
Durham – Where Great Things Happen
MAYOR William V. “Bill” Bell CITY COUNCIL Cora M. Cole-McFadden Eddie Davis Jillian Johnson Don L. Moffitt Charlie Reece Steve Schewel CITY MANAGER Thomas J. Bonfield CIP COORDINATOR Christina Tookes CIP ADVISORY COMMITTEE Bertha T. Johnson, Budget and Management Services John J. Allore, Budget and Management Services Bethany Shewmaker, Budget and Management Services Christina Tookes, Budget and Management Services W. Bo Ferguson, City Manager’s Office Kathy Compton, Finance Christopher Iannuzzi and Andy Sannipoli, Fire Joe Clark, Fleet Robyn Heeks, Jina Propst and Henri Prosperi, General Services Chris Dickey, Office of Economic and Workforce Development Thomas Dawson, Parks and Recreation Sara Young, Planning Bill Gascoigne, Police Lorie Fillyaw and Marvin Williams, Public Works Brian Green, Technology Solutions Ellen Beckmann, Thomas Leathers and Bill Judge, Transportation Jerry Morrone, Water Management SPECIAL THANKS TO Vivienne Bass, Executive Assistant, Budget and Management Services April French and Peggy McFarland, Finance Ronald Dunbar, Jeff Faucette and John Stinson, Technology Solutions
Cover Design by: Docusource of North Carolina Pictures by: Briana Brough, Durham Magazine & Durham Public Affairs Office Printing and Duplication by: Docusource of North Carolina
Durham – Where Great Things Happen
City Vision Statement Durham is the leading city in providing an excellent and sustainable quality of life.
City Mission Statement To provide quality services to make Durham a great place to live, work and play.
Council Goals Strong and Diverse Economy Safe and Secure Community Thriving Livable Neighborhoods Innovative & High Performing Organization Stewardship of City’s Physical and Environmental Assets
About the Cover William V. “Bill” Bell stepped into Durham politics 45 years ago. He wanted to maximize Durham's economy, education and other resources, believing that government best serves citizens by partnering with them and the private sector. Mayor Bell, a retired IBM Senior Engineer, and currently the Executive Vice-President/COO of UDI Community Development Corporation (UDI/CDC), served as an elected Durham County Commissioner for 26 years, and Chairman of the Durham Board of County Commissioners for 12 years. As Chairman of the Durham County Board of Commissioners he was recognized as the architect of the 1992 merger of the then "Durham City Schools System" and the then "Durham County School System" into the now "Durham Public School System" (DPS). He was elected Mayor of Durham, NC in 2001 and is the longest serving Mayor in Durham's history. Mayor Bell’s milestones during his tenure include the revitalization of Northeast Central Durham and much of the Southside community. DPAC and the American Tobacco Campus were successfully completed through a combination of public/private partnerships. He began a data-driven Poverty Reduction Initiative in Northeast Central Durham and he is very supportive of the Durham Orange Light Rail Project. Over the years, Mayor Bell served on numerous local, state, national boards and committees, and has been the recipient of many local, state and national awards and honors.
Thank you for your service Mr. Mayor, and best wishes!!
CITY OF DURHAM CAPITAL IMPROVEMENT PROGRAM PROCESS The Capital Improvement Program (CIP) is a statement of the City of Durham's policy regarding longrange capital asset development. It is vital to the City because it is the principal planning tool designed to achieve urban growth and development. This program strategically focuses on projects for a six year period and is updated and revised annually. To be included in the CIP, a project should require a total expenditure of at least $100,000. By providing a planned schedule, cost estimates, and location of public sector improvements, the Capital Improvement Program provides private sector decision makers with valuable information upon which to base investment decisions. It also provides local elected officials and the public with valuable information concerning proposed public facilities and their associated costs. Ultimately, this coordination of orderly and efficient programs of private and public investment will benefit the City. The 2018 CIP Process For the preparation of the FY2018-23 CIP the City continues its strategic prioritization process in the selection of capital projects. The process involves the participation of senior management, the internal CIP advisory committee, and the Citizen Capital Improvement Panel (CCIP). Keys to ensuring that the City’s capital needs will continue to be met under restrictive financial limitations include asset management, effective project costing, and ongoing prioritization of capital projects. CIP Preparation The CIP process includes a professional analysis of projects, the guidance of citizens, businesses, and community leaders, and the leadership of the City Manager and City Council to produce a sound CIP for FY 2018-2023. The City also maintains a web-based application that allows citizens to view an update on all capital projects at: http://ww2.durhamnc.gov/cip/. CIP PROCESS The FY 2018-23 CIP process included the participation of the CIP Advisory Committee and a Citizen Capital Improvement Panel (CCIP). The CIP Advisory Committee consists of representatives from across the organization charged with: 1. Aligning projects with identified master and strategic plans. 2. Identifying issues that may be barriers to successful project management. 3. Strengthening cross-functional communication between internal project managers. 4. Focusing on continuous improvement in the Capital Improvement process. The Scoring Team was composed of CIP Internal Committee members who are City staff with professional expertise in the range of project categories. The team was charged with: 1. Reviewing and refining the project scoring matrix. 2. Guiding departments through the project scoring process. 3. Ensuring consistency, fairness, and objectivity through the scoring and ranking process. The Citizen Capital Improvement Panel (CCIP) is composed of business and community leaders charged with: 1. Helping City staff prioritize the right combination of new capital improvement projects. 2. Advising the City Council of the most critical CIP projects to meet the City’s ongoing needs. 3. Evaluating and recommending projects for funding in the Capital Improvement Plan. The Budget and Management Services Department (BMS) initiated the CIP process by soliciting proposals from departments for capital project needs within the scope of their operations. The CIP Advisory Committee assisted with the identification of projects. Departments scored their own projects
using the refined scoring matrix. Department staff presented their rationale for project scores to the Scoring Team, who then reviewed all project scores and modified scores to ensure consistency and objectivity. While the Scoring Team managed the internal review and assessment of requested projects, the CCIP received a presentation on capital project needs, and developed guiding principles by which projects are prioritized. The FY 2018-23 CIP includes approximately $176.1 million for capital projects funded through impact fees, enterprise funds, grants, the capital project fund, pay-go funding, and debt financings. The majority of these projects are enterprise fund projects. The recommendations of the CIP Advisory Committee, the Scoring Team, and the CCIP were submitted to the City Manager for review and were presented to the City Council. The Plan was adopted by the City Council on June 19, 2017. GOALS OF THE CIP The CIP is prepared with the guidance of two major goals: 1.
To address the City's immediate and long-term capital needs, especially those related to: • • • • •
2.
Maintaining the existing infrastructure in order to protect the City's investments. Expanding the tax base in a way that will benefit both future and current citizens. Managing and encouraging orderly growth in compliance with the Comprehensive Plan. Providing City services in the most efficient and safe manner. Maintaining and improving the quality of life in a way that enhances the perception of the community by citizens and potential investors.
To explore all feasible funding sources (as time and resources permit) in order to finance the City's capital needs.
The CIP is also prepared with the guidance of the five adopted goals of the City Council: • • • • •
A Strong and Diverse Economy Safe and Secure Community Thriving Livable Neighborhoods Innovative and High Performing Organization Stewardship of City’s Physical and Environmental Assets
FUNDING PRIORITIES Projects with the following characteristics are given priority for funding: • • • • • • •
Public health and public safety – prevents or corrects a major or minor health or safety hazard. Legal requirement – clearly demonstrates a mandate by State or Federal law. Major deferred maintenance on existing, large infrastructure/facilities – lack of project will likely result in compounded repair costs in the future and/or materially disrupts the enjoyment of the facilities. Economic development – directly increases net annual revenues and creates indirect community wealth, e.g. jobs, business retention, etc. Cultural, social, or leisure demand – directly addresses a major cultural, social, or leisure demand. Operating budget impact – directly reduces operating costs or is eligible for available funding sources. Extent of primary service area – serves the entire City.
• • • • • • •
Relationship to other projects – completes a project that is underway or advances the effectiveness of another project. Comprehensive and/or strategic plans or policies – is consistent with the City’s existing long range strategic plans. Equitable distribution – considers geographic, environmental and socio-economic balance. Green projects – uses sustainable environmental building principles and minimizes traffic and sprawl. Joint use – combines two or more projects in the same site or facility resulting in immediate or future savings. Enhance artistic/cultural heritage – preserves existing cultural activities and historic features of the community or attracts new beneficial cultural and artistic activities. Best practices – maintains the City’s systems or facilities for delivering services and information to the public.
RELATIONSHIP OF THE CIP TO THE OPERATING BUDGET The operating budget and the CIP are closely related. The CIP is a program that matches the City's major capital needs with the financial ability to meet those needs. As a plan, it is subject to change. However, a sound and reliable CIP is critical to maintaining the good financial health of the City. CIP projects that are proposed to be funded via the General Fund, Water and Sewer Fund and Stormwater Fund are intended to be included in the annual budget in the appropriate year(s). Even so, because circumstances may change between the adoption of the CIP and the annual budget, CIP projects must be resubmitted as part of each department's annual Capital Improvement budget request. Funds for such projects are not available unless and until they are included by specific ordinance in the annual budget approved by the City Council. The needs greatly outpace the resources available to address adequately, so many projects are deferred each year. Projects with revenue sources showing as “Unidentified” have no set funding source and must compete for the same limited resources each year. In many cases, the completion of capital projects will impact a department's operating budget as projects are completed and require maintenance and upkeep. Some facilities may require additional utilities, such as electricity and water, above current consumption levels – an impact may not be readily evident when projects are funded and then constructed over several years. Consequently, the impacts of capital projects on the annual operating budget are estimated when available and noted in the CIP under each project. Most projects will not have an operating impact in the year during which they are funded since this is typically the construction/installation phase. Also, if a project is a renovation which does not include expansion and the operating costs are already captured in the department’s annual operating budget, no additional operating costs will be listed. RELATIONSHIP OF THE CIP TO IMPLEMENTATION OF PLANNING AND GROWTH MANAGEMENT POLICIES It is essential that CIP project proposals support plans and policies previously adopted by the City Council in order to coordinate and direct the physical development of the City. In evaluating each CIP proposal, particular attention is given to the conformity of proposals with the strategic plan, the City's broadest overall policy and planning tool for managing growth. CIP CATEGORIES I.
Culture and Recreation. Projects in this category are related to enhancing the cultural and recreational opportunities for city residents, including park and recreation center renovations, the construction of new parks, playgrounds, trails, and athletic fields. This year’s CIP included funding to continue Aquatic Updates/Upgrades to city pools, Bryant Bridge South Trail, Valley Springs Park, Campus Hills Recreation Center Roof Replacement and the continuation of the cultural public art fund.
II.
Downtown Revitalization. Projects in this category provide for the revitalization and enhancement of downtown Durham.
III.
General Services. Projects in this category are related to city buildings and facilities. This year’s CIP includes the continuation of a comprehensive long-term fleet replacement plan and year (2) of the Police Take Home Vehicle program, energy management efforts and continues critical security upgrades to city facilities.
IV.
Public Protection. Public protection projects will enhance the City’s ability to protect lives and property through police, fire, and emergency communication services. Projects in this category include deferred maintenance corrections at police and fire facilities and the renovation of cityowned buildings. This year’s CIP includes funding for critical Public Safety Radio Replacements.
V.
Solid Waste. This category contains funding for Solid Waste Management projects. This year’s CIP includes funding for the purchase of Solid Waste fleet vehicles.
VI.
Stormwater. Projects in this category are designed to address and improve stormwater flow throughout the City. Projects capture the City’s efforts to correct sustained damage resulting from defective and malfunctioning city lines. This year’s CIP includes funding for future watershed planning and design, major stormwater infrastructure improvements, and funding for Stormwater fleet replacement vehicles.
VII.
Technology. This category contains projects that improve the technological capabilities of the City, producing a more innovative, efficient and accountable government.
VIII.
Transportation. Transportation projects provide street, thoroughfare, sidewalk, and mass transit improvements by constructing new infrastructure or making significant improvements to the City’s existing roadway and sidewalk network. This year’s CIP includes funding for street paving and maintenance, construction of new sidewalks, continues the Duke Belt Line Trail project, and continues to address Failed and Struggling Development infrastructure projects.
IX.
Water. Projects in this category are related to water treatment projects such as Jordan Lake, maintenance such as Water Distribution System Rehabilitation, or water regulatory improvements.
X.
Wastewater. Projects in this category are related to maintenance such as the Sewer Collection System Rehabilitation, or improvement of the City’s sanitary sewer collection and treatment system. Funding for projects this fiscal year will come from the Capital Facilities Fee Fund, Water and Sewer Fund operating revenues and revenue bonds. This year’s CIP includes funding for Water & Sewer fleet replacement vehicles and wastewater process rehabilitation at Lake Michie and Little River.
XI.
Other Enterprise Funds. Projects in this category are specific to unique enterprise funds that were established to address capital infrastructure needs for the Parking Fund and Transit Fund. This year’s CIP included funding for deferred maintenance upgrades to the Parking Garages, design of a new Downtown Parking Garage, Parking Security Upgrades and the continuation of Transit Fund Fleet purchases.
REVENUE SOURCES The City of Durham uses many revenue sources to finance capital projects. The planned uses of these sources are reflected in the FY 2018-2023 Capital Improvement Program. The following describes the City's major revenue sources:
Pay-As-You-Go This funding originates from revenue generated from the General Fund and the Capital Projects Fund, or from enterprise fund appropriations made in the City's annual operating budget. Typically, these appropriations are transferred to the Capital Projects Fund for accounting purposes if the project period lasts more than one fiscal year. CIP projects that are proposed to be funded via the annual operating budget are intended to be included in the annual budget in the appropriate year. Funds for such projects are not available unless and until they are approved by the City Council. General Obligation Bond The City may borrow money from lenders, pledging the full faith and credit of the City to pay the loan through property tax revenue. This method generally requires both the approval of voters through a referendum and the approval of the Local Government Commission. The City's voters approved referenda during November 1996, November 2005, November 2007, and November 2010 to finance capital projects with general obligation bonds. The City sells general obligation bonds to pay for expenses associated with capital projects. Bond sales are held as needed. The City may issue general obligation debt under the two-thirds rule, wherein the City may issue up to two-thirds the value of the general obligation debt retired in the prior year so long as no new general obligation debt was issued in the same year. Revenue Bond The City may borrow money from lenders, pledging the revenues generated from the specific operations of the project to pay the debt. Because of the nature of the security, revenue bonds do not require voter approval. Like general obligation bonds, the City sells revenue bonds as needed to pay for expenses associated with capital projects. Installment Sales The City may enter into an installment sales (Certificates of Participation) contract for a building or for equipment using that building or equipment to secure the financing, similar to a mortgage transaction. The City does not pledge the use of its taxing power to pay the contract. The Local Government Commission must approve the use of installment sales contracts. Impact Fees Impact fees are one-time charges levied against new development based on the impact on city infrastructure as determined by the land use of the project. The impact fees will be used as a funding source for a proportionate cost of capital facilities and land made necessary by new construction. Impact fees cannot be used for routine or periodic maintenance, or improvements made to the existing infrastructure where the improvements are not related to new development. The City’s impact fees are collected in three zones for streets, parks and recreation facilities, and open space land; Street Zone 4 (Southwest Durham), Street Zone 5 (Northeast Durham), Street Zone 6 (Downtown), Recreation and Open Space Zone 1 (Southwest Durham), Recreation and Open Space Zone 2 (East Durham) and Recreation and Open Space 3 (North Durham). Impact fees will be used only to serve the zone where the fees were collected. The revenue must be appropriated within ten years or returned to the developer. The expenditure of this revenue is programmed with the CIP cycle. Intergovernmental Revenues This category of revenues identifies funding from Durham County, the State of North Carolina, and the Federal Government. The funding sources include the State's revolving loan fund for wastewater treatment plants, state and federal funding for transportation and transit-related improvements. Project pages also show Community Development Block Grant and HOME funds in Housing CIP projects for informational purposes.
Other Capital projects may be fully or partially funded through miscellaneous revenue sources not referenced above. Examples of other funding sources include program revenues, land sales or contributions, payments in lieu of taxes, private contributions, loan repayments, and rental income. Unidentified Projects that do not have an identified source of future revenue to fund them are listed here. These projects usually compete for a small pool of general fund dollars, though some may later be determined to be eligible for use of impact fees or certificates of participation. These projects are also candidates for inclusion in future general obligation bond referendums. Completed Projects The following CIP projects were completed during FY 2017: Culture and Recreation • Aquatics Upgrades – City Wide Master Plan • Aquatic Updates (Pools) – Dehumidifier Units • Indian Trail Park Playground Updates • Snow Hill Road Park – Expansion Study • Twin Lakes Park – Soccer Field Renovation
Public Protection • Fire Station #1 Upgrades • Fire Station #9 • Fire Admin Building Upgrades – Roof, HVAC Parking Fund • On-Street Parking Upgrades • Parking Garage – Elevator Modifications
CITY OF DURHAM CAPITAL IMPROVEMENT PROGRAM FY 2018 - 2023 CAPITAL IMPROVEMENT PROGRAM SUMMARY
SUMMARY BY PROJECT CATEGORY Category
Prior Year
Culture & Recreation Downtown Revitalization General Services Other Enterprise Funds Public Protection
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
8,694,560
1,560,000
2,581,329
4,439,727
20,000
20,000
20,000
0
17,335,616
250,000
0
0
0
0
0
0
0
250,000
32,543,000
7,945,342
0
0
0
0
0
0
40,488,342
10,241,000
20,595,288
0
0
0
0
0
0
30,836,288
71,822,639
2,000,000
2,000,000
0
3,212,202
3,308,568
0
0
82,343,409
Solid Waste
9,416,787
3,934,756
0
0
0
0
0
0
13,351,543
Stormwater
32,489,136
3,904,816
9,800,000
8,650,000
7,900,000
5,425,000
0
0
68,168,952
Technology
1,751,556
0
0
0
0
0
0
0
61,958,947
13,519,465
10,506,593
8,400,407
15,223,789
10,813,608
14,782,638
1,500,000
136,705,447
Wastewater
278,040,295
76,150,000
16,744,360
45,840,160
37,541,400
38,763,780
36,400,000
0
529,479,995
Water
249,157,966
46,588,056
33,110,000
17,345,000
120,079,999
5,950,000
5,200,000
0
477,431,021
Transportation
$756,365,886
$176,197,723
$74,742,282
$84,675,294 $183,977,390
$64,280,956 $56,402,638
1,751,556
$1,500,000
$1,398,142,169
SUMMARY BY REVENUE SOURCE Source
GOB Authorized GOB Unauthorized Impact Fees
Prior Year
FY 2017-18
FY 2018-19
14,146,856
0
0
7,054,301
0
0
FY 2019-20
Future Years
Total Funds
FY 2020-21
FY 2021-22
FY 2022-23
0
0
0
0
0
0
0
0
0
0
7,054,301
0
0
0
0
29,304,819
14,146,856
26,571,919
2,732,900
0
0
Installment Sales
101,259,019
33,998,267
2,968,602
4,000,000
0
2,388,105
11,683,802
0
156,297,795
Intergovernmental
19,860,178
0
0
0
0
0
0
0
19,860,178
Other
55,721,809
6,032,988
5,000,000
6,000,000
7,000,000
0
0
0
79,754,797
Pay-As-You-Go
129,577,684
47,583,568
37,710,000
30,050,000
14,750,000
9,825,000
4,400,000
0
273,896,252
Rev Authorized
9,533,654
0
0
0
0
0
0
0
9,533,654
392,640,466
83,600,000
21,944,360
41,785,160
150,771,399
40,313,780
37,200,000
0
768,255,165
0
2,250,000
7,119,320
2,840,134
11,455,991
11,754,071
3,118,836
1,500,000
40,038,352
$756,365,886
$176,197,723
$74,742,282 $84,675,294 $183,977,390 $64,280,956 $56,402,638
$1,500,000
$1,398,142,169
Rev Unauthorized
Unidentified
Culture & Recreation Table of Contents Project Title
Page
Culture & Recreation: Summary By Project Culture & Recreation: Summary By Revenue Source Athletic Court Renovations Athletic Field Upgrades - Snowhill Road Park ATT Parking Lot at Scott King Road Birchwood Park Upgrades - Parking Lot Campus Hills Baseball Field Lighting Project Campus Hills Recreation Center - Roof Replacement Crest St. Park (Baseball Field Lights) DPR Restroom Long Meadow Park Edgemont Park - Playground Equipment Future Trails Herndon Park Artificial Turf Soccer Field Lyon Park Restroom Project Public Art Fund R. Kelly Bryant Bridge South Trail Rock Quarry Park Upgrades Twin Lakes Park Upgrades (Feasibility Study) West Ellerbee Creek Trail - Phase II
I-1 I-2 I-3 I-4 I-5 I-6 I-7 I-8 I-9 I - 10 I - 11 I - 12 I - 13 I - 14 I - 15 I - 16 I - 17 I - 18 I - 19
Sherwood Park Futsal Courts Indian Trail Park Equipment
Red Maple Park Basketball Courts
Program Category: Culture & Recreation SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
Athletic Court Renovations
2,675,460
0
0
419,727
0
0
0
0
3,095,187
Athletic Field Upgrades Snowhill Rd. Park
550,000
0
0
0
0
0
0
0
550,000
ATT Parking Lot at Scott King Road
100,000
0
0
0
0
0
0
0
100,000
Birchwood Park Upgrades Parking Lot
160,000
0
0
0
0
0
0
0
160,000
0
250,000
0
0
0
0
0
0
250,000
Campus Hills Recreation Center Roof Replacement
250,000
0
0
0
0
0
0
0
250,000
Crest St. Park (Baseball Field Lights)
235,000
0
0
0
0
0
0
0
235,000
DPR Restroom Long Meadow Park
250,000
0
0
0
0
0
0
0
250,000
Edgemont Park Playground Equipment
200,000
0
0
0
0
0
0
0
200,000
0
850,000
0
4,000,000
0
0
0
0
4,850,000
900,000
0
1,639,091
0
0
0
0
0
2,539,091
0
135,000
0
0
0
0
0
0
135,000
Public Art Fund
70,000
75,000
20,000
20,000
20,000
20,000
20,000
0
245,000
R. Kelly Bryant Bridge South Trail
557,500
0
422,238
0
0
0
0
0
979,738
Rock Quarry Park Upgrades
0
250,000
500,000
0
0
0
0
0
750,000
Twin Lakes Park Upgrades (Feasibility Study)
725,000
0
0
0
0
0
0
0
725,000
2,021,600
0
0
0
0
0
0
0
2,021,600
$8,694,560
$1,560,000
$2,581,329
$4,439,727
$20,000
$20,000
$0
$17,335,616
Campus Hills Baseball Field Lighting Project
Future Trails Herndon Park Artificial Turf Soccer Field
Lyon Park Restroom Project
West Ellerbee Creek Trail Phase II
I-1
$20,000
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
2,159,091
439,727
20,000
20,000
20,000
0
2,658,818
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
55,000
0
0
0
0
0
0
0
55,000
Other
90,000
75,000
0
0
0
0
0
0
165,000
Intergovernmental
1,081,600
0
0
0
0
0
0
0
1,081,600
Installment Sales
4,244,960
1,235,000
422,238
4,000,000
0
0
0
0
9,902,198
Impact Fees
2,598,000
250,000
0
0
0
0
0
0
2,848,000
0
0
0
0
0
0
0
0
0
625,000
0
0
0
0
0
0
0
625,000
$8,694,560
$1,560,000
$2,581,329
$4,439,727
$20,000
$20,000
$20,000
$0
$17,335,616
GOB Unauthorized GOB Authorized
I-2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Durham Parks and Recreation-
All
Project Title
Pin Number
Master Plan
Athletic Court Renovations
0832-20-70-9137
Project Description Continue ongoing resurfacing of existing tennis and basketball courts throughout the City.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$2,168,843
TYPE REQUEST
Beginning
07/15
Completion
12/20
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$3,095,187
Construction
$2,675,460
$0
$0
$419,727
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,675,460
$0
$0
$419,727
$0
$0
$0
$0
$3,095,187
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$2,675,460
Total Revenue Installment Sales
Prior Year
2022-23
$2,675,460
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$419,727
$0
$0
$0
$0
$419,727
$2,675,460
$0
$0
$419,727
$0
$0
$0
$0
$3,095,187
Total
I-3
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Culture & Recreation
General Services
Project Title
Pin Number
Athletic Field Upgrades - Snowhill Rd. Park
0835-01-15-8482
District: 2
Master Plan
Project Description The feasibility study will address site characteristics and regulatory requirements of the 117 acre property on Snow Hill Road. Two concept plan options for additional park amenities on the athletic field parcel, and cost estimates will be included. First phase included ongoing field irrigation and lighting upgrades.
PROJECT STATUS -
Appropriation Planning/Design Construction Equip/Furnishings Contingency
Total
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$295,172
TYPE REQUEST
Beginning
07/15
Completion
09/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
$0
$0
$0
$0
$0
$0
$0
$0
$500,000
$0
$0
$0
$0
$0
$0
$0
$500,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$50,000
$0
$0
$0
$0
$0
$0
$0
$50,000
$550,000
$0
$0
$0
$0
$0
$0
$0
$550,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL $550,000
Revenue
Prior Year
Installment Sales
$550,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$550,000
$0
$0
$0
$0
$0
$0
$0
$550,000
Unidentified
Total
I-4
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
DPR
4
Project Title
Pin Number
Master Plan
ATT Parking Lot at Scott King Road
0717-04-94-0106
Project Description Funding designated for the construction of a parking lot with accessible spaces for trail users. Project addresses inadequate parking at Herndon Park and alleviates parking along Scott King Road.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$49,540
TYPE REQUEST
Beginning
07/14
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$100,000
$0
$0
$0
$0
$0
$100,000
$0
$0
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$100,000
$0
$0
$100,000
Future Years
TOTAL $100,000
2022-23
Revenue
Prior Year
Impact Fees
$100,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$100,000
$0
$0
$0
$0
$0
$0
$0
$100,000
Intergovernmental
Total
I-5
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Culture & Recreation
General Services
Project Title
Pin Number
Birchwood Park Upgrades - Parking Lot
0841-19-61-5835
District:
Master Plan
Project Description Currently there is no parking lot for this park. This funding will provide a paved parking lot for residents to access the park.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$45,340
TYPE REQUEST
Beginning
07/16
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$160,000
$0
$0
$0
$0
$0
$160,000
$0
$0
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$160,000
$0
$0
$160,000
Future Years
TOTAL
2022-23
Revenue
Prior Year
Impact Fees
$160,000
$0
$0
$0
$0
$0
$0
$0
$160,000
$160,000
$0
$0
$0
$0
$0
$0
$0
$160,000
Total
I-6
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Park Maintenance
4
Project Title
Pin Number
Master Plan
Campus Hills Baseball Field Lighting Project
2013 Parks Master Plan
Project Description FY18 funding will provide for installation of sports lighting to serve the baseball field at Campus Hills Park.
PROJECT STATUS -
PROJECTED DATES:
Total Expenditures
Appropriation Construction
Prior Year
$0
TYPE REQUEST
Beginning
07/17
Completion
06/18
New
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
$250,000
$0
$0
$0
$0
$0
$0
$250,000
Total
$0
$250,000
$0
$0
$0
$0
$0
$0
$250,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$250,000
$0
$0
$0
$0
$0
$0
$250,000
$0
$250,000
$0
$0
$0
$0
$0
$0
$250,000
Installment Sales
Total
I-7
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Recreation Centers/Aquatics
4
Project Title
Pin Number
Master Plan
Campus Hills Recreation Center Roof Replacement
0830-14-24-3928
Durham Parks and Recreation Master Plan 2013
Project Description This project would resolve recurring building roof leaks by replacing the existing membrane roof at the Recreation Center building at Campus Hills Park. The work would include removal of existing ballast stone (which will be salvaged for site use by Parks & Recreation), removal and disposal of existing membrane and metal flashings and installation of new roofing system, flashing, sealants and edge trim metal.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$0
TYPE REQUEST
Beginning
07/16
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$250,000
$0
$0
$0
$0
$0
$250,000
$0
$0
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$250,000
$0
$0
$250,000
Future Years
TOTAL
2022-23
Revenue
Prior Year
Installment Sales
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
Total
I-8
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Athletics / Programming
3
Project Title
Pin Number
Master Plan
Crest St. Park (Baseball Field Lights)
0812-16-83-4442
2013 DPR Master Plan
Project Description Funding will install sports field lighting on the athletic field at Crest St. Park; replacement of the existing galvanized fencing with vinyl coated chain link fencing and providing an accessible concrete walkway.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$7,800
TYPE REQUEST
Beginning
07/15
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$235,000
$0
$0
$0
$0
$0
$235,000
$0
$0
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$235,000
$0
$0
$235,000
Future Years
TOTAL
2022-23
Revenue
Prior Year
Impact Fees
$235,000
$0
$0
$0
$0
$0
$0
$0
$235,000
$235,000
$0
$0
$0
$0
$0
$0
$0
$235,000
Total
I-9
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
DPR
1
Project Title
Pin Number
Master Plan
DPR Restroom Long Meadow Park
0831-10-46-3598
Project Description Installation of pre-fabricated restroom building at Long Meadow Park.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$46,750
TYPE REQUEST
Beginning
07/14
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$250,000
$0
$0
$0
$0
$0
$250,000
$0
$0
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$250,000
$0
$0
$250,000
Future Years
TOTAL
2022-23
Revenue
Prior Year
Impact Fees
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
Total
I - 10
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
DPR
1
Project Title
Pin Number
Master Plan
Edgemont Park - Playground Equipment
0831-13-14-9447
Project Description Project funded in FY15 for acquisition of adjoining property lots and the installation of new park equipment. Property acquired in FY17. Planning stage for project initiated.
PROJECT STATUS -
Appropriation Land Equip/Furnishings
Total
Prior Year
PROJECTED DATES:
June 2017
Total Expenditures
$35,216
TYPE REQUEST
Beginning
07/14
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$50,000
$0
$0
$0
$0
$0
$0
$0
$50,000
$150,000
$0
$0
$0
$0
$0
$0
$0
$150,000
$200,000
$0
$0
$0
$0
$0
$0
$0
$200,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Revenue
Prior Year
Impact Fees
$200,000
$0
$0
$0
$0
$0
$0
$0
$200,000
$200,000
$0
$0
$0
$0
$0
$0
$0
$200,000
Total
I - 11
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
General Services
DPR - Planning
All
Project Title
Pin Number
Master Plan
Future Trails
2013 DPR Master Plan
Project Description Funding is planned for future trail development such as Bryant Bridge North, Pearsontown Trail, Third Fork Creek Trail, Sandy Creek Trail and North Ellerbee Creek Trail.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/17
Completion
07/24
New
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
$850,000
$0
$4,000,000
$0
$0
$0
$0
$4,850,000
Total
$0
$850,000
$0
$4,000,000
$0
$0
$0
$0
$4,850,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$850,000
$0
$4,000,000
$0
$0
$0
$0
$4,850,000
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$850,000
$0
$4,000,000
$0
$0
$0
$0
$4,850,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
I - 12
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
DPR
4
Project Title
Pin Number
Master Plan
Herndon Park Artificial Turf Soccer Field
0717-04-94-0106
Parks & Recreation Facilities Master Plan
Project Description Funding designated for converting tournament soccer field to artificial turf for durability and longevity.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$789,089
TYPE REQUEST
Beginning
07/14
Completion
12/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$900,000
$0
$1,639,091
$0
$0
$0
$900,000
$0
$1,639,091
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$2,539,091
$0
$0
$2,539,091
Future Years
TOTAL
2022-23
Revenue
Prior Year
Impact Fees
$900,000
$0
$0
$0
$0
$0
$0
$0
$900,000
Unidentified
$0
$0
$1,639,091
$0
$0
$0
$0
$0
$1,639,091
$900,000
$0
$1,639,091
$0
$0
$0
$0
$0
$2,539,091
Total
I - 13
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Parks and Recreation
3
Project Title
Pin Number
Master Plan
Lyon Park Restroom Project
0821-14-44-3838
Project Description The existing restroom will be demolished and placement of a new prefabricated structure will occur.
PROJECT STATUS -
PROJECTED DATES:
Total Expenditures
Appropriation
Prior Year
$0
TYPE REQUEST
Beginning
07/17
Completion
06/18
New
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
Planning/Design
$0
$25,000
$0
$0
$0
$0
$0
$0
$25,000
Construction
$0
$100,000
$0
$0
$0
$0
$0
$0
$100,000
Contingency
$0
$10,000
$0
$0
$0
$0
$0
$0
$10,000
Total
$0
$135,000
$0
$0
$0
$0
$0
$0
$135,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$135,000
$0
$0
$0
$0
$0
$0
$135,000
$0
$135,000
$0
$0
$0
$0
$0
$0
$135,000
Installment Sales
Total
I - 14
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Culture & Recreation
Economic & Workforce Devel
Project Title
Pin Number
District: All
Master Plan
Public Art Fund
Project Description Continues dedicated funds for city public art. Annually, a portion of CIP project funding is appropriated for this purpose.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
$0
TYPE REQUEST
Beginning
11/12
Completion
05/24
Continuation
Appropriation
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Planning/Design
2022-23
Future Years
TOTAL
$70,000
$75,000
$20,000
$20,000
$20,000
$20,000
$20,000
$0
$245,000
Total
$70,000
$75,000
$20,000
$20,000
$20,000
$20,000
$20,000
$0
$245,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL $55,000
2022-23
Pay-As-You-Go
$55,000
$0
$0
$0
$0
$0
$0
$0
Other
$15,000
$75,000
$0
$0
$0
$0
$0
$0
$90,000
$0
$0
$20,000
$20,000
$20,000
$20,000
$20,000
$0
$100,000
$70,000
$75,000
$20,000
$20,000
$20,000
$20,000
$20,000
$0
$245,000
Unidentified
Total
I - 15
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Recreation-Trails and Greenwa
1
Project Title
Pin Number
Master Plan
R. Kelly Bryant Bridge South Trail
0820-12-85-3590
Project Description A Design and Construction Project that will develop a new 1.11 mile trail between the R. Kelly Bryant Bridge at NC 147 and the Rocky Creek Trail at Dakota St./NC 55.
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design
$173,500
Land
$384,000
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$50,000
2017-18
TYPE REQUEST
Beginning
07/16
Completion
06/20
Continuation
Future Years
TOTAL
$0
$0
$173,500
$0
$0
$806,238
$0
$0
$0
$0
$0
$0
$0
$0
$979,738
2019-20
2020-21
2021-22
Future Years
TOTAL
2018-19
2019-20
2020-21
2021-22
$0
$0
$0
$0
$0
$0
$422,238
$0
$0
$0
$0
$0
$0
$0
$0
$557,500
$0
$422,238
$0
2017-18
2018-19
2022-23
Revenue
Prior Year
Installment Sales
$557,500
$0
$422,238
$0
$0
$0
$0
$0
$979,738
$557,500
$0
$422,238
$0
$0
$0
$0
$0
$979,738
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
Prior Year
2022-23
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
I - 16
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Events/Athletics
Project Title
Pin Number
Master Plan
Rock Quarry Park Upgrades
0823-20-80-8458
2013 DPR Master Plan
Project Description Objective to upfit Rock Quarry Park as a multi-use site for athletics and for City-wide events and to re-locate the northern City dog park site. Upgrading and renovation of existing facilities was the number one recommendation of the 2013 Master Plan.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
2017-18
TYPE REQUEST
Beginning
07/17
Completion
12/20
New
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
Planning/Design
$0
$100,000
$0
$0
$0
$0
$0
$0
$100,000
Construction
$0
$150,000
$500,000
$0
$0
$0
$0
$0
$650,000
Total
$0
$250,000
$500,000
$0
$0
$0
$0
$0
$750,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Impact Fees
$0
$250,000
$0
$0
$0
$0
$0
$0
$250,000
Unidentified
$0
$0
$500,000
$0
$0
$0
$0
$0
$500,000
$0
$250,000
$500,000
$0
$0
$0
$0
$0
$750,000
Total
I - 17
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Culture & Recreation
General Services
Project Title
Pin Number
Twin Lakes Park Upgrades (Feasibility Study)
0841-07-69-7161
District: 1
Master Plan
Project Description The existing soccer field is in high demand and there is a need for more fields at this park. There are design issues that need to be considered including utilities, connectivity to the existing park and storm water impacts. The feasibility study will produce schematic design option and cost estimates to form the basis for future CIP request or grant applications.
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design Construction Contingency
Total Revenue
PROJECTED DATES:
June 2017
Total Expenditures
$625,241
TYPE REQUEST
Beginning
07/16
Completion
08/18
Continuation
Future Years
TOTAL
$0
$0
$146,199
$0
$0
$538,628
$0
$0
$0
$40,173
$0
$0
$0
$0
$725,000
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$146,199
$0
$0
$0
$0
$0
$538,628
$0
$0
$0
$0
$0
$40,173
$0
$0
$0
$0
$725,000
$0
$0
$0
2017-18
2018-19
Prior Year
2022-23
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$625,000
$0
$0
$0
$0
$0
$0
$0
$625,000
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
$100,000
$0
$0
$0
$0
$0
$0
$0
$100,000
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$725,000
$0
$0
$0
$0
$0
$0
$0
$725,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Impact Fees
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
I - 18
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Culture & Recreation
Parks & Recreation
Development
2
Project Title
Pin Number
Master Plan
West Ellerbee Creek Trail - Phase II
7822-06-38-1047
Durham Trails & Greenways Master Plan
Project Description Design and Construction project of a 1 mile trail connecting the existing Phase I project with the North/South Trail on Stadium Drive.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
Appropriation
Prior Year
Planning/Design Land
$2,845,315
TYPE REQUEST
Beginning
07/13
Completion
06/18
Continuation
Future Years
TOTAL
$0
$0
$141,800
$0
$0
$360,000
$0
$0
$0
$1,519,800
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,021,600
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$141,800
$0
$0
$0
$0
$0
$360,000
$0
$0
$0
$0
$0
$1,519,800
$0
$0
$0
$0
Equip/Furnishings
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$2,021,600
$0
$0
2017-18
Construction
Total
Revenue
Prior Year
2022-23
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$212,000
$0
$0
$0
$0
$0
$0
$0
$212,000
Impact Fees
$653,000
$0
$0
$0
$0
$0
$0
$0
$653,000
Intergovernmental $1,081,600
$0
$0
$0
$0
$0
$0
$0
$1,081,600
Other
$75,000
$0
$0
$0
$0
$0
$0
$0
$75,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,021,600
$0
$0
$0
$0
$0
$0
$0
$2,021,600
Unidentified
Total
I - 19
Downtown Revitalization Table of Contents Project Title
Page
Downtown Revitalization: Summary By Project Downtown Revitalization: Summary By Revenue Source Brick Paver Repairs
American Tobacco Complex Green Space
II - 1 II - 2 II - 3
21 C formerly CCB Building Rooftop
Durham Bulls Athletics Park
The Durham Hotel Rooftop
Program Category: Downtown Revitalization SUMMARY BY PROJECT Category Brick Paver Repairs
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
250,000
0
0
0
0
0
0
0
250,000
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
II - 1
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
0
0
0
0
0
0
0
0
0
Other
0
0
0
0
0
0
0
0
0
250,000
0
0
0
0
0
0
0
250,000
0
0
0
0
0
0
0
0
0
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
Installment Sales GOB Authorized
II - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Downtown Revitalization
Public Works
Engineering Survey, Design an
All
Project Title
Pin Number
Master Plan
Brick Paver Repairs
Project Description This project will address the on-going and specialized repair needs of the downtown streetscape infrastructure.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/13
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
$0
$0
$0
$0
$0
$0
$0
$0
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL $0
Construction
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$250,000
$0
$0
$0
$0
$0
$0
$0
$250,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Installment Sales
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
II - 3
General Services Table of Contents Project Title
Page
General Services: Summary By Project General Services: Summary By Revenue Source ADA Compliance Cemeteries Upgrades City-Wide Security Upgrades Energy Management - (City Hall HVAC Controls/Lighting) General Fund Fleet Vehicles New Sign & Signal Shop
III III III III III III III III
Energy Management Projects
-
1 2 3 4 5 6 7 8
101 City Hall Plaza Exterior Renovation
Fleet Management
Program Category: General Services SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
ADA Compliance
2,703,947
0
0
0
0
0
0
0
2,703,947
Cemeteries Upgrade
2,746,451
0
0
0
0
0
0
0
2,746,451
852,000
318,270
0
0
0
0
0
0
1,170,270
Energy Management
1,747,490
350,000
0
0
0
0
0
0
2,097,490
General Fund Fleet Vehicles
20,363,112
7,277,072
0
0
0
0
0
0
27,640,184
4,130,000
0
0
0
0
0
0
0
4,130,000
$32,543,000
$7,945,342
$0
$0
$0
$0
$0
$0
$40,488,342
City-Wide Security Upgrades
New Sign & Signal Shop
III - 1
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
0
0
0
0
0
0
0
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
2,223,956
1,286,696
0
0
0
0
0
0
3,510,652
21,812,053
427,232
0
0
0
0
0
0
22,239,285
0
0
0
0
0
0
0
0
0
6,376,506
6,231,414
0
0
0
0
0
0
12,607,920
Impact Fees
0
0
0
0
0
0
0
0
0
GOB Unauthorized
0
0
0
0
0
0
0
0
0
2,130,485
0
0
0
0
0
0
0
2,130,485
$32,543,000
$7,945,342
$0
$0
$0
$0
$0
$0
$40,488,342
Other Intergovernmental Installment Sales
GOB Authorized
III - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
General Services
General Services
Project Title
Pin Number
District: All
Master Plan
ADA Compliance
Project Description This CIP request addresses the deficiencies identified by the Department of Justice concerning the requirements for ADA compliance throughout the City. Work continues within various City facilities, with future funding needs anticipated in FY19.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$337,713
TYPE REQUEST
Beginning
07/04
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
Planning/Design
$1,279,800
$0
$0
$0
$0
$0
$0
$0
$1,279,800
Construction
$1,343,947
$0
$0
$0
$0
$0
$0
$0
$1,343,947
Contingency
$80,200
$0
$0
$0
$0
$0
$0
$0
$80,200
$2,703,947
$0
$0
$0
$0
$0
$0
$0
$2,703,947
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Revenue
Prior Year
Pay-As-You-Go
$648,956
$0
$0
$0
$0
$0
$0
$0
$648,956
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,904,991
$0
$0
$0
$0
$0
$0
$0
$1,904,991
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$150,000
$0
$0
$0
$0
$0
$0
$0
$150,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,703,947
$0
$0
$0
$0
$0
$0
$0
$2,703,947
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Installment Sales
Other Unidentified
Total
Operating
Prior Year
2022-23
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
III - 3
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
General Services
General Services
Project Title
Pin Number
Cemeteries Upgrade
0821-09-16-2884
District: 3
Master Plan
Project Description Funding will complete all of repairs and upgrades at Maplewood and Beechwood Cemeteries. The recommendations for these repairs are supported by the Cemeteries Assessment Study completed in February 2014 and include: entry improvements, driveway repair and replacement, walkway improvements, additional parking, improvements to maintenance/service and soil storage areas and accessibility upgrades at both cemeteries.
PROJECT STATUS -
Appropriation Planning/Design Construction Contingency
Total Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$931,071
TYPE REQUEST
Beginning
07/16
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$340,000
$0
$0
$0
$0
$0
$0
$0
$340,000
$2,406,451
$0
$0
$0
$0
$0
$0
$0
$2,406,451
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,746,451
$0
$0
$0
$0
$0
$0
$0
$2,746,451
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,120,000
$0
$0
$0
$0
$0
$0
$0
$1,120,000
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,626,451
$0
$0
$0
$0
$0
$0
$0
$1,626,451
$2,746,451
$0
$0
$0
$0
$0
$0
$0
$2,746,451
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Installment Sales
Other
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
III - 4
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
General Services
General Services
Project Management
1,2,4
Project Title
Pin Number
Master Plan
City-Wide Security Upgrades
Project Description This project will provide security system upgrades at Fleet Admin, Emergency Communications Radio Towers, Fleet Fire Maintenance, GSD, PWOC, SWM and DPR pools and recreation centers. FY18 funding will allow for security upgrades at City Hall.
PROJECT STATUS Total Expenditures
Appropriation
Prior Year
Planning/Design Construction
Total
PROJECTED DATES:
June 2017 $222,112
TYPE REQUEST
Beginning
07/15
Completion
06/18
Continuation
2022-23
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$100,000
$0
$0
$0
$0
$0
$0
$0
$100,000
$752,000
$318,270
$0
$0
$0
$0
$0
$0
$1,070,270
$852,000
$318,270
$0
$0
$0
$0
$0
$0
$1,170,270
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Revenue
Prior Year
Installment Sales
$852,000
$318,270
$0
$0
$0
$0
$0
$0
$1,170,270
$852,000
$318,270
$0
$0
$0
$0
$0
$0
$1,170,270
Total
III - 5
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
General Services
General Services
Energy Management
All
Project Title
Pin Number
Master Plan
Energy Management
0822-14-34-0100
General Services Departmental Strategic Plan
Project Description The Energy Management Capital Improvement Projects will reduce electric and natural gas use through HVAC and lighting improvements at City Hall, General Services, Fleet, Fire Administration and Fire Station #2. These six buildings are among the top energy users for the City.
PROJECT STATUS -
Appropriation Planning/Design Construction Contingency
Total Revenue Installment Sales Other Unidentified
Total
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$1,240,683
TYPE REQUEST
Beginning
07/13
Completion
12/18
Continuation
TOTAL
2018-19
2019-20
2020-21
2021-22
$141,146
$0
$0
$0
$0
$0
$0
$0
$141,146
$1,520,895
$350,000
$0
$0
$0
$0
$0
$0
$1,870,895
$85,449
$0
$0
$0
$0
$0
$0
$0
$85,449
$1,747,490
$350,000
$0
$0
$0
$0
$0
$0
$2,097,490
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$500,000
$350,000
$0
$0
$0
$0
$0
$0
$850,000
$1,247,490
$0
$0
$0
$0
$0
$0
$0
$1,247,490
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,747,490
$350,000
$0
$0
$0
$0
$0
$0
$2,097,490
Prior Year
III - 6
2022-23
Future Years
2017-18
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
General Services
Fleet
Project Title
Pin Number
Division/Program:
District: All
Master Plan
General Fund Fleet Vehicles
Project Description This project is for the financing of fleet vehicles for all General Fund departments. Majority of replacements are Police vehicles. FY'18 includes funding to continue a 10-year fleet model for replacements, along with Police Take-Home Vehicle Program (year 2).
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$4,606,134
TYPE REQUEST
Beginning
10/11
Completion
03/24
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$20,363,112
$7,277,072
$0
$0
$0
$0
$0
$0
$27,640,184
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$20,363,112
$7,277,072
$0
$0
$0
$0
$0
$0
$27,640,184
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$1,575,000
$1,286,696
$0
$0
$0
$0
$0
$0
$2,861,696
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$5,563,144
$0
$0
$0
$0
$0
$0
$5,563,144
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$18,788,112
$427,232
$0
$0
$0
$0
$0
$0
$19,215,344
$0
$0
$0
$0
$0
$0
$0
$0
$0
$20,363,112
$7,277,072
$0
$0
$0
$0
$0
$0
$27,640,184
Other
Unidentified
Total
III - 7
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
General Services
General Services
Transportation
4
Project Title
Pin Number
Master Plan
New Sign & Signal Shop
0831-06-47-0950
Durham Comprehensive Plan
Project Description A new shop is needed to maintain necessary levels of service and to centralize the facility location. A new signal shop would allow the return of the existing site to improved uses.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$1,911,741
TYPE REQUEST
Beginning
07/07
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$456,200
$0
$0
$0
$0
$0
$0
$0
$456,200
$3,673,800
$0
$0
$0
$0
$0
$0
$0
$3,673,800
Total
$4,130,000
$0
$0
$0
$0
$0
$0
$0
$4,130,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$2,130,485
$0
$0
$0
$0
$0
$0
$0
$2,130,485
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,999,515
$0
$0
$0
$0
$0
$0
$0
$1,999,515
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,130,000
$0
$0
$0
$0
$0
$0
$0
$4,130,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Installment Sales
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
III - 8
Public Protection Table of Contents Project Title
Page
Public Protection: Summary By Project Public Protection: Summary By Revenue Source DPD Firing Range Restroom Facility Fire Admin Building Updates - Roof, Envelope and HVAC Fire Station #17 Fire Station #18 Police HQ Replacement & Annex Public Safety Radio Replacement
IV IV IV IV IV IV IV IV -
Fire Station #9
1 2 3 4 5 6 7 8
Durham Fire Department Headquarters
New Police and 911 Headquarters
Program Category: Public Protection SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
258,582
0
0
0
0
0
0
0
258,582
Fire Admin Building Updates Roof, Env & HVAC
1,030,000
0
0
0
0
0
0
0
1,030,000
Fire Station #17
5,400,000
0
0
0
0
0
0
0
5,400,000
Fire Station #18
1,000,000
0
0
0
3,212,202
3,308,568
0
0
7,520,770
Police HQ Replacement & Annex
62,434,057
0
0
0
0
0
0
0
62,434,057
2,000,000
2,000,000
2,000,000
0
0
0
0
0
6,000,000
$72,122,639
$2,000,000
$2,000,000
$0
$3,212,202
$3,308,568
$0
$0
$82,643,409
DPD Firing Range Restroom Facility
Public Safety Radio Replacement
IV - 1
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
0
0
3,212,202
3,308,568
0
0
6,520,770
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
0
0
0
0
0
0
0
0
0
258,582
0
0
0
0
0
0
0
258,582
Other Intergovernmental Installment Sales Impact Fees
GOB Unauthorized GOB Authorized
0
0
0
0
0
0
0
0
0
65,009,756
2,000,000
2,000,000
0
0
0
0
0
69,009,756
0
0
0
0
0
0
0
0
0
6,854,301
0
0
0
0
0
0
0
6,854,301
0
0
0
0
0
0
0
0
0
$72,122,639
$2,000,000
$2,000,000
$0
$3,212,202
$3,308,568
$0
$0
$82,643,409
IV - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Public Protection
Police
Police
2
Project Title
Pin Number
Master Plan
DPD Firing Range Restroom Facility
0857-03-13-8559
Project Description Construct a restroom and shower facility at the Police Department's Firearms Training Facility (Range) to serve City and other authorized users.
PROJECT STATUS -
Appropriation Planning/Design Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/14
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$45,667
$0
$0
$0
$0
$0
$0
$0
$45,667
$212,915
$0
$0
$0
$0
$0
$0
$0
$212,915
$258,582
$0
$0
$0
$0
$0
$0
$0
$258,582
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$258,582
Revenue
Prior Year
Other
$258,582
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$258,582
$0
$0
$0
$0
$0
$0
$0
$258,582
Unidentified
Total
IV - 3
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Public Protection
General Services
Project Title
Pin Number
Fire Admin Building Updates - Roof, Env & HVAC
0842-01-18-1935
District: 1
Master Plan
Project Description This project will address critical Fire Administration maintenance items including a failing roof system and near-end of life HVAC system. The project will also correct the cosmetic issues left from an old structural settlement issue. Additionally, the project will provide a long requested security improvement for Fire department staff by adding a secondary entry door in the lobby area to control civilian access to the staff office areas.
PROJECT STATUS Total Expenditures
Appropriation Planning/Design
Prior Year
PROJECTED DATES:
June 2017 $991,467
TYPE REQUEST
Beginning
07/15
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$63,000
$0
$0
$0
$0
$0
$0
$0
$63,000
$967,000
$0
$0
$0
$0
$0
$0
$0
$967,000
Total
$1,030,000
$0
$0
$0
$0
$0
$0
$0
$1,030,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$1,030,000
$0
$0
$0
$0
$0
$0
$0
$1,030,000
$1,030,000
$0
$0
$0
$0
$0
$0
$0
$1,030,000
Construction
Installment Sales
Total
IV - 4
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Public Protection
Fire
Fire
All
Project Title
Pin Number
Master Plan
Fire Station #17
0769-01-09-5180
Project Description This project constructs a new co-shared fire station in the Southeast area (Mineral Springs, Leesville Road, Hwy 70) of the City to address growth and annexation. This project includes new apparatus purchase needed to provide services, and will be staffed with 15 existing firefighters hired through the SAFER Grant.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$808,207
TYPE REQUEST
Beginning
07/13
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$225,000
$0
$0
$0
$0
$0
$0
$0
$225,000
$3,500,000
$0
$0
$0
$0
$0
$0
$0
$3,500,000
Equip/Furnishings $1,650,000
$0
$0
$0
$0
$0
$0
$0
$1,650,000
Contingency
$25,000
$0
$0
$0
$0
$0
$0
$0
$25,000
$5,400,000
$0
$0
$0
$0
$0
$0
$0
$5,400,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$5,400,000
$0
$0
$0
$0
$0
$0
$0
$5,400,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,400,000
$0
$0
$0
$0
$0
$0
$0
$5,400,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total
Revenue Installment Sales Unidentified
Total
Operating
Prior Year
Prior Year
2022-23
2022-23
Maint/Operations
$0
$0
$100,000
$0
$0
$0
$0
$0
$100,000
Personnel
$0
$0
$1,894,592
$0
$0
$0
$0
$0
$1,894,592
Total
$0
$0
$1,994,592
$0
$0
$0
$0
$0
$1,994,592
IV - 5
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Public Protection
Fire
Project Title
Pin Number
Division/Program:
District: 4
Master Plan
Fire Station #18
Project Description In alignment with the City's Strategic Plan (Goals 2&4), a new Fire Station is needed for coverage in the southern area of the City where the 751 annexations are taking place. Three of the last five annexation impact studies come from the proposed Station 18 response area. In addition a large percentage of the proposed response area for Station 18 already resides within the city limits. Prior year funding is for land acquisition.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$5,450
TYPE REQUEST
Beginning
07/15
Completion
06/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,000,000
$0
$0
$0
$0
$0
$0
$0
$1,000,000
Construction
$0
$0
$0
$0
$3,212,202 $3,308,568
$6,520,770
Equip/Furnishings
$0
$0
$0
$0
$1,000,000
$0
$0
$0
2017-18
2018-19
2019-20
$1,000,000
$0
$0
$0
$0
$0
$0
$0
$1,000,000
$0
$0
$0
$3,212,202 $3,308,568
Land
Total
Revenue Installment Sales Unidentified
Total
Prior Year
IV - 6
$0
$0
$0
$0
$0
$0
$3,212,202 $3,308,568
$0
$0
$7,520,770
Future Years
TOTAL
$0
2020-21
2021-22
2022-23
$0
$0
$0
$0
$1,000,000
$3,212,202 $3,308,568
$0
$0
$6,520,770
$0
$0
$7,520,770
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Public Protection
Police
Project Title
Pin Number
Master Plan
Police HQ Replacement & Annex
0831-09-15-1474
Police Facility Master Plan
All
Project Description This project will fund the construction of a new Police Headquarters, 911 Center, and Parking Deck to meet current and future needs. The site location for the new facility is 602 East Main Street.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/09
Completion
12/18
Continuation
Future Years
TOTAL
$0
$0
$10,695,068
$0
$0
$5,740,000
$0
$0
$0
$45,998,989
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$62,434,057
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL $0
2017-18
2018-19
2019-20
2020-21
2021-22
$10,695,068
$0
$0
$0
$0
$0
$5,740,000
$0
$0
$0
$0
$0
$45,998,989
$0
$0
$0
$0
Equip/Furnishings
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$62,434,057
$0
$0
2017-18
Appropriation Planning/Design Land Construction
Total
Revenue
Prior Year
$61,936,211
Prior Year
2022-23
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$6,854,301
$0
$0
$0
$0
$0
$0
$0
$6,854,301
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales $55,579,756
$0
$0
$0
$0
$0
$0
$0
$55,579,756
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$62,434,057
$0
$0
$0
$0
$0
$0
$0
$62,434,057
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
GOB Unauthorize
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IV - 7
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Public Protection
Emergency Communications
Communications Maintenance
All
Project Title
Pin Number
Master Plan
Public Safety Radio Replacement
Project Description Operational radios are vital to the city's goal of providing public safety and effective communications for core services that are provided directly to the citizens. Project replaces the 10+ year old public safety radio inventory. The life and safety of Police officers, Fire fighters, and the public are at risk if we do not maintain working radio equipment. FY'18 funds continues a three (3) year phased approach to funding all replacements.
PROJECT STATUS Total Expenditures
$1,999,979
TYPE REQUEST
Beginning
07/16
Completion
06/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
Equip/Furnishings $2,000,000
$2,000,000
$2,000,000
$0
$0
$0
Total
$2,000,000
$2,000,000
$2,000,000
$0
$0
$0
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
$2,000,000
$2,000,000
$2,000,000
$0
$0
$0
$2,000,000
$2,000,000
$2,000,000
$0
$0
$0
Appropriation
Installment Sales
Total
Prior Year
PROJECTED DATES:
June 2017
IV - 8
Future Years
TOTAL
$0
$0
$6,000,000
$0
$0
$6,000,000
Future Years
TOTAL
$0
$0
$6,000,000
$0
$0
$6,000,000
2022-23
2022-23
Solid Waste Table of Contents Project Title
Page
Solid Waste: Summary By Project Solid Waste: Summary By Revenue Source Solid Waste Annex and Truck Wash Feasibility Study Solid Waste Customer Convenience Center Improvements Solid Waste Fleet Vehicles
Solid Waste Annex Building (Before)
VVVVV-
1 2 3 4 5
Solid Waste Fleet
Solid Waste Annex Building and Truck Wash Renovation
Program Category: Solid Waste SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
125,000
2,250,000
0
Solid Waste Customer Convenience Ctr. Improvements
0
154,000
Solid Waste Fleet Vehicles
9,291,787
$9,416,787
Solid Waste Annex and Truck Wash Feasibility Study
FY 2018-19
FY 2019-20
Total Request
FY 2021-22
0
0
0
0
0
2,375,000
0
0
0
0
0
0
154,000
1,530,756
0
0
0
0
0
0
10,822,543
$3,934,756
$0
$0
$0
$0
$0
$0
$13,351,543
V-1
FY 2022-23
Future Years
FY 2020-21
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
2,250,000
0
0
0
0
0
0
2,250,000
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
0
154,000
0
0
0
0
0
0
154,000
9,291,787
1,530,756
0
0
0
0
0
0
10,822,543
0
0
0
0
0
0
0
0
0
125,000
0
0
0
0
0
0
0
125,000
Impact Fees
0
0
0
0
0
0
0
0
0
GOB Unauthorized
0
0
0
0
0
0
0
0
0
GOB Authorized
0
0
0
0
0
0
0
0
0
$9,416,787
$3,934,756
$0
$0
$0
$0
$0
$0
$13,351,543
Other Intergovernmental Installment Sales
V-2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Solid Waste
Solid Waste Management
Project Title
Pin Number
Solid Waste Annex and Truck Wash Feasibility Study
0832-09-97-3359
District: 1
Master Plan
Project Description FY18 funding is to perform construction as recommended from the assessment, feasibility study for the SWM Annex building, truck washing station and concrete repairs at the disposal facility.
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$414,310
TYPE REQUEST
Beginning
11/15
Completion
07/18
Continuation
2022-23
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$125,000
$250,000
$0
$0
$0
$0
$0
$0
$375,000
$0
$2,000,000
$0
$0
$0
$0
$0
$0
$2,000,000
$125,000
$2,250,000
$0
$0
$0
$0
$0
$0
$2,375,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Revenue
Prior Year
Installment Sales
$125,000
$0
$0
$0
$0
$0
$0
$0
$125,000
$0
$2,250,000
$0
$0
$0
$0
$0
$0
$2,250,000
$125,000
$2,250,000
$0
$0
$0
$0
$0
$0
$2,375,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Unidentified
Total Operating
Prior Year
2022-23
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
V-3
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Solid Waste
General Services
Solid Waste Management/Tran
All
Project Title
Pin Number
Master Plan
Solid Waste Customer Convenience Ctr. Improvements
0843-03-10-6304
Project Description FY18 funding will renovate the existing office space for disposal staff. Existing 300 SF building will upgraded.
PROJECT STATUS -
PROJECTED DATES:
Total Expenditures
Appropriation
Prior Year
$0
TYPE REQUEST
Beginning
07/17
Completion
06/18
New
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
Planning/Design
$0
$18,700
$0
$0
$0
$0
$0
$0
$18,700
Construction
$0
$116,400
$0
$0
$0
$0
$0
$0
$116,400
Contingency
$0
$18,900
$0
$0
$0
$0
$0
$0
$18,900
Total
$0
$154,000
$0
$0
$0
$0
$0
$0
$154,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$154,000
$0
$0
$0
$0
$0
$0
$154,000
$0
$154,000
$0
$0
$0
$0
$0
$0
$154,000
Pay-As-You-Go
Total
V-4
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Solid Waste
Fleet
Project Title
Pin Number
Division/Program:
District: All
Master Plan
Solid Waste Fleet Vehicles
Project Description This project is for the financing of fleet vehicles for the Solid Waste Department.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$3,964,804
TYPE REQUEST
Beginning
10/11
Completion
03/24
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$9,291,787
$1,530,756
$0
$0
$0
$0
$0
$0
$10,822,543
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$9,291,787
$1,530,756
$0
$0
$0
$0
$0
$0
$10,822,543
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$9,291,787
$1,530,756
$0
$0
$0
$0
$0
$0
$10,822,543
$0
$0
$0
$0
$0
$0
$0
$0
$0
$9,291,787
$1,530,756
$0
$0
$0
$0
$0
$0
$10,822,543
Other
Unidentified
Total
V-5
Stormwater Table of Contents Project Title
Page
Stormwater: Summary By Project Stormwater: Summary By Revenue Source Drainage Repair of City Owned Properties Floodplain Management Private Property Drainage Projects Stormwater Fleet Vehicles Stormwater Infrastructure & BMP Improvements Stormwater Retrofitting Watershed Planning & Design
VI VI VI VI VI VI VI VI VI
Watershed Planning
Stormwater Retrofit
-
1 2 3 4 5 6 7 8 9
Stormwater Fleet
Stormwater Algae Turf
Program Category: Stormwater SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
Drainage Repair of City Owned Properties
2,338,417
610,000
650,000
650,000
650,000
650,000
0
0
5,548,417
Floodplain Management
1,091,000
30,000
400,000
0
400,000
0
0
0
1,921,000
Private Property Drainage Projects
4,092,670
40,000
200,000
200,000
200,000
225,000
0
0
4,957,670
Stormwater Fleet Vehicles
3,970,032
714,816
700,000
700,000
700,000
0
0
0
6,784,848
Stormwater Infrastructure & BMP Improvements
7,705,700
1,630,000
1,400,000
1,400,000
1,400,000
1,400,000
0
0
14,935,700
Stormwater Retrofitting
5,693,000
180,000
5,450,000
5,000,000
3,550,000
2,450,000
0
0
22,323,000
Watershed Planning & Implementation
7,598,317
700,000
1,000,000
700,000
1,000,000
700,000
0
0
11,698,317
$32,489,136
$3,904,816
$9,800,000
$8,650,000
$7,900,000
$5,425,000
$0
$0
$68,168,952
VI - 1
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
0
0
0
0
0
0
0
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
29,517,412
3,904,816
9,800,000
8,650,000
7,900,000
5,425,000
0
0
65,197,228
Other
490,543
0
0
0
0
0
0
0
490,543
2,481,181
0
0
0
0
0
0
0
2,481,181
Installment Sales
0
0
0
0
0
0
0
0
0
Impact Fees
0
0
0
0
0
0
0
0
0
GOB Unauthorized
0
0
0
0
0
0
0
0
0
GOB Authorized
0
0
0
0
0
0
0
0
0
$32,489,136
$3,904,816
$9,800,000
$8,650,000
$7,900,000
$5,425,000
$0
$0
$68,168,952
Intergovernmental
VI - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Stormwater
Public Works
Stormwater
All
Project Title
Pin Number
Master Plan
Drainage Repair of City Owned Properties
Project Description This program involves the repair or improvement of existing stormwater systems located on City owned property. The program will be developed and administered by Stormwater Services Division. Funds may be used for, but are not limited to, the analysis, design, and construction of drainage repair and improvement projects involving City owned land.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
Appropriation
Prior Year
Planning/Design
$2,248,638
TYPE REQUEST
Beginning
07/07
Completion
07/20
Continuation
Future Years
TOTAL
$0
$0
$580,000
$0
$0
$0
$550,000
$0
$0
$4,968,417
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$650,000
$650,000
$650,000
$0
$0
$5,548,417
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$80,000
$100,000
$100,000
$100,000
$100,000
$100,000
$0
$0
$0
$0
$0
$0
$2,258,417
$510,000
$550,000
$550,000
$550,000
Equip/Furnishings
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$2,338,417
$610,000
$650,000
2017-18
Land Construction
Total
Revenue
Prior Year
2022-23
2022-23
Pay-As-You-Go
$2,338,417
$610,000
$650,000
$650,000
$650,000
$650,000
$0
$0
$5,548,417
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,338,417
$610,000
$650,000
$650,000
$650,000
$650,000
$0
$0
$5,548,417
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 3
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Stormwater
Public Works
Stormwater
All
Project Title
Pin Number
Master Plan
Floodplain Management
Project Description This is an on-going program that involves efforts to reduce or eliminate longterm risk to people and property from flooding hazards and their effects. The program includes floodplain analysis and the identification, evaluation, and implementation of floodplain management projects.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
$165,526
Appropriation
Prior Year
2017-18
Planning/Design
$100,000
Land
$781,000
Construction
TYPE REQUEST
Beginning
09/09
Completion
07/20
2018-19
2019-20
$15,000
$50,000
$15,000
$200,000
Continuation
2022-23
Future Years
TOTAL
2020-21
2021-22
$0
$50,000
$0
$0
$0
$215,000
$0
$200,000
$0
$0
$0
$1,196,000
$210,000
$0
$150,000
$0
$150,000
$0
$0
$0
$510,000
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,091,000
$30,000
$400,000
$0
$400,000
$0
$0
$0
$1,921,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$1,091,000
$30,000
$400,000
$0
$400,000
$0
$0
$0
$1,921,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,091,000
$30,000
$400,000
$0
$400,000
$0
$0
$0
$1,921,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 4
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Stormwater
Public Works
Stormwater
All
Project Title
Pin Number
Master Plan
Private Property Drainage Projects
Project Description This project funds drainage improvement projects citywide on private property. Projects are identified by Stormwater staff through requests from property owners and are ranked and constructed according to severity. This is an ongoing annual activity.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
$2,562,670
Prior Year
2017-18
2018-19
TYPE REQUEST
Beginning
07/04
Completion
07/20
2019-20
2020-21
Continuation
2021-22
2022-23
Future Years
TOTAL
$10,000
$10,000
$20,000
$20,000
$20,000
$20,000
$0
$0
$100,000
$4,082,670
$30,000
$180,000
$180,000
$180,000
$205,000
$0
$0
$4,857,670
Total
$4,092,670
$40,000
$200,000
$200,000
$200,000
$225,000
$0
$0
$4,957,670
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
2022-23
Pay-As-You-Go
$1,854,300
$40,000
$200,000
$200,000
$200,000
$225,000
$0
$0
$2,719,300
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental $2,238,370
$0
$0
$0
$0
$0
$0
$0
$2,238,370
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,092,670
$40,000
$200,000
$200,000
$200,000
$225,000
$0
$0
$4,957,670
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 5
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Stormwater
Fleet
Project Title
Pin Number
Division/Program:
District: All
Master Plan
Stormwater Fleet Vehicles
Project Description This project is for the financing of fleet vehicles for the Stormwater Fund.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$390,982
TYPE REQUEST
Beginning
10/11
Completion
03/24
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,970,032
$714,816
$700,000
$700,000
$700,000
$0
$0
$0
$6,784,848
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,970,032
$714,816
$700,000
$700,000
$700,000
$0
$0
$0
$6,784,848
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$3,479,489
$714,816
$700,000
$700,000
$700,000
$0
$0
$0
$6,294,305
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$490,543
$0
$0
$0
$0
$0
$0
$0
$490,543
Other
Unidentified
Total Operating
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,970,032
$714,816
$700,000
$700,000
$700,000
$0
$0
$0
$6,784,848
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 6
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Stormwater
Public Works
Stormwater
All
Project Title
Pin Number
Master Plan
Stormwater Infrastructure & BMP Improvements
Project Description This project funds repair, improvements or analysis of watersheds, major drainage systems or BMP systems that involve private or public property and require extensive analysis, design, permit approvals or monitoring. Projects are identified and managed by Stormwater staff.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
Appropriation
Prior Year
Planning/Design
$6,629,781
TYPE REQUEST
Beginning
09/09
Completion
03/19
Continuation
Future Years
TOTAL
$0
$0
$1,625,000
$0
$0
$0
$0
$0
$13,010,700
$0
$0
$0
$150,000
$0
$0
$0
$150,000
$1,400,000 $1,400,000
$0
$0
$14,935,700
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$925,000
$100,000
$150,000
$150,000
$150,000
$150,000
$0
$0
$0
$0
$0
$0
$6,480,700
$1,530,000
$1,250,000
$1,250,000
$1,250,000 $1,250,000
Equip/Furnishings
$150,000
$0
$0
$0
$0
Contingency
$150,000
$0
$0
$0
$0
$7,705,700
$1,630,000
$1,400,000
$1,400,000
2017-18
2018-19
2019-20
Land Construction
Total
Revenue
Prior Year
2020-21
2021-22
2022-23
Pay-As-You-Go
$7,705,700
$1,630,000
$1,400,000
$1,400,000
$0
$0
$14,935,700
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,705,700
$1,630,000
$1,400,000
$1,400,000
$1,400,000 $1,400,000
$0
$0
$14,935,700
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
$1,400,000 $1,400,000
2022-23
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 7
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Stormwater
Public Works
Stormwater
All
Project Title
Pin Number
Master Plan
Stormwater Retrofitting
Project Description This project funds professional service and construction contracts for planning, design, permitting, construction drawings and the construction of stormwater retrofit projects to comply with NPDES permit requirements and state regulations.
PROJECT STATUS -
Appropriation Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$4,047,955
TYPE REQUEST
Beginning
07/12
Completion
07/20
Continuation
Future Years
TOTAL
$0
$0
$3,000,000
$0
$0
$1,500,000
$0
$0
$17,323,000
$0
$0
$0
$500,000
$0
$0
$0
$0
$3,550,000 $2,450,000
$0
$0
$22,323,000
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$1,000,000
$0
$500,000
$500,000
$550,000
$450,000
$800,000
$0
$500,000
$200,000
$0
$0
$3,393,000
$180,000
$4,450,000
$4,300,000
$3,000,000 $2,000,000
$500,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,693,000
$180,000
$5,450,000
$5,000,000
2017-18
2018-19
2019-20
Prior Year
2020-21
2021-22
2022-23
Pay-As-You-Go
$5,693,000
$180,000
$5,450,000
$5,000,000
$0
$0
$22,323,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,693,000
$180,000
$5,450,000
$5,000,000
$3,550,000 $2,450,000
$0
$0
$22,323,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
$3,550,000 $2,450,000
2022-23
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 8
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Stormwater
Public Works
Stormwater
All
Project Title
Pin Number
Master Plan
Watershed Planning & Implementation
0821-05-97-9539
Watershed Master Plans
Project Description This project funds professional service contracts to develop watershed plans for streams flowing in or through the City. This activity, required by a NPDES permit and state regulations, will provide data necessary to perform future stormwater capital improvement projects.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$7,049,043
TYPE REQUEST
Beginning
07/04
Completion
07/20
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$7,598,317
$700,000
$1,000,000
$700,000
$1,000,000
$700,000
$0
$0
$11,698,317
Total
$7,598,317
$700,000
$1,000,000
$700,000
$1,000,000
$700,000
$0
$0
$11,698,317
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Pay-As-You-Go
$7,355,506
$700,000
$1,000,000
$700,000
$1,000,000
$700,000
$0
$0
$11,455,506
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
$242,811
$0
$0
$0
$0
$0
$0
$0
$242,811
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,598,317
$700,000
$1,000,000
$700,000
$1,000,000
$700,000
$0
$0
$11,698,317
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Intergovernmental
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VI - 9
Technology Table of Contents Project Title
Page
Technology: Summary By Project Technology: Summary By Revenue Source IT Infrastructure Improvements
VII - 1 VII - 2 VII - 3
Program Category: Technology SUMMARY BY PROJECT Category IT Infrastructure Improvements
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
1,751,556
0
0
0
0
0
0
0
1,751,556
$1,751,556
$0
$0
$0
$0
$0
$0
$0
$1,751,556
VII - 1
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
0
0
0
0
0
0
0
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
0
0
0
0
0
0
0
0
0
1,751,556
0
0
0
0
0
0
0
1,751,556
Intergovernmental
0
0
0
0
0
0
0
0
0
Installment Sales
0
0
0
0
0
0
0
0
0
Impact Fees
0
0
0
0
0
0
0
0
0
GOB Unauthorized
0
0
0
0
0
0
0
0
0
GOB Authorized
0
0
0
0
0
0
0
0
0
$1,751,556
$0
$0
$0
$0
$0
$0
$0
$1,751,556
Other
VII - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Technology
Technology Solutions
Administration
All
Project Title
Pin Number
Master Plan
IT Infrastructure Improvements
0821-08-97-8693
Project Description This project will remediate inadequate IT infrastructure supporting the City’s business functions, and address existing risks and vulnerabilities to ensure the accessibility, integrity, and protection of the City’s intellectual property and to support the City’s ability to provide continuous critical business operations. These improvements will support the business operations for the City’s departments and the organization overall.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
Appropriation
Prior Year
Planning/Design
$1,351,295
TYPE REQUEST
Beginning
07/11
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$80,000
$0
$0
$0
$0
$0
$0
$0
$80,000
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
Construction
$0
$0
$0
$0
$0
$0
$0
$0
$0
Equip/Furnishings $1,671,556
$0
$0
$0
$0
$0
$0
$0
$1,671,556
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,751,556
$0
$0
$0
$0
$0
$0
$0
$1,751,556
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,751,556
$0
$0
$0
$0
$0
$0
$0
$1,751,556
Other
Unidentified
Total Operating
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,751,556
$0
$0
$0
$0
$0
$0
$0
$1,751,556
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VII - 3
Transportation Table of Contents Project Title
Page
Transportation: Summary By Project Transportation: Summary By Revenue Source Bicycle Facilities Bridge Repair Carver Street Extension Dirt/Petition Street Paving Duke Belt Line Trail Failed and Struggling Development Infrastructure Fayetteville / Buxton / Riddle Road Improvements Fayetteville Road Improvements Ph. II Federal-State Matching Projects Misc. Thoroughfares and Street Improvements Sidewalk Repair, ADA and Gaps Station Area Strategic Infrastructure (SASI) Street Paving & Maintenance Traffic Calming
Bicycle Facilities
NC147/Hwy 70 Connector
Proposed Durham Light Rail
VIII - 1 VIII - 2 VIII - 3 VIII - 4 VIII - 5 VIII - 6 VIII - 7 VIII - 8 VIII - 9 VIII - 10 VIII - 11 VIII - 12 VIII - 13 VIII - 14 VIII - 15 VIII - 16
Bridge Repair
Program Category: Transportation SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
0
100,000
0
0
0
0
0
0
100,000
Bridge Repair
515,000
0
546,364
0
579,637
0
614,937
0
2,255,938
Carver Street Extension
8,185,000
0
0
0
0
0
0
0
8,185,000
Dirt/Petition Street Paving
800,000
0
2,087,851
562,754
579,637
597,026
614,937
0
5,242,205
Duke Belt Line Trail
2,797,700
0
0
0
0
0
0
0
2,797,700
Failed and Struggling Development Infrastructure
4,211,877
500,000
546,364
0
0
0
0
0
5,258,241
Fayetteville / Buxton / Riddle Road Improvements
5,000,000
0
0
0
0
0
0
0
5,000,000
Fayetteville Road Improvements Ph. II
8,035,789
0
0
0
0
0
0
0
8,035,789
Federal-State Matching Projects
13,018,001
4,501,195
498,196
0
5,216,733
5,970,261
0
0
29,204,386
Misc Thoroughfares and Street Improvements
4,371,772
318,270
327,818
337,653
347,782
358,216
368,962
0
6,430,473
Sidewalk Repair, ADA and Gaps
7,423,257
1,500,000
1,500,000
1,500,000
1,500,000
1,500,000
1,500,000
1,500,000
17,923,257
0
0
0
0
0
2,388,105
11,683,802
0
14,071,907
Street Paving & Maintenance
6,000,000
6,600,000
5,000,000
6,000,000
7,000,000
0
0
0
30,600,000
Traffic Calming
1,600,551
0
0
0
0
0
0
0
1,600,551
$61,958,947
$13,519,465
$10,506,593
$8,400,407
$15,223,789
$10,813,608
$1,500,000
$136,705,447
Bicycle Facilities
Station Area Strategic Infrastructure (SASI)
VIII - 1
$14,782,638
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Unidentified
0
0
4,960,229
2,400,407
8,223,789
8,425,503
3,098,836
1,500,000
28,608,764
Rev Unauthorized
0
0
0
0
0
0
0
0
0
Rev Authorized
0
0
0
0
0
0
0
0
0
Pay-As-You-Go
2,039,678
3,100,000
0
0
0
0
0
0
5,139,678 32,450,036
Other
10,450,036
4,000,000
5,000,000
6,000,000
7,000,000
0
0
0
Intergovernmental
2,585,696
0
0
0
0
0
0
0
2,585,696
Installment Sales
19,350,572
3,936,565
546,364
0
0
2,388,105
11,683,802
0
37,905,408
Impact Fees
23,973,919
2,482,900
0
0
0
0
0
0
26,456,819
200,000
0
0
0
0
0
0
0
200,000
3,359,046
0
0
0
0
0
0
0
3,359,046
$8,400,407 $15,223,789 $10,813,608 $14,782,638
$1,500,000
$136,705,447
GOB Unauthorized GOB Authorized
$61,958,947
$13,519,465 $10,506,593
VIII - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Transportation
Transportation Planning
All
Project Title
Pin Number
Master Plan
Bicycle Facilities
Durham Walks Plan
Project Description This project will proactively install bicycle facilities as recommended in the Bike+Walk Implementation Plan. FY18 funds are for design of neighborhood greenways, a corridor project, pavement markings and intersection safety improvements.
PROJECT STATUS -
PROJECTED DATES:
Total Expenditures
Appropriation
Prior Year
$0
TYPE REQUEST
Beginning
07/17
Completion
06/19
New
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$75,000
Planning/Design
$0
$75,000
$0
$0
$0
$0
$0
$0
Construction
$0
$25,000
$0
$0
$0
$0
$0
$0
$25,000
Total
$0
$100,000
$0
$0
$0
$0
$0
$0
$100,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$100,000
$0
$0
$0
$0
$0
$0
$100,000
$0
$100,000
$0
$0
$0
$0
$0
$0
$100,000
Installment Sales
Total
VIII - 3
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering
All
Project Title
Pin Number
Master Plan
Bridge Repair
Project Description Develop bi-annual bridge reports with preventative maintenance and administer maintenance activities. FY17 funding will address demolition of a bridge on Maryland Avenue (off Guess Road at Ellerbee Creek).
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design
$515,000 $0 $515,000
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$0
2017-18
TYPE REQUEST
Beginning
07/16
Completion
06/22
2018-19
2019-20
$0
$0
$0
$546,364
$0
2017-18
New
2022-23
Future Years
TOTAL
2020-21
2021-22
$0
$0
$0
$0
$0
$515,000
$0
$579,637
$0
$614,937
$0
$1,740,938
$546,364
$0
$579,637
$0
$614,937
$0
$2,255,938
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Revenue
Prior Year
Installment Sales
$515,000
$0
$0
$0
$0
$0
$0
$0
$515,000
$0
$0
$546,364
$0
$579,637
$0
$614,937
$0
$1,740,938
$515,000
$0
$546,364
$0
$579,637
$0
$614,937
$0
$2,255,938
Unidentified
Total
VIII - 4
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering
2
Project Title
Pin Number
Master Plan
Carver Street Extension
0833-01-45-7719
Long Range Transportation Plan
Project Description This project extends Carver Street one mile in northeastern Durham from Danube Lane east to Hamlin Road.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$8,533,675
TYPE REQUEST
Beginning
07/12
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
Planning/Design
$2,050,000
$0
$0
$0
$0
$0
$0
$0
$2,050,000
Land
$2,635,000
$0
$0
$0
$0
$0
$0
$0
$2,635,000
Construction
$3,500,000
$0
$0
$0
$0
$0
$0
$0
$3,500,000
$8,185,000
$0
$0
$0
$0
$0
$0
$0
$8,185,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Revenue
Prior Year
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,185,000
$0
$0
$0
$0
$0
$0
$0
$8,185,000
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,185,000
$0
$0
$0
$0
$0
$0
$0
$8,185,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Impact Fees
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 5
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering
All
Project Title
Pin Number
Master Plan
Dirt/Petition Street Paving
Pavement Condition Study
Project Description Funding is to pave gravel or dirt streets. The projects have been ordered by City Council once a successful petition has been completed by the property owners, or have been ordered under City Councils Enabling Act Authority.
PROJECT STATUS -
Appropriation
Prior Year
Construction
Total
PROJECTED DATES:
June 2017
Total Expenditures
$0
TYPE REQUEST
Beginning
07/12
Completion
07/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$800,000
$0
$2,087,851
$562,754
$579,637
$597,026
$800,000
$0
$2,087,851
$562,754
$579,637
$597,026
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$614,937
$0
$5,242,205
$614,937
$0
$5,242,205
Future Years
TOTAL
2022-23
Revenue
Prior Year
Installment Sales
$800,000
$0
$0
$0
$0
$0
$0
$0
$800,000
$0
$0
$2,087,851
$562,754
$579,637
$597,026
$614,937
$0
$4,442,205
$800,000
$0
$2,087,851
$562,754
$579,637
$597,026
$614,937
$0
$5,242,205
Unidentified
Total
VIII - 6
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Transportation
Pedestrian/Bike Planning
2
Project Title
Pin Number
Master Plan
Duke Belt Line Trail
Durham Trails and Greenways Master Plan
Project Description FY17 funding will provide for land acquisition. The project will consist of repurposing 2.2 miles of trail for pedestrian and/or bike use; connecting users from Downtown Durham to points of interest in neighborhoods to the North and East.
PROJECT STATUS Total Expenditures
Appropriation Planning/Design
Prior Year
PROJECTED DATES:
June 2017 $266,324
TYPE REQUEST
Beginning
07/15
Completion
12/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$297,700
$0
$0
$0
$0
$0
$0
$0
$297,700
$2,500,000
$0
$0
$0
$0
$0
$0
$0
$2,500,000
Total
$2,797,700
$0
$0
$0
$0
$0
$0
$0
$2,797,700
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Land
Pay-As-You-Go Installment Sales Other
Total
2022-23
$75,000
$0
$0
$0
$0
$0
$0
$0
$75,000
$2,500,000
$0
$0
$0
$0
$0
$0
$0
$2,500,000
$222,700
$0
$0
$0
$0
$0
$0
$0
$222,700
$2,797,700
$0
$0
$0
$0
$0
$0
$0
$2,797,700
VIII - 7
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering
All
Project Title
Pin Number
Master Plan
Failed and Struggling Development Infrastructure
Project Description Funding for completon of infrastructure in Failed and Struggling Developments, due to the real estate economic downfall of 2007. FY18 funding will continue to address the Ravenstone and Stonehill subdivisions, along with various stormwater infrastructure issues.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/12
Completion
12/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,211,877
$500,000
$546,364
$0
$0
$0
$0
$0
$5,258,241
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,211,877
$500,000
$546,364
$0
$0
$0
$0
$0
$5,258,241
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL $859,730
Construction
Total
Revenue
Prior Year
Pay-As-You-Go
$359,730
$500,000
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$200,000
$0
$0
$0
$0
$0
$0
$0
$200,000
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$546,364
$0
$0
$0
$0
$0
$546,364
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,652,147
$0
$0
$0
$0
$0
$0
$0
$3,652,147
GOB Unauthorize
Other
Unidentified
Total Operating
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,211,877
$500,000
$546,364
$0
$0
$0
$0
$0
$5,258,241
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 8
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering Survey, Design an
4
Project Title
Pin Number
Master Plan
Fayetteville / Buxton / Riddle Road Improvements
Project Description This project will provide improvements to Fayetteville Road by realignment of Buxton Road and Riddle Road to form one intersection with Fayetteville Road.
PROJECT STATUS -
Appropriation
Prior Year
PROJECTED DATES:
June 2017
Total Expenditures
$8,795
TYPE REQUEST
Beginning
07/13
Completion
12/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
Land
$1,600,000
$0
$0
$0
$0
$0
$0
$0
$1,600,000
Construction
$3,400,000
$0
$0
$0
$0
$0
$0
$0
$3,400,000
Total
$5,000,000
$0
$0
$0
$0
$0
$0
$0
$5,000,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$5,000,000
$0
$0
$0
$0
$0
$0
$0
$5,000,000
$5,000,000
$0
$0
$0
$0
$0
$0
$0
$5,000,000
Impact Fees
Total
VIII - 9
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering
4
Project Title
Pin Number
Master Plan
Fayetteville Road Improvements Ph. II
0729-02-76-3045
Long Range Transportation Plan
Project Description This project will provide improvements to Fayetteville Road that promote safety and better traffic flow. The project limits are from Riddle Road south to Woodcroft Parkway.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/12
Completion
12/24
Continuation
Future Years
TOTAL
$0
$0
$1,000,000
$0
$0
$0
$0
$0
$0
$7,035,789
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,035,789
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$1,000,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,035,789
$0
$0
$0
$0
Equip/Furnishings
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$8,035,789
$0
$0
2017-18
Appropriation Planning/Design Land Construction
Total
Revenue
Prior Year
$1,958,132
Prior Year
2022-23
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,035,789
$0
$0
$0
$0
$0
$0
$0
$8,035,789
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,035,789
$0
$0
$0
$0
$0
$0
$0
$8,035,789
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Impact Fees
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 10
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Transportation
Transportation
All
Project Title
Pin Number
Master Plan
Federal-State Matching Projects
Metropolitan Transportation Plan (MTP)
Project Description The project provides local matching funds for federal and State transportation grants for various roadway appearance, intersection capacity, pedestrian, bicycle, and safety improvement projects. New in FY'18 specific individual projects have been added to the CIP ordinance.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/04
Completion
06/23
Continuation
Future Years
TOTAL
$0
$0
$1,124,726
$0
$0
$367,010
$0
$0
$27,712,650
$0
$0
$0
$0
$0
$0
$0
$0
$5,216,733 $5,970,261
$0
$0
$29,204,386
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$1,124,726
$0
$0
$0
$0
$0
$367,010
$0
$0
$0
$0
$0
$11,526,265
$4,501,195
$498,196
$0
$5,216,733 $5,970,261
Equip/Furnishings
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$13,018,001
$4,501,195
$498,196
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Appropriation Planning/Design Land Construction
Total
Revenue
Prior Year
$162,315
Prior Year
2022-23
2022-23
Pay-As-You-Go
$500,000
$0
$0
$0
$0
$0
$0
$0
$500,000
GOB Authorized
$2,259,046
$0
$0
$0
$0
$0
$0
$0
$2,259,046
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$6,416,185
$2,018,295
$0
$0
$0
$0
$0
$0
$8,434,480
Impact Fees
$2,753,130
$2,482,900
$0
$0
$0
$0
$0
$0
$5,236,030
Intergovernmental
$980,000
$0
$0
$0
$0
$0
$0
$0
$980,000
Other
$109,640
$0
$0
$0
$0
$0
$0
$0
$109,640
$0
$0
$498,196
$0
$5,216,733 $5,970,261
$0
$0
$11,685,190
$13,018,001
$4,501,195
$498,196
$0
$5,216,733 $5,970,261
$0
$0
$29,204,386
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Unidentified
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 11
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Transportation
Transportation
All
Project Title
Pin Number
Master Plan
Misc Thoroughfares and Street Improvements
Long Range Transportation Plan
Project Description This project provides funding to construct missing segments of streets between those segments not built by developers, plus other improvements like turn lanes, intersection widening, new traffic signals and railroad crossing safety improvements. Projects are citywide.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/04
Completion
07/24
Continuation
Future Years
TOTAL
$0
$0
$1,090,606
$0
$0
$0
$358,216
$368,962
$0
$4,316,082
$0
$0
$0
$0
$1,001,123
$0
$0
$0
$0
$22,662
$337,653
$347,782
$358,216
$368,962
$0
$6,430,473
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$1,090,606
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,257,381
$318,270
$327,818
$337,653
$347,782
Equip/Furnishings $1,001,123
$0
$0
$0
Contingency
$22,662
$0
$0
$0
$4,371,772
$318,270
$327,818
2017-18
Appropriation Planning/Design Land Construction
Total
Prior Year
($17)
2022-23
Revenue
Prior Year
Pay-As-You-Go
$604,948
$0
$0
$0
$0
$0
$0
$0
$604,948
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,637,995
$318,270
$0
$0
$0
$0
$0
$0
$2,956,265
Installment Sales Impact Fees
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$959,918
$0
$0
$0
$0
$0
$0
$0
$959,918
Other
$168,911
$0
$0
$0
$0
$0
$0
$0
$168,911
$0
$0
$327,818
$337,653
$347,782
$358,216
$368,962
$0
$1,740,431
$4,371,772
$318,270
$327,818
$337,653
$347,782
$358,216
$368,962
$0
$6,430,473
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Unidentified
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 12
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Engineering
All
Project Title
Pin Number
Master Plan
Sidewalk Repair, ADA and Gaps
Pedestrian Master Plan
Project Description This program includes funding for on-going repair, maintenance and ADA required improvements to existing City sidewalks. The program improves pedestrian safety, encourages walking, provides better access for pedestrians and preserves City sidewalk assets. FY16 allocation includes funding for new sidewalk design only related to the existing DurhamWalks! Plan projects. Subsequent funding level in future years includes ongoing sidewalk repairs and needs determined by a DurhamWalks Plan refresh.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/11
Completion
06/24
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,423,257
$1,500,000
$1,500,000
$1,500,000
$1,500,000 $1,500,000 $1,500,000
$1,500,000
$17,923,257
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,423,257
$1,500,000
$1,500,000
$1,500,000
$1,500,000 $1,500,000 $1,500,000
$1,500,000
$17,923,257
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total
Revenue
Prior Year
Pay-As-You-Go
$500,000
$0
$0
$0
$0
$0
$0
$0
$500,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,980,841
$1,500,000
$0
$0
$0
$0
$0
$0
$7,480,841
Installment Sales Impact Fees
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$645,778
$0
$0
$0
$0
$0
$0
$0
$645,778
Other
$296,638
$0
$0
$0
$0
$0
$0
$0
$296,638
$0
$0
$1,500,000
$1,500,000
$1,500,000 $1,500,000 $1,500,000
$1,500,000
$9,000,000
$7,423,257
$1,500,000
$1,500,000
$1,500,000
$1,500,000 $1,500,000 $1,500,000
$1,500,000
$17,923,257
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Unidentified
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 13
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Transportation
Transportation
Project Title
Pin Number
Division/Program:
District: All
Master Plan
Station Area Strategic Infrastructure (SASI)
Project Description The Station Area Strategic Infrastructure (SASI) project is a multidepartmental/agency planning process to examine infrastructure opportunities and issues introduced by proposed Light Rail Transit (LRT) and Commuter Rail Transit (CRT) service in Durham.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/22
Completion
12/24
2017-18
2018-19
2019-20
2020-21
2021-22
New
2022-23
Future Years
TOTAL
$0
$0
$0
$0
$0 $2,388,105 $11,683,802
$0
$14,071,907
Total
$0
$0
$0
$0
$0 $2,388,105 $11,683,802
$0
$14,071,907
Revenue
Prior Year
2017-18
2018-19
2019-20
Future Years
TOTAL
$0
$0
$0
$0
$0 $2,388,105 $11,683,802
$0
$14,071,907
$0
$0
$0
$0
$0 $2,388,105 $11,683,802
$0
$14,071,907
Installment Sales
Total
VIII - 14
2020-21
2021-22
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Public Works
Street Maintenance
All
Project Title
Pin Number
Master Plan
Street Paving & Maintenance
Project Description This project will address ongoing street paving and maintenance needs throughout the City. The department of Public Works has oversight of the City's Pavement Condition Index and will use funding to address deficiencies.
PROJECT STATUS -
Appropriation Construction
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/14
Completion
06/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$6,000,000
$6,600,000
$5,000,000
$6,000,000
$7,000,000
$0
$0
$0
$30,600,000
Total
$6,000,000
$6,600,000
$5,000,000
$6,000,000
$7,000,000
$0
$0
$0
$30,600,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Pay-As-You-Go
Other
Total Operating
2022-23
$0
$2,600,000
$0
$0
$0
$0
$0
$0
$2,600,000
$6,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$0
$0
$0
$28,000,000
$6,000,000
$6,600,000
$5,000,000
$6,000,000
$7,000,000
$0
$0
$0
$30,600,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 15
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Transportation
Transportation
Transportation
All
Project Title
Pin Number
Master Plan
Traffic Calming
Durham Comprehensive Plan
Project Description This project provides the implementation of speed reduction measures including pedestrian curb extensions, roundabouts and traffic diverters that make neighborhoods more pedestrian friendly. Funding will address and complete: Raised median island at Roxboro St./Mangum St./Markham Ave. and Duke St./Gregson pedestrian curb extension.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/04
Completion
07/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$135,465
$0
$0
$0
$0
$0
$0
$0
$135,465
$1,465,086
$0
$0
$0
$0
$0
$0
$0
$1,465,086
Total
$1,600,551
$0
$0
$0
$0
$0
$0
$0
$1,600,551
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$1,100,000
$0
$0
$0
$0
$0
$0
$0
$1,100,000
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$500,551
$0
$0
$0
$0
$0
$0
$0
$500,551
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,600,551
$0
$0
$0
$0
$0
$0
$0
$1,600,551
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Installment Sales
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
VIII - 16
Water Table of Contents Project Title
Page
Water: Summary By Project Water: Summary By Revenue Source Brown WTP Expansion, Phase 2 Downtown East - West Reinforcing Main Future Water Supply/Source Protection Jordan Lake WTP Lake Michie & Little River Rehabilitation Teer Quarry Water Supply Project, Phase 2 Water & Sewer Fleet Vehicles Water Distribution System Rehabilitation Water Extensions & Improvements Water Facilities Rehabilitation Water Regulatory Improvements Water Residuals Handling
IX - 1 IX - 2 IX - 3 IX - 4 IX - 5 IX - 6 IX - 7 IX - 8 IX - 9 IX - 10 IX - 11 IX - 12 IX - 13 IX - 14
Lake Michie
New Water Piping
Jordan Lake
South Durham WTF Tank
Program Category: Water SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
Brown WTP Expansion, Phase 2
13,577,957
0
0
0
0
0
0
0
13,577,957
Downtown East-West Reinforcing Main
3,850,000
3,850,000
15,910,000
0
0
0
0
0
23,610,000
Future Water Supply/Source Protection
8,373,721
500,000
500,000
500,000
500,000
500,000
500,000
0
11,373,721
Jordan Lake WTP
5,182,146
1,000,000
3,000,000
3,000,000
99,999,999
0
0
0
112,182,145
Lake Michie & Little River Rehabilitation
5,246,238
6,300,000
2,950,000
4,845,000
4,580,000
1,450,000
700,000
0
26,071,238
Teer Quarry Water Supply Project, Phase 2
15,016,950
0
0
0
0
0
0
0
15,016,950
Water & Sewer Fleet Vehicles
4,048,491
1,238,056
0
0
0
0
0
0
5,286,547
Water Distribution System Rehabilitation
60,255,000
21,500,000
5,450,000
4,700,000
12,700,000
2,700,000
2,700,000
0
110,005,000
Water Extensions & Improvements
16,174,244
1,000,000
3,000,000
3,000,000
1,000,000
0
0
0
24,174,244
Water Facilities Rehabilitation
36,615,219
11,200,000
2,300,000
1,300,000
1,300,000
1,300,000
1,300,000
0
55,315,219
Water Regulatory Improvements
35,268,000
0
0
0
0
0
0
0
35,268,000
Water Residuals Handling
45,550,000
0
0
0
0
0
0
0
45,550,000
$249,157,966
$46,588,056
$33,110,000
$17,345,000 $120,079,999
$5,950,000
$0
$477,431,021
IX - 1
$5,200,000
SUMMARY BY REVENUE SOURCE Category Unidentified Rev Unauthorized
Prior Year
FY 2017-18
FY 2018-19
0
0
0
184,414,466
40,500,000
14,200,000
FY 2019-20 0
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
0
0
0
0
0
14,345,000 119,079,999
5,950,000
5,200,000
0
383,689,465
Rev Authorized
6,397,043
0
0
0
0
0
0
0
6,397,043
Pay-As-You-Go
42,790,851
6,088,056
18,910,000
3,000,000
1,000,000
0
0
0
71,788,907
Other
6,470,020
0
0
0
0
0
0
0
6,470,020
Intergovernmental
5,985,586
0
0
0
0
0
0
0
5,985,586
Installment Sales
0
0
0
0
0
0
0
0
0
Impact Fees
0
0
0
0
0
0
0
0
0
GOB Unauthorized
0
0
0
0
0
0
0
0
0
3,100,000
0
0
0
0
0
0
0
3,100,000
$46,588,056 $33,110,000 $17,345,000 $120,079,999
$5,950,000
$5,200,000
GOB Authorized
$249,157,966
IX - 2
$0 $477,431,021
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Water Management
Project Title
Pin Number
Master Plan
Brown WTP Expansion, Phase 2
0835-04-72-4043
Water and Sewer Utility Strategic Plan
2
Project Description The second expansion design phase of the Brown WTP will be finished with current projects, and construction will begin when State Permit is issued. Facility funding for both water treatment plants for residuals handling was moved to a new CIP item titled Water Residuals Handling.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
01/06
Completion
01/19
Continuation
Future Years
TOTAL
$0
$0
$5,735,000
$0
$0
$150,000
$0
$0
$0
$6,954,382
$0
$0
$0
$0
$481,575
$0
$0
$0
$0
$257,000
$0
$0
$0
$0
$0
$13,577,957
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$5,735,000
$0
$0
$0
$0
$0
$150,000
$0
$0
$0
$0
$0
$6,954,382
$0
$0
$0
$0
Equip/Furnishings
$481,575
$0
$0
$0
Contingency
$257,000
$0
$0
$0
$13,577,957
$0
$0
2017-18
Appropriation Planning/Design Land Construction
Total
Revenue
Prior Year
$5,583,091
Prior Year
2022-23
2022-23
Pay-As-You-Go
$2,859,675
$0
$0
$0
$0
$0
$0
$0
$2,859,675
GOB Authorized
$1,000,000
$0
$0
$0
$0
$0
$0
$0
$1,000,000
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $3,457,920
$0
$0
$0
$0
$0
$0
$0
$3,457,920
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental $3,131,282
$0
$0
$0
$0
$0
$0
$0
$3,131,282
Other
$3,129,080
$0
$0
$0
$0
$0
$0
$0
$3,129,080
$0
$0
$0
$0
$0
$0
$0
$0
$0
$13,577,957
$0
$0
$0
$0
$0
$0
$0
$13,577,957
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Unidentified
Total Operating Capital Outlay
Prior Year
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$11,000
$0
$0
$0
$0
$0
$0
$0
$11,000
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$11,000
$0
$0
$0
$0
$0
$0
$0
$11,000
Maint/Operations
IX - 3
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Water Management
Utility Engineering
1,3,4,5
Project Title
Pin Number
Master Plan
Downtown East-West Reinforcing Main
2002 Distribution System Study
Project Description Conduct a route analysis, followed by design, permitting, and construction for a 36-inch water transmission main. The main will be a continuation of the 36inch Hillandale Dual Water Main Replacement project that eventually ties into the elevated storage tank at Pettigrew and Alston.
PROJECT STATUS -
Appropriation Planning/Design
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
06/13
Completion
07/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$7,700,000
$3,850,000
$3,850,000
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
Construction
$0
$0 $15,910,000
$0
$0
$0
$0
$0
$15,910,000
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,850,000 $15,910,000
$0
$0
$0
$0
$0
$23,610,000
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$3,850,000 $15,910,000
Total
Revenue
$3,850,000
Prior Year
2017-18
2022-23
Pay-As-You-Go
$3,850,000
$0
$0
$0
$0
$0
$23,610,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,850,000 $15,910,000
$0
$0
$0
$0
$0
$23,610,000
Future Years
TOTAL
Total Operating
$3,850,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 4
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Water Management
Utility Engineering
All
Project Title
Pin Number
Master Plan
Future Water Supply/Source Protection
Water and Sewer Utility Strategic Plan
Project Description This project provides funding for the acquisition of land needed for expansion of the City's water supplies and protection of existing lakes by acquiring additional buffer areas.
PROJECT STATUS -
Appropriation Planning/Design Land Construction
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$5,449,967
2017-18
2018-19
TYPE REQUEST
Beginning
07/04
Completion
07/23
2019-20
2020-21
Continuation
2021-22
2022-23
Future Years
TOTAL
$121,426
$0
$0
$0
$0
$0
$0
$0
$121,426
$7,455,204
$500,000
$500,000
$500,000
$500,000
$500,000
$500,000
$0
$10,455,204
$797,091
$0
$0
$0
$0
$0
$0
$0
$797,091
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,373,721
$500,000
$500,000
$500,000
$500,000
$500,000
$500,000
$0
$11,373,721
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$66,843
$0
$0
$0
$0
$0
$0
$0
$66,843
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $6,448,800
$500,000
$500,000
$500,000
$500,000
$500,000
$500,000
$0
$9,448,800 $0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental $1,350,000
$0
$0
$0
$0
$0
$0
$0
$1,350,000
Other
$508,078
$0
$0
$0
$0
$0
$0
$0
$508,078
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,373,721
$500,000
$500,000
$500,000
$500,000
$500,000
$500,000
$0
$11,373,721
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Unidentified
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 5
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Water Management
Utility Engineering
All
Project Title
Pin Number
Master Plan
Jordan Lake WTP
0708-04-63-3956
Water and Sewer Utility Strategic Plan
Project Description This project is for a new water supply intake on Jordan Lake. The initial planning will investigate the options for utilizing water allocation and the land needs for pipe lines and pump stations. The next steps are preliminary design, permitting, final design, and construction. A raw water pump station, a raw water transmission line to Durham, and potentially a new water treatment plant are options currently envisioned.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
09/09
Completion
07/24
Continuation
Future Years
TOTAL
$0
$0
$12,182,146
$0
$0
$99,999,999
$0
$0
$112,182,145
Future Years
TOTAL
$0
$0
$500,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,000,000 $99,999,999
$0
$0
$0
$111,682,145
2017-18
2018-19
2019-20
2020-21
2021-22
$5,182,146
$1,000,000
$3,000,000
$3,000,000
$0
$0
$0
$0
$0
$0 $99,999,999
$0
Total
$5,182,146
$1,000,000
$3,000,000
$3,000,000 $99,999,999
$0
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Pay-As-You-Go
$500,000
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
Rev Unauthorized $4,682,146
$1,000,000
$3,000,000
Appropriation Planning/Design Construction
Prior Year
$1,598,105
2022-23
2022-23
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,182,146
$1,000,000
$3,000,000
$3,000,000 $99,999,999
$0
$0
$0
$112,182,145
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 6
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Water
Water Management
Project Title
Pin Number
Lake Michie & Little River Rehabilitation
0857-03-03-6386
District: 2
Master Plan
Project Description This is a Dam Facility Rehabilitation project that combines the Lake Michie Dam Repairs and Little River Dam Repairs projects. Lake Michie needs lead based paint removal, gate repairs, clearing of trees, and hydaulic valve replacement. Little River work needs the lower gate repaired and caulking. Little River needs a 20 year maintenance plan and Lake Michie needs an updated maintenance plan.
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
$115,065
TYPE REQUEST
Beginning
07/04
Completion
07/22
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$970,000
$300,000
$300,000
$500,000
$380,000
$150,000
$0
$0
$0
$0
$0
$0
$4,206,238
$6,000,000
$2,650,000
$4,345,000
$4,200,000 $1,300,000
Future Years
TOTAL
$70,000
$0
$2,670,000
$0
$0
$0
$630,000
$0
$23,331,238
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$70,000
$0
$0
$0
$0
$0
$0
$0
$70,000
$5,246,238
$6,300,000
$2,950,000
$4,845,000
$4,580,000 $1,450,000
$700,000
$0
$26,071,238
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$2,596,238
$0
$0
$0
$0
$0
$0
$0
$2,596,238
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $2,650,000
$6,300,000
$2,950,000
$4,845,000
$4,580,000 $1,450,000
$700,000
$0
$23,475,000
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,246,238
$6,300,000
$2,950,000
$4,845,000
$4,580,000 $1,450,000
$700,000
$0
$26,071,238
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 7
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Water Management
Utility Engineering
2
Project Title
Pin Number
Master Plan
Teer Quarry Water Supply Project, Phase 2
0834-03-24-3512
Water and Sewer Utility Strategic Plan
Project Description This project will convert an abandoned stone quarry in northern Durham into a raw water storage facility. The finished project will add approximately 7 MGD of water supply to the City's existing 37 MGD supply.
PROJECT STATUS -
Appropriation Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$1,453,413
TYPE REQUEST
Beginning
07/04
Completion
07/18
Continuation
Future Years
TOTAL
$0
$0
$2,880,000
$0
$0
$0
$0
$0
$0
$9,709,560
2017-18
2018-19
2019-20
2020-21
2021-22
$2,880,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$9,709,560
$0
$0
$0
$0
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,427,390
$0
$0
$0
$0
$0
$0
$0
$2,427,390
$15,016,950
$0
$0
$0
$0
$0
$0
$0
$15,016,950
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$4,853,500
$0
$0
$0
$0
$0
$0
$0
$4,853,500
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
$200,000
$0
$0
$0
$0
$0
$0
$0
$200,000
Rev Unauthorized $9,963,450
$0
$0
$0
$0
$0
$0
$0
$9,963,450
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$15,016,950
$0
$0
$0
$0
$0
$0
$0
$15,016,950
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Rev Authorized
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 8
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Water
Fleet
Project Title
Pin Number
Division/Program:
District: All
Master Plan
Water & Sewer Fleet Vehicles
Project Description This project is for the financing of fleet vehicles for all Water Management Department Vehicles.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$1,151,010
TYPE REQUEST
Beginning
10/11
Completion
03/24
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,048,491
$1,238,056
$0
$0
$0
$0
$0
$0
$5,286,547
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,048,491
$1,238,056
$0
$0
$0
$0
$0
$0
$5,286,547
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total
Revenue
Prior Year
2022-23
Pay-As-You-Go
$3,021,397
$1,238,056
$0
$0
$0
$0
$0
$0
$4,259,453
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,027,094
$0
$0
$0
$0
$0
$0
$0
$1,027,094
Other
Unidentified
Total Operating
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,048,491
$1,238,056
$0
$0
$0
$0
$0
$0
$5,286,547
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 9
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Water
Water Management
Project Title
Pin Number
District: All
Master Plan
Water Distribution System Rehabilitation
Project Description This project involves condition assesment, rehabilitation and replacement of the City's Water Distribution System. Mains, valves, hydrants and pump stations are inspected and analyzed for decisions on appropriate methods of rehabiltation or replacement of vital infrastructure. This is an on-going program.
PROJECT STATUS -
Appropriation Planning/Design Land Construction
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$1,108,080
TYPE REQUEST
Beginning
12/04
Completion
12/24
Continuation
Future Years
TOTAL
$700,000
$0
$13,950,000
$0
$0
$0
$4,000,000 $10,700,000 $2,000,000 $2,000,000
$0
$96,055,000 $0
2017-18
2018-19
2019-20
2020-21
2021-22
$7,900,000
$1,500,000
$450,000
$700,000
$2,000,000
$700,000
$0
$0
$0
$0
$0
$0
$52,355,000 $20,000,000
$5,000,000
2022-23
Equip/Furnishings
$0
$0
$0
$0
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$0
$0
$0
$0
$0
$60,255,000 $21,500,000
$5,450,000
$4,700,000 $12,700,000 $2,700,000 $2,700,000
$0
$110,005,000
Future Years
TOTAL
Total
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Pay-As-You-Go
$10,778,341
$0
$0
$0
$0
$0
$0
$0
$10,778,341
GOB Authorized
$1,700,000
$0
$0
$0
$0
$0
$0
$0
$1,700,000
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $47,276,659 $21,500,000
$5,450,000
$4,700,000 $12,700,000 $2,700,000 $2,700,000
$0
$97,026,659 $0
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
$500,000
$0
$0
$0
$0
$0
$0
$0
$500,000
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$60,255,000 $21,500,000
$5,450,000
$4,700,000 $12,700,000 $2,700,000 $2,700,000
$0
$110,005,000
Future Years
TOTAL
Intergovernmental
Total Operating
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 10
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Public Works
Engineering
All
Project Title
Pin Number
Master Plan
Water Extensions & Improvements
Water and Sewer Utility Strategic Plan
Project Description This ongoing program constructs water line extensions requested by petitions, relocates water lines resulting from NCDOT projects, reimburses developers for water improvements, and constructs lines to abate health hazards.
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
$171,730
TYPE REQUEST
Beginning
07/10
Completion
07/21
Continuation
Future Years
TOTAL
$0
$0
$109,423
$0
$0
$0
$0
$0
$0
$24,051,382
2017-18
2018-19
2019-20
2020-21
2021-22
$109,423
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$16,051,382
$1,000,000
$3,000,000
$3,000,000
$1,000,000
2022-23
$3,087
$0
$0
$0
$0
$0
$0
$0
$3,087
$10,352
$0
$0
$0
$0
$0
$0
$0
$10,352
$16,174,244
$1,000,000
$3,000,000
$3,000,000
$1,000,000
$0
$0
$0
$24,174,244
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$8,350,000
$1,000,000
$3,000,000
$3,000,000
$1,000,000
$0
$0
$0
$16,350,000
GOB Authorized
$400,000
$0
$0
$0
$0
$0
$0
$0
$400,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,650,000
$0
$0
$0
$0
$0
$0
$0
$1,650,000
Rev Unauthorized $3,250,000
$0
$0
$0
$0
$0
$0
$0
$3,250,000
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental $1,004,304
$0
$0
$0
$0
$0
$0
$0
$1,004,304
Other
$1,519,940
$0
$0
$0
$0
$0
$0
$0
$1,519,940
$0
$0
$0
$0
$0
$0
$0
$0
$0
$16,174,244
$1,000,000
$3,000,000
$3,000,000
$1,000,000
$0
$0
$0
$24,174,244
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
GOB Unauthorize
Rev Authorized
Unidentified
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 11
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Water
Water Management
Project Title
Pin Number
Master Plan
Water Facilities Rehabilitation
0835-04-72-4043
Water and Sewer Utility Strategic Plan
All
Project Description This project is to maintain the infrastructure at the water faciities, enhance the current operation, and maintain compliance with State regulations.
PROJECT STATUS -
Appropriation Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$7,558,715
TYPE REQUEST
Beginning
12/09
Completion
12/23
Continuation
Future Years
TOTAL
$100,000
$0
$2,856,000
$0
$0
$0
$1,200,000 $1,200,000 $1,200,000
$0
$51,674,219
2017-18
2018-19
2019-20
2020-21
2021-22
$1,656,000
$500,000
$300,000
$100,000
$100,000
$100,000
$0
$0
$0
$0
$0
$0
$34,174,219 $10,700,000
$2,000,000
$1,200,000
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$785,000
$0
$0
$0
$0
$0
$0
$0
$785,000
$36,615,219 $11,200,000
$2,300,000
$1,300,000
$1,300,000 $1,300,000 $1,300,000
$0
$55,315,219
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$1,149,975
$0
$0
$0
$0
$0
$0
$0
$1,149,975
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,982,648
$0
$0
$0
$0
$0
$0
$0
$3,982,648
Rev Unauthorized $31,442,796 $11,200,000
$1,300,000 $1,300,000 $1,300,000
Rev Authorized
$2,300,000
$1,300,000
$0
$50,142,796
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$39,800
$0
$0
$0
$0
$0
$0
$0
$39,800
$0
$0
$0
$0
$0
$0
$0
$0
$0
$36,615,219 $11,200,000
$2,300,000
$1,300,000
$1,300,000 $1,300,000 $1,300,000
$0
$55,315,219
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Other
Unidentified
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 12
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Water
Water Management
Project Title
Pin Number
District: All
Master Plan
Water Regulatory Improvements
Water and Sewer Strategic Plan
Project Description This project consists of Long Term Enhanced Surface Treatment Rule and Safe Drinking Water Act Stage II Disinfection By-Product Rule Improvements that are a result of compliance with new regulations. The projects involve the installation of ultraviolet disinfection, ozone and other ancillary facility improvements at both water treatment plants.
PROJECT STATUS -
Appropriation Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$3,945,351
TYPE REQUEST
Beginning
12/07
Completion
06/19
Continuation
Future Years
TOTAL
$0
$0
$6,000,000
$0
$0
$0
$0
$0
$0
$26,268,000
2017-18
2018-19
2019-20
2020-21
2021-22
$6,000,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$26,268,000
$0
$0
$0
$0
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$3,000,000
$0
$0
$0
$0
$0
$0
$0
$3,000,000
$35,268,000
$0
$0
$0
$0
$0
$0
$0
$35,268,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$3,152,635
$0
$0
$0
$0
$0
$0
$0
$3,152,635
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
$564,395
$0
$0
$0
$0
$0
$0
$0
$564,395
Rev Unauthorized $31,550,970
$0
$0
$0
$0
$0
$0
$0
$31,550,970
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$35,268,000
$0
$0
$0
$0
$0
$0
$0
$35,268,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Rev Authorized
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 13
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Water
Water Management
Project Title
Pin Number
District: All
Master Plan
Water Residuals Handling
Water and Sewer Utility Strategic Plan
Project Description This project will add facilities at both water treatment plants for residuals management. Facilities will include thickening, dewatering, and disposal of solids residuals from the water treatment process. This project will enhance the current operations and maintain compliance with State regulations.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/11
Completion
07/19
Continuation
Future Years
TOTAL
$0
$0
$6,550,000
$0
$0
$0
$0
$0
$0
$39,000,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$45,550,000
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$6,550,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$39,000,000
$0
$0
$0
$0
Equip/Furnishings
$0
$0
$0
$0
Contingency
$0
$0
$0
$0
$45,550,000
$0
$0
2017-18
Appropriation Planning/Design Land Construction
Total
Revenue
Prior Year
$40,500,000
Prior Year
2022-23
2022-23
Pay-As-You-Go
$1,612,247
$0
$0
$0
$0
$0
$0
$0
$1,612,247
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $43,691,725
$0
$0
$0
$0
$0
$0
$0
$43,691,725
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$246,028
$0
$0
$0
$0
$0
$0
$0
$246,028
$0
$0
$0
$0
$0
$0
$0
$0
$0
$45,550,000
$0
$0
$0
$0
$0
$0
$0
$45,550,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Other
Unidentified
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
IX - 14
Wastewater Table of Contents Project Title
Page
Wastewater: Summary By Project Wastewater: Summary By Revenue Source Enhanced Nitrogen Removal Facility Paving Reclaimed Water Systems, Phase 1 & 2 Sewer Collection System Rehabilitation Sewer Extensions & Improvements Southeast Regional Lift Station Wastewater Process Rehabilitation Water Management Facility Expansion
S. Durham Water Reclamation Facility
N. Durham WTF – Biological Treatment
Brown Water Treatment Facility
X-1 X-2 X-3 X-4 X-5 X-6 X-7 X-8 X-9 X-10
Water Treatment Facility
Program Category: Wastewater SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
18,723,704
15,300,000
0
0
600,000
7,600,000
10,000,000
0
52,223,704
Facility Paving
2,860,000
6,550,000
0
0
0
0
0
0
9,410,000
Reclaimed Water Systems, Phases 1 & 2
2,181,000
6,800,000
0
4,400,000
4,400,000
0
0
0
17,781,000
Sewer Collection System Rehabilitation
63,243,749
24,500,000
7,000,000
16,400,000
4,850,000
4,400,000
4,400,000
0
124,793,749
Sewer Extensions & Improvements
8,796,842
2,000,000
2,000,000
2,000,000
1,000,000
0
0
0
15,796,842
Southeast Regional Lift Station
4,700,000
0
0
0
0
0
0
0
4,700,000
Wastewater Process Rehabilitation
116,535,000
21,000,000
7,744,360
23,040,160
26,691,400
26,763,780
22,000,000
0
243,774,700
Water Management Facility Expansion
61,000,000
0
0
0
0
0
0
0
61,000,000
$278,040,295
$76,150,000
$16,744,360
$45,840,160
$37,541,400
$38,763,780
$0
$529,479,995
Enhanced Nitrogen Removal
X-1
$36,400,000
SUMMARY BY REVENUE SOURCE Category Unidentified Rev Unauthorized
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
0
0
0
0
0
0
0
0
0
208,226,000
43,100,000
7,744,360
27,440,160
31,691,400
34,363,780
32,000,000
0
384,565,700
Rev Authorized
3,136,611
0
0
0
0
0
0
0
3,136,611
Pay-As-You-Go
52,950,787
33,050,000
9,000,000
18,400,000
5,850,000
4,400,000
4,400,000
0
128,050,787
Other
5,107,232
0
0
0
0
0
0
0
5,107,232
Intergovernmental
3,076,115
0
0
0
0
0
0
0
3,076,115
611,225
0
0
0
0
0
0
0
611,225
Impact Fees
0
0
0
0
0
0
0
0
0
GOB Unauthorized
0
0
0
0
0
0
0
0
0
4,932,325
0
0
0
0
0
0
0
4,932,325
Installment Sales
GOB Authorized
$278,040,295
$76,150,000 $16,744,360 $45,840,160 $37,541,400 $38,763,780 $36,400,000
X-2
$0 $529,479,995
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Water Management
Project Title
Pin Number
Master Plan
Enhanced Nitrogen Removal
0708-04-63-3956
Water and Sewer Utility Strategic Plan
All
Project Description This project will provide equipment and structures at the South and North Durham Water Reclamation Facilities to meet new requirements for wastewater discharge. Large construction items include a new 145' diameter clarifier at North Durham, replacing a clarifier at South Durham and new denitrification filters at South Durham. Installation of process equipment to remove phosphorous from dewatering sludge side stream is also included.
PROJECT STATUS -
Appropriation Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/10
Completion
07/22
Continuation
Future Years
TOTAL
$900,000
$0
$4,480,000
$0
$0
$0
$0
$0 $7,000,000 $9,100,000
$0
$46,307,704
2017-18
2018-19
2019-20
2020-21
2021-22
$2,080,000
$300,000
$0
$0
$600,000
$600,000
$0
$0
$0
$0
$0
$0
$15,207,704 $15,000,000
$0
2022-23
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,436,000
$0
$0
$0
$0
$0
$0
$0
$1,436,000
$18,723,704 $15,300,000
$0
$0
$600,000 $7,600,000 $10,000,000
$0
$52,223,704
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$7,165,029
$0
$0
$0
$0
$0
$0
$0
$7,165,029
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
$919,246
$0
$0
$0
$0
$0
$0
$0
$919,246
Rev Unauthorized $8,215,754 $15,300,000
$600,000 $7,600,000 $10,000,000
Installment Sales
Rev Authorized
$0
$0
$0
$41,715,754
$611,225
$0
$0
$0
$0
$0
$0
$0
$611,225
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental $1,217,455
$0
$0
$0
$0
$0
$0
$0
$1,217,455
Other
$594,995
$0
$0
$0
$0
$0
$0
$0
$594,995
$0
$0
$0
$0
$0
$0
$0
$0
$0
$18,723,704 $15,300,000
$0
$0
$600,000 $7,600,000 $10,000,000
$0
$52,223,704
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Impact Fees
Unidentified
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X-3
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Water Management
Utility Engineering
All
Project Title
Pin Number
Master Plan
Facility Paving
Water and Sewer Utility Strategic Plan
Project Description The pavement at all the facilities operated by Water Management are in various levels of disrepair and need resurfacing or replacement. Addressing pavement needs now will control future costs. FY'18 funding consists of roadway improvements for new facility expansion.
PROJECT STATUS -
Appropriation Construction
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$621,594
TYPE REQUEST
Beginning
07/09
Completion
06/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$2,860,000
$6,550,000
$0
$0
$0
$0
$0
$0
$9,410,000
Total
$2,860,000
$6,550,000
$0
$0
$0
$0
$0
$0
$9,410,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
2022-23
Pay-As-You-Go
$2,090,000
$6,550,000
$0
$0
$0
$0
$0
$0
$8,640,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$770,000
$0
$0
$0
$0
$0
$0
$0
$770,000
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,860,000
$6,550,000
$0
$0
$0
$0
$0
$0
$9,410,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Rev Unauthorized
Total Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X-4
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Water Management
Utility Engineering
2
Project Title
Pin Number
Master Plan
Reclaimed Water Systems, Phases 1 & 2
0842-01-18-1935
Water and Sewer Utility Strategic Plan
Project Description Funds have been approved for Phase 1 (which includes bulk tank distribution facilities, a Reclaimed Water Master Plan, and construction of a reclaimed water pumping station). Phase 2 consists of initial pipelines to distribute reclaimed water to areas that can use reclaimed water to replace water demand currently provided by the potable treated water system. FY'18 funds construction of the new distribution system.
PROJECT STATUS -
Appropriation
Prior Year
Planning/Design Land Construction Contingency
Total
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
$0
TYPE REQUEST
Beginning
09/09
Completion
07/22
Continuation
Future Years
TOTAL
$0
$0
$916,000
$0
$0
$0
$0
$0
$0
$16,702,000
$0
$0
$0
$0
$163,000
$4,400,000
$0
$0
$0
$17,781,000
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
$916,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,102,000
$6,800,000
$0
$4,400,000
$4,400,000
$163,000
$0
$0
$0
$2,181,000
$6,800,000
$0
$4,400,000
2017-18
2018-19
2019-20
2020-21
2021-22
Prior Year
2022-23
2022-23
Pay-As-You-Go
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $2,181,000
$6,800,000
$0
$4,400,000
$4,400,000
$0
$0
$0
$17,781,000
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,181,000
$6,800,000
$0
$4,400,000
$4,400,000
$0
$0
$0
$17,781,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total Operating
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X-5
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Water Management
Utility Engineering
All
Project Title
Pin Number
Master Plan
Sewer Collection System Rehabilitation
Water & Sewer Strategic Plan
Project Description This project involves condition assessment, rehabilitation and replacement of the City's Sewer Collection System. Sewer mains, manholes, outfalls, force mains and pump stations are inspected and analyzed for decisions on appropriate methods of rehabilitation or replacement of infrastructure. This is an on-going program.
PROJECT STATUS -
Appropriation Planning/Design Land Construction Equip/Furnishings Contingency
Total
Revenue Pay-As-You-Go
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$343,212
TYPE REQUEST
Beginning
12/04
Completion
12/24
Continuation
Future Years
TOTAL
$400,000
$0
$6,143,920
$0
$0
$46,767
$4,450,000 $4,000,000 $4,000,000
$0
$118,597,167 $5,895
2017-18
2018-19
2019-20
2020-21
2021-22
$2,543,920
$2,000,000
$0
$400,000
$400,000
$400,000
$46,767
$0
$0
$0
$0
$0
$60,647,167 $22,500,000
$7,000,000 $16,000,000
2022-23
$5,895
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,850,000 $4,400,000 $4,400,000
$0
$124,793,749
Future Years
TOTAL
$63,243,749 $24,500,000
Prior Year
2017-18
2018-19
2019-20
2021-22
2022-23
$0
$94,151,359
$0
$0
$0
$0
$0
$0
$0
$4,850,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$2,187,769
$0
$0
$0
$0
$0
$0
$0
$2,187,769
Rev Unauthorized $18,289,118
$0
$0
$0
$0
$0
$0
$0
$18,289,118
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental $1,858,660
$0
$0
$0
$0
$0
$0
$0
$1,858,660
Other
$3,456,843
$0
$0
$0
$0
$0
$0
$0
$3,456,843
$0
$0
$0
$0
$0
$0
$0
$0
$0
$4,850,000 $4,400,000 $4,400,000
$0
$124,793,749
Future Years
TOTAL
GOB Unauthorize
Rev Authorized
Unidentified
Total Operating
$63,243,749 $24,500,000
Prior Year
$7,000,000 $16,400,000
2020-21
$4,850,000
GOB Authorized
$32,601,359 $24,500,000
$7,000,000 $16,400,000
$7,000,000 $16,400,000
$4,850,000 $4,400,000 $4,400,000
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X-6
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Public Works
Engineering
All
Project Title
Pin Number
Master Plan
Sewer Extensions & Improvements
Water and Sewer Utility Strategic Plan
Project Description This ongoing program constructs sewer line extensions requested by petitions, relocates sewer lines resulting from NCDOT projects, reimburses developers for sewer improvements, and constructs lines to abate health hazards.
PROJECT STATUS -
Appropriation
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$0
TYPE REQUEST
Beginning
07/12
Completion
07/21
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
Planning/Design
$0
$0
$0
$0
$0
$0
$0
$0
Land
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,796,842
$2,000,000
$2,000,000
$2,000,000
$1,000,000
$0
$0
$0
$15,796,842
$8,796,842
$2,000,000
$2,000,000
$2,000,000
$1,000,000
$0
$0
$0
$15,796,842
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Construction
Total Revenue
Prior Year
2022-23
Pay-As-You-Go
$2,909,399
$2,000,000
$2,000,000
$2,000,000
$1,000,000
$0
$0
$0
$9,909,399
GOB Authorized
$82,325
$0
$0
$0
$0
$0
$0
$0
$82,325
$0
$0
$0
$0
$0
$0
$0
$0
$0
$29,596
$0
$0
$0
$0
$0
$0
$0
$29,596
Rev Unauthorized $5,775,522
$0
$0
$0
$0
$0
$0
$0
$5,775,522
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,796,842
$2,000,000
$2,000,000
$2,000,000
$1,000,000
$0
$0
$0
$15,796,842
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
GOB Unauthorize Rev Authorized
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X-7
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Water Management
Water and Sewer
4
Project Title
Pin Number
Master Plan
Southeast Regional Lift Station
Water and Sewer Strategic Plan
Project Description The goal of this project is to construct a new regional sewage lift station in the Lick Basin/Eastern portion of the City's sewer service area. FY16 will focus on the evaluation and design for the new infrastructure which will support ongoing development.
PROJECT STATUS -
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/16
Completion
07/20
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
$4,700,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$4,700,000
$0
$0
$0
$0
$0
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Rev Unauthorized $4,700,000
$0
$0
$0
$0
$0
$4,700,000
$0
$0
$0
$0
$0
Appropriation Planning/Design Construction
Total
Prior Year
$0
X-8
Future Years
TOTAL
$0
$0
$4,700,000
$0
$0
$0
$0
$0
$4,700,000
Future Years
TOTAL
$0
$0
$4,700,000
$0
$0
$4,700,000
2022-23
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Wastewater
Water Management
Project Title
Pin Number
District: 2
Master Plan
Wastewater Process Rehabilitation
Water and Sewer Strategic Plan
Project Description This project provides for ongoing needs at both North and South Durham Water Reclamation Facilities, which include roof replacement, new coatings, odor system rehab, electric blower rehab, piping changes and other large rehabilitation projects.
PROJECT STATUS -
Appropriation Planning/Design Construction
Prior Year
$12,870,000
$1,663,271
2017-18
$1,000,000
$102,825,000 $20,000,000
Contingency
Total
$840,000
$0
$116,535,000 $21,000,000
Prior Year
Revenue
PROJECTED DATES:
June 2017
Total Expenditures
TYPE REQUEST
Beginning
07/07
Completion
07/24
2018-19
2019-20
$744,360
$1,040,160
2020-21
Continuation
2021-22
2022-23
Future Years
TOTAL
$1,691,400 $1,763,780 $2,000,000
$0
$21,109,700
$7,000,000 $22,000,000 $25,000,000 $25,000,000 $20,000,000
$0
$221,825,000
$0
$0
$840,000
$7,744,360 $23,040,160 $26,691,400 $26,763,780 $22,000,000
$0
$0
$0
$0
$0
$243,774,700
Future Years
TOTAL
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Pay-As-You-Go
$3,885,000
$0
$0
$0
$0
$0
$0
$0
$3,885,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,744,360 $23,040,160 $26,691,400 $26,763,780 $22,000,000
$0
$238,834,306
Rev Unauthorized$111,594,606 $21,000,000
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,055,394
$0
$0
$0
$0
$0
$0
$0
$1,055,394
$0
$0
$0
$0
$0
$0
$0
$0
$0
$7,744,360 $23,040,160 $26,691,400 $26,763,780 $22,000,000
$0
$243,774,700
Future Years
TOTAL
Other Unidentified
Total
Operating
$116,535,000 $21,000,000
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X-9
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Wastewater
Water Management
Utility Engineering
1
Project Title
Pin Number
Master Plan
Water Management Facility Expansion
0842-09-16-8832
Project Description This project involves the renovation and expansion of the Water Management Facility at Mist Lake Drive to accommodate the Water & Sewer Maintenance Division that is currently located at the Public Works Operations Center.
PROJECT STATUS -
Appropriation Planning/Design Construction
Total Revenue
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$206,417
TYPE REQUEST
Beginning
09/10
Completion
07/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$5,000,000
$0
$0
$0
$0
$0
$0
$0
$5,000,000
$56,000,000
$0
$0
$0
$0
$0
$0
$0
$56,000,000
$61,000,000
$0
$0
$0
$0
$0
$0
$0
$61,000,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Prior Year
2022-23
Pay-As-You-Go
$4,300,000
$0
$0
$0
$0
$0
$0
$0
$4,300,000
GOB Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
GOB Unauthorize
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Authorized
$0
$0
$0
$0
$0
$0
$0
$0
$0
Rev Unauthorized $56,700,000
$0
$0
$0
$0
$0
$0
$0
$56,700,000
Installment Sales
$0
$0
$0
$0
$0
$0
$0
$0
$0
Impact Fees
$0
$0
$0
$0
$0
$0
$0
$0
$0
Intergovernmental
$0
$0
$0
$0
$0
$0
$0
$0
$0
Other
$0
$0
$0
$0
$0
$0
$0
$0
$0
Unidentified
$0
$0
$0
$0
$0
$0
$0
$0
$0
$61,000,000
$0
$0
$0
$0
$0
$0
$0
$61,000,000
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
Total
Operating
Prior Year
2022-23
Capital Outlay
$0
$0
$0
$0
$0
$0
$0
$0
$0
Maint/Operations
$0
$0
$0
$0
$0
$0
$0
$0
$0
Personnel
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$0
$0
$0
$0
$0
X - 10
Other Enterprise Funds Table of Contents Project Title
Page
Other Enterprise Funds: Summary By Project Other Enterprise Funds: Summary By Revenue Source Downtown Parking Garage (NEW) Off-Street Parking Upgrades Parking Garages - Elevator Modernizations Parking Security Upgrades/Enhancement Transit Fleet Vehicles
XI XI XI XI XI XI XI
-
1 2 3 4 5 6 7
Off Street Parking
Durham Bull City Connector - Transit Fleet
Church Street Parking Garage
Site of New Downtown Parking Garage
Program Category: Other Enterprise Funds SUMMARY BY PROJECT Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Request
Downtown Parking Garage (NEW)
2,500,000
20,595,288
0
0
0
0
0
0
23,095,288
Off-Street Parking Upgrades
1,000,000
0
0
0
0
0
0
0
1,000,000
Parking Garages Elevator Modernizations
1,891,000
0
0
0
0
0
0
0
1,891,000
Parking Security Upgrades/Enha ncements
500,000
0
0
0
0
0
0
0
500,000
4,650,000
0
0
0
0
0
0
0
4,650,000
$10,541,000
$20,595,288
$0
$0
$0
$0
$0
$0
$31,136,288
Transit Fleet Vehicles
XI - 1
SUMMARY BY REVENUE SOURCE Category
Prior Year
FY 2017-18
FY 2018-19
FY 2019-20
FY 2020-21
FY 2021-22
FY 2022-23
Future Years
Total Funds
Intergovernmental
4,650,000
0
0
0
0
0
0
0
4,650,000
Installment Sales
5,891,000
20,595,288
0
0
0
0
0
0
26,486,288
$10,541,000
$20,595,288
$0
$0
$0
$0
$0
$0
$31,136,288
XI - 2
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Other Enterprise Funds
Transportation
Parking
1
Project Title
Pin Number
Master Plan
Downtown Parking Garage (NEW)
Parking Study Master Plan
Project Description This project consists of design and construction of a new mixed-use Downtown parking garage. The new facility will consist of 667 parking spaces, approximately 15,687 SF Retail and 4,750 SF of Office at the ground floor level for the Parking Division. FY'18 funding is for construction.
PROJECT STATUS -
Appropriation Planning/Design Construction
Total Revenue Installment Sales
Total
PROJECTED DATES:
June 2017
Total Expenditures
Prior Year
$2,500,000
$2,394,793
TYPE REQUEST
Beginning
07/16
Completion
01/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$0
$0
$0
$0
$0
$0
$0
$2,500,000
$0 $20,595,288
$0
$0
$0
$0
$0
$0
$20,595,288
$2,500,000 $20,595,288
$0
$0
$0
$0
$0
$0
$23,095,288
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$2,500,000 $20,595,288
$0
$0
$0
$0
$0
$0
$23,095,288
$2,500,000 $20,595,288
$0
$0
$0
$0
$0
$0
$23,095,288
Prior Year
XI - 3
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
Other Enterprise Funds
Transportation
Parking
Project Title
Pin Number
Master Plan
Off-Street Parking Upgrades
District:
Parking Study Master Plan
Project Description FY17 funding will allow for procurement of a new comprehensive Parking Access and Revenue control system to replace the defunct equipment in five (5) city owned parking garages.
PROJECT STATUS -
$0
TYPE REQUEST
Beginning
07/16
Completion
06/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
Equip/Furnishings $1,000,000
$0
$0
$0
$0
$0
Total
$1,000,000
$0
$0
$0
$0
$0
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
$1,000,000
$0
$0
$0
$0
$0
$1,000,000
$0
$0
$0
$0
$0
Appropriation
Installment Sales
Total
Prior Year
PROJECTED DATES:
June 2017
Total Expenditures
XI - 4
Future Years
TOTAL
$0
$0
$1,000,000
$0
$0
$1,000,000
Future Years
TOTAL
$0
$0
$1,000,000
$0
$0
$1,000,000
2022-23
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Other Enterprise Funds
General Services
Transportation / Parking Garag
5
Project Title
Pin Number
Master Plan
Parking Garages - Elevator Modernizations
0821-08-88-7397
Project Description The Project involves up-grading and modernizing seven elevators in three downtown parking garages - Chapel Hill Street (1), Durham Centre (3) and Corcoran Street (3). The elevators can no longer be effectively repaired.
PROJECT STATUS Total Expenditures
Appropriation Construction
Prior Year
PROJECTED DATES:
June 2017 $1,886,924
TYPE REQUEST
Beginning
06/16
Completion
06/18
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
Future Years
TOTAL
$1,891,000
$0
$0
$0
$0
$0
$0
$0
$1,891,000
Total
$1,891,000
$0
$0
$0
$0
$0
$0
$0
$1,891,000
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$1,891,000
$0
$0
$0
$0
$0
$0
$0
$1,891,000
$1,891,000
$0
$0
$0
$0
$0
$0
$0
$1,891,000
Installment Sales
Total
XI - 5
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Other Enterprise Funds
Transportation
Parking
1
Project Title
Pin Number
Master Plan
Parking Security Upgrades/Enhancements
Project Description Funding includes upgrading the current security and camera surveillance systems in various parking garages.
PROJECT STATUS -
Appropriation
Prior Year
Equip/Furnishings
Total
PROJECTED DATES:
June 2017
Total Expenditures
$0
TYPE REQUEST
Beginning
07/16
Completion
06/19
Revision
2017-18
2018-19
2019-20
2020-21
2021-22
$500,000
$0
$0
$0
$0
$0
$500,000
$0
$0
$0
$0
$0
2017-18
2018-19
2019-20
2020-21
2021-22
Future Years
TOTAL
$0
$0
$500,000
$0
$0
$500,000
Future Years
TOTAL
2022-23
Revenue
Prior Year
Installment Sales
$500,000
$0
$0
$0
$0
$0
$0
$0
$500,000
$500,000
$0
$0
$0
$0
$0
$0
$0
$500,000
Total
XI - 6
2022-23
CITY OF DURHAM CAPITAL IMPROVEMENTS PROGRAM Service Area
Department
Division/Program:
District:
Other Enterprise Funds
Transportation
Transit Services
All
Project Title
Pin Number
Master Plan
Transit Fleet Vehicles
Project Description This funding provides for the purchase and replacement of new motor vehicles for transit services.
PROJECT STATUS Total Expenditures
$2,446,255
TYPE REQUEST
Beginning
03/14
Completion
09/19
Continuation
2017-18
2018-19
2019-20
2020-21
2021-22
Equip/Furnishings $4,650,000
$0
$0
$0
$0
$0
Total
$4,650,000
$0
$0
$0
$0
$0
Revenue
Prior Year
2017-18
2018-19
2019-20
2020-21
2021-22
Intergovernmental $4,650,000
$0
$0
$0
$0
$0
$4,650,000
$0
$0
$0
$0
$0
Appropriation
Total
Prior Year
PROJECTED DATES:
June 2017
XI - 7
Future Years
TOTAL
$0
$0
$4,650,000
$0
$0
$4,650,000
Future Years
TOTAL
$0
$0
$4,650,000
$0
$0
$4,650,000
2022-23
2022-23
City Of Durham Capital Improvements Program Projects Requested and Unfunded Service Area Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Culture & Recreation Downtown Revitalization General Services General Services Public Protection Public Protection Public Protection Public Protection Public Protection Public Protection Transportation Transportation
Project Title Aquatics Center Central Park Phase 2 Coley Road Park East End Park/ED Mickle Recreation Center Phase II Lake Michie Phase II Lakeview Park Phase II Full Service Recreation Center Northern Athletic Park Phase 1 & 2 Northgate Park Renovation Southern Durham Recreation Center Church Street Parking Deck Phase II City Hall Space Planning & 2nd Flr. Annex Design City Hall Print Shop Upfits Fire Station #6 Fire Station #7 Fire Station Old #9 Phase II Fire Station #10 Fire Station #19 Fire Station #20 Downtown Loop Two-Way Conversion NC751 Widening
Total $
15,750,000 171,491 8,100,000 597,845 347,833 244,146 20,000,000 10,100,000 1,075,147 25,000,000 2,867,025 350,000 315,000 5,960,000 5,960,000 321,237 4,850,000 6,550,000 6,550,000 12,000,000 3,000,000
$ 130,109,724
Thank You! MAYOR BILL BELL
Thank you for 45 years of public service to the City and County of Durham, North Carolina. Thanks to your work and service, Durham is a place where great things are happening and will continue to happen.
Mayor Bell, 1972 Durham County Commissioner