STORMWATER

Microtunnelling used for twin culvert replacement project By Nicholas MacEachern

H

arbourside Engineering Consultants (HEC) was retained by Construction Demathieu and Bard Inc. (CDB) to develop the structural design and temporary construction work designs required for the Calamity Creek Culvert Replacement Project, just north of New Liskeard, Ontario. The purpose of the project was to replace and decommission an existing cast-in-place reinforced concrete, single cell box culvert having a cross section of approximately 3.05 m wide x 2.45 m high and running 270 m long. The existing structure was situated up to 8 m below the grade of the roadway, which added to the project’s challenges. The Ministry of Transportation of Ontario (MTO) project documents specified twin 2.1 m inside diameter (I.D.) pipe culverts to meet the predetermined hydraulic capacity requirements. The MTO contract also required that the project be completed without causing significant disruptions to the traffic along Highway 11. Forterra Pipe & Precast Ltd. recommended that the concrete microtunnelling pipe be produced using the “drycast” process, which allowed for higher production rates compared to the specified “wetcast” process. The pipe segments were designed with a typical microtunnelling joint comprised of a 13 mm thick galvanized steel ring. In addition to the steel endring, the joint also featured a confined tapered profile gasket that provides a hydrostatic capacity of 30 psi. Forterra’s engineering team provided the structural designs for the pipe, which were reviewed and accepted by Harbourside Engineering and the MTO. The 2.1 m microtunnelling pipe also needed to meet several quality assurance and certification standards, including the requirements of the Canadian Precast Concrete Quality Assurance (CPCQA) certification program. 16  |  December 2021

Aerial view of the Calamity Creek Culvert Replacement Project.

Pipe segments were also assessed using the requirements of the D-Load test and hydrostatic test, which were performed by Forterra at their manufacturing facility. The D-Load (or Three Edge Bearing test – 3EB) is a physical test used to ensure the pipe will provide the required structural capacity. CRS Tunnelling Inc. was retained for this project and chose an earth pressure balance tunnel boring machine (EPBTBM) to complete the work. It allowed for soft, wet, or unstable ground to be tunnelled safely with speed. This EPBTBM was equipped with face control doors and chamber access in case the crew needed to go into the cutting head chamber for maintenance or inspection. The latter proved important as it hit a major underground obstacle of wood debris during the first drive. The twin pipe culverts were installed in two drives. Each drive would run the entire 270 m length. As mentioned

above, the project did encounter a delay during the first drive. This resulted in the second drive occurring during the winter months, with some temperatures hitting as low as -40°C. Both the concrete microtunnelling pipe and the EPBTBM continued to operate throughout these conditions. The second drive broke through the receiving shaft on December 12, 2019. The project, which included the decommissioning of the existing culvert was completed in October 2020. Reprinted from the Canadian Concrete Pipe and Precast Journal, Fall 2021.

Nicholas MacEachern is with Harbourside Engineering Consultants. Email: nmaceachern@harboursideengineering.ca For more information, visit: www.forterra.com

Environmental Science & Engineering Magazine


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Red Deer’s new residuals management facility will reduce environmental impacts

2min
pages 62-64

Product Showcase

7min
pages 56-58

District metered areas: Why accuracy matters

7min
pages 54-55

Using hydrogeological flow modelling to identify sources of hepatitis outbreaks

10min
pages 50-53

Using a camera nozzle and chain cutter to efficiently handle blocked sewers

4min
pages 46-47

Dauphin, MB meets its cold weather ammonia level requirements

4min
pages 44-45

Remote gas flow monitoring in a biodigester

2min
pages 42-43

Using air-operated double-diaphragm pumps to optimize filter press operation

5min
pages 40-41

Using augmented reality tools to inspect wastewater plants

2min
page 39

Incidents of cyber attacks on the rise during the COVID-19 pandemic

3min
page 38

How to diagnose and repair automatic control valves

5min
pages 36-37

Ontario bill targets removal of licensure barriers for immigrant engineers

2min
page 29

The importance of the author-verifier relationship in project management

7min
pages 34-35

Embedding sustainability as part of your company’s DNA to drive growth

4min
pages 30-31

Capturing the value of converting records to digital formats – Cover Story

4min
pages 32-33

Funding innovation in engineering is critical to tackling climate change

3min
pages 24-25

Choosing right delivery model more important than ever for large projects

7min
pages 26-28

Small town chooses prefabricated wastewater lift stations

4min
pages 22-23

Examine the fate and transport of groundwater contaminants before settling legally

11min
pages 17-21

Canada makes new environmental pledges at climate conference

2min
pages 12-13

World’s largest wastewater energy transfer project underway for Toronto hospital

2min
page 14

Canada ready to unleash the power of biogas

5min
pages 8-9

70 Canadian groups sign plastics pact to pivot towards circular economy

2min
page 15

Study finds rubber tire chemicals impacting river through urban runoff

2min
pages 10-11

Microtunnelling used for twin culvert replacement project

2min
page 16

Appreciating the value of face-to-face networking opportunities

2min
pages 6-7
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.