/EP_1_Fitzgerald

Page 1

Hidroenergia 2006 – Crieff, Scotland Gerard Brendan Fitzgerald Dr. J. Prendergast & Mr. C. O’Donoghue (School of Engineering)


Project Title: “The Analysis of Fresh Water Rivers as an Alternative source of Energy in Remote Areas of Ireland”


Presentation Contents • Introduction • Overview of Small-Scale Hydropower (SHP) • Environmental aspects of SHP • Developing SHP in Ireland • Case Studies • Conclusions

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Introduction “On target to achieve 13.2% of power from RE sources by 2010” • Why do we need Small Scale Hydropower? – Ireland imported 87% of its energy requirements in 2002 – Need to diversify fuel mix to ensure security of supply – Electricity demand is constantly increasing (193MW/year) – Gross electricity consumption from hydropower only 2.35% in 2004 – Increased need for flexible plant according to the Transmission System Operator of Ireland Hidroenergia ‘06

Gerard Brendan Fitzgerald


Hidroenergia ‘06

Gerard Brendan Fitzgerald


SHP Resource Distribution • Installed capacity 29MW (schemes <10MW) • Ireland has potential for further 38MW (1997 ESBI report) • Over 50% of this is located in South West • Locating power supply close to consumers Hidroenergia ‘06

Gerard Brendan Fitzgerald


Overview of Hydropower • Focus on “Run-of-River” hydro generation • Requires little or no damming of river • Ensures flow regime is protected

Small

1MW – 10MW

Mini

100kW – 1MW

Micro

10kW – 100kW

• Small civil works • Highly efficient, predictable resource (90% Efficiency) • Long lasting, reliable technology (50 years on average) Hidroenergia ‘06

Gerard Brendan Fitzgerald


Potential Impacts of SHP • Impacts During Construction – Temporary diversion of Rivers – Use of Excavators for earth moving

• Impacts During Operation – Biological Impacts (local flora and fauna) – Landscape Impacts – Visual & Sonic Impacts – Recreational Impacts

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Environmental Integration of SHP • Scheme Aesthetics – Landscaping and vegetation – Interred Penstock – Underground Powerhouse

• Noise Reduction – Acoustic Insulation of Powerhouse & Turbine – Internal noise levels can be reduced to 70dBA

• Material Management – Trash racks remove waste material from waterways Hidroenergia ‘06

Gerard Brendan Fitzgerald


Environmental Integration of SHP • Biological Protection – Reserved/Compensation Flow • Central Fisheries Board river categorisation – Fish passes • Behavioural Guidance System (Downstream fish) • Fish ladders (Upstream migrants) – Fish friendly turbines • Reduce fish injury and mortality

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Developing SHP in Ireland

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Case Studies

Hidroenergia ‘06 Hidroenergia ‘06

Gerard Brendan Fitzgerald Gerard Brendan Fitzgerald


Case Study 1: Old Mill Site • Derrymore, Co. Kerry • Derelict Grain Mill • Existing Weir • On a Category 1 River • No fish movements • Natural Lake (Storage)

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Case Study 1: Old Mill Site (contd.) N

• Technical Data – Mean Flow = 0.2 m3/s – Gross Head ≈ 96 m

• Potential Install Capacity 121kW • Annual Energy Output 659MWh (RETScreen Software Package) • Potential to supply 143 homes • Low Environmental Impact Hidroenergia ‘06

Gerard Brendan Fitzgerald


Case Study 2: Multipurpose SHP • Blennerville, Co. Kerry • Water Supply Scheme Intake

• Existing Infrastructure: Intake and Weir • No known fish movements • Potential to include SHP on water network

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Case Study 2: Multipurpose Scheme (contd.) N

• Technical Data – Mean Flow ≈ 0.1 m3/s – Gross Head ≈ 60 m • Potential Install Capacity 24kW • Annual Energy Output 141MWh • Potential to Supply 30 homes with water & electricity • Low Environmental Impact

Hidroenergia ‘06

Gerard Brendan Fitzgerald


Financial Evaluation – Old Mill Site Total Estimated Cost of Development = € 999,508

Hidroenergia ‘06

Initial Design Costs

€ 51,700

Civil Works

€ 599,770

Penstock

€ 89,000

Turbine & Generator

€ 128,850

Connection costs

€ 40,000

Contingencies

€ 90,188

Gerard Brendan Fitzgerald


Financial Evaluation – Old Mill Site (contd.) Government supported tariff (ReFIT) Net Present Value (Discount Rate 7.5%) Internal Rate of Return Years to Positive Cash Flow

7.2 cents/kWh € 134, 189 8.6 % 25

• Old Mill redevelopment financially feasible • Large revenue following ‘break even’ period • Level of risk is high for a long term investment Hidroenergia ‘06

Gerard Brendan Fitzgerald


Financial Evaluation – Multipurpose Scheme Total Estimated Cost of Development = € 253,244

Hidroenergia ‘06

Initial Design Costs

€ 17,700

Civil Works

€ 81,285

Penstock

€ 58,500

Turbine & Generator

€ 44,908

Connection costs

€ 28,000

Contingencies

€ 22,851

Gerard Brendan Fitzgerald


Financial Evaluation – Multipurpose Scheme Government supported tariff (ReFIT) Net Present Value (Discount Rate 7.5%)

7.2 cents/kWh € 99, 815

Internal Rate of Return Years to Positive Cash Flow

9.3 % 24

• Multipurpose scheme development financially feasible • Good potential as a long term investment Hidroenergia ‘06

Gerard Brendan Fitzgerald


Conclusions • Both schemes are technically & financially feasible • Further incentives needed for development of grid connected SHP schemes in Ireland • Need to streamline planning to reduce delays • Transparency with regard to grid connection costs is required • For hydro to grow, public acceptance is one of the most important issues Hidroenergia ‘06

Gerard Brendan Fitzgerald


Thank you


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.