/SHAPES%20D23_final

Page 1

Guide on how to refurbish low head small hydro sites


Contents 1

About SHAPES PROJECT

3

2

Foreword

3

3

What’s peculiar? Definitions

3

4

When to refurbish

4

5

Basic technical-economic presuppositions

4

6

Fields of action

4

7

Site configurations

5

8

What’s peculiar? Technical and methodological issues

5

9

Preliminary studies

7

10 10.1 10.2 10.3

Actions on Q

7

Foreword By reducing waterways roughness (case study n. 9) By increasing the area of the cross section of the waterways [e.G. From earth-trapezoidal to concrete-rectangular] – (case study n. 9) By increasing the flow rate by negotiating a new water right with a higher rated discharge (case study n. 7)

7 8 8

11 11.1 11.2 11.3 11.4

Actions on H

8

Foreword By increasing the weir elevation (case study n. 6 And case study n. 7) By restoring the initial gross head By replacing old screens equipped by rectangular bars with screens with hydrodynamic profile

8 9 9 9

12 12.1 12.2 12.2.1 12.2.2 12.2.3 12.3 12.4 12.4.1 12.4.2 12.5 12.5.1

Actions on ␩ and T - Turbine and generator replacement

9

Foreword What’s worth replacing? Works below the tailrace water level (case study n. 3) Fluid-dynamics design of the draft tube Embedded parts How many units? Replacement of an old TG unit with a new one of the same type Francis open flume turbines (FOF) - case study n. 4 Kaplan turbines (case study n. 5 and case study n. 6) Replacement of an old TG unit with a new one of a different type (case study n. 3) Replace an old FOF turbine with a vertical bulb turbine (VBT) in the same pit

9 10 10 10 11 11 11 11 12 12 12

13 13.1 13.2 13.3 13.4 13.5 13.6

Actions on T

12

Foreword By improving sediment management By improving trash management By improving floating debris management (case study n. 2) By improving weir operation safety (case study n. 1) By setting or improving plant automation

12 12 13 13 14 14

14

Environmental added value

15

15

Flood management added value

15

16

Conclusions

15

17

Examples

16

10.4

8


1 2

Guide on how to refurbish low head small hydro sites SHAPES stands for SMALL HYDRO ACTION FOR THE PROMOTION OF EFFICIENT SOLUTIONS. SHAPES is a project partially funded by DG-TREN (European Commission) within FP6 and it has been running for two and a half years starting in December 2007. The overall objectives of SHAPES is to facilitate and strengthen the co-operation between EU Small Hydropower (SHP) Research and Market actors with the overall objective of streamlining future research & development and promote R&D results in order to enhance penetration of SHP and know-how within the EU and on new markets in developing countries.

About SHAPES PROJECT

Foreword

3

The off low h present guide id is i addressed dd d to people l interested i d in i the h refurbishment f bi h l head small hydroelectric plants and already having some basic knowledge of the main technical issues involved in the small hydro subject. That’s why in the guide, in order to keep it of a reasonable size and as effective as possible, the aforesaid basic knowledge is taken for granted. Furthermore, the guide will be focused on its three cross-specificities: refurbishment, low head and small hydroelectric plants. For general issues related to small hydropower and hydropower in general the reader can refer to the “Guide on How to Develop a Small Hydropower Plant” published by ESHA and available at www.esha.be. According to this approach, addressed only to the specificities of the subject, the guide doesn’t enter in any detail the usual activities connected with the implementation of a small hydroelectric plant (collection and interpretation of hydrological data, estimation of gross and net head, economic evaluations etc.), but it refers to those activities only when they’re relevant to the subject and it’s advisable to face them in a particular way. Finally, at the end of this document, several case studies are presented, which most of the following chapters will refer to.

What’s peculiar? Definitions

REFURBISHMENT

SMALL HYDROPOWER

Restoration of the integrity of the main parts of an existing plant, with restoration or improvement of the plant in terms of energy output, reliability of operation and environmental soundness

Hydropower plants with an installed capacity up to 10 MW

Strong constraints (spatial, functional, environmental, operational)

Strong constraints (spatial, functional, environmental, operational)

LOW HEAD PLANTS

Gross head = 1,5 ÷ 30 m

HYDRO Pico: P ≤ 1 kW Micro: 1 < P ≤ 100 kW Mini: 100 < P ≤ 1.000 kW Small: 1.000 < P ≤ 10.000 kW

Very Low Head: 1,5-3,0 m Low Head: 3,0-30 m

3


4 5

Guide on how to refurbish low head small hydro sites

When to refurbish

Refurbishment as a necessity When some components of the plant need to be changed, because they compromise the economics of the plant, there is no choice on which parts need refurbishment, but only on how to operate. The analysis of the future risk of failure can anyway be helpful in setting some priorities of actions.

Refurbishment as an opportunity Even if there is no particular necessity, refurbishing can be an opportunity to increase the overall efficiency and the energy production of the plant (also taking advantage of possible incentives). As you can choose what to refurbish, a priority scale on which parts of the plant are to be upgraded can be defined on a technical and economic basis.

Basic technical-economic presuppositions

4

Refurbishing a low head plant needs money, and usually a lot of money, as small hydro investments are capital intensive. Furthermore, low heads plants highly suffer from scale effects, mainly because, if compared to a high head plant with the same output, they have a greater incidence of civil works cost. In any case, when you have to refurbish the plant you must rank different project alternatives, included the zero alternative, that is no refurbishment at all. The best method for doing that is through the NPV (Net Present Value) method:

Where

I = lifetime period as year, quarter, month, etc Ii = investment in period i [Currency unit] Ri = revenues in period i [Currency unit] Oi = operating costs in period i [Currency unit] Mi = maintenance costs in period i [Currency unit] Vr = residual value of the investment over its lifetime,

6

Fields of action

where equipment lifetime exceeds the plant working life [Currency unit] Ev = environmental added value of the plant due to the refurbishment [Currency unit] r = periodic discount rate [%] n = number of lifetime periods

For the scope of this guide it’s important to make more explicit in the NPV formula the term related to revenues Ri

Where: Pi = price of the energy produced in period i [Currency unit/kWh] Ei = energy produced in period i [kWh/time unit] ␩i = overall efficiency of the plant in period i [%] = unit weight of water [kN/m3 ] Hi = net head in period i [m] Qi = flow rate in period i [m3/s] Ti = hours of operation in period i [h] The said formula, coupled with the NPV formula, leads to:

Each factor of this formula represents a field of action in the context of a refurbishment, exception made, in general, for the financial parameter r and the energy price Pi. The environmental issue needs a short comment. Environmental added value can’t be reduced to a purely monetary value. In this context there’s only the need of taking into account, in the following considerations, the fact that, during the refurbishment, different alternatives can have different environmental consequences, both in terms of purely monetary costs and even of environmental benefits.


7

Guide on how to refurbish low head small hydro sites

Site configurations

8

Diversion plants

Power house located

In addition to the action envisaged for at the toe of a weir. toe-of-weir plants, many actions can be In this case the actions are mainly addressed to hydraulic improvements addressed to units replacement and of the waterways to the improvement in trash and sediment management

What’s peculiar? Technical and methodological issues Once defined the main relevant elements, it’s necessary to point out the consequences of such definitions. To some extent, refurbishment needs a general approach, independently from the head of the plant. This approach can be a stepwise one:

5

Refurbishment

Necessity?

Opportunity?

Risk of failure analysis

Preliminary studies Current performances

Setting economical framework

Current main plant parameters (Q,H) Technical constraints

Setting priorities

Legal constraints Environmental constraints

Final technical choices Low head plants have many technical peculiarities. The actions during refurbishment must be taken accordingly:


Guide on how to refurbish low head small hydro sites

LOW HEAD PLANTS Roughness reduction %

LARGER ELECTROMECHANICAL EQUIPMENT

LARGE FLOW RATES

Reliability of operation (no higher efficiency at any cost...) Optimisation of civil works AND hydro units

6

Simpler, though less efficient, solutions worthwhile

Elimination of sliding problems

Diversion plants - Possibility of hydraulic improvements

Replace open channel with penstock

Reduction of civil works below water level Reduction of interference with existing structures

Flap gates vs. slide gates

Weir safety Suitable span to avoid clogging Reshaping intake

Sediment manamegent Floating bodies management

log and debris booms

Trash management

Install/Improve Trash Rack Cleaning Machines (TRCMs)

Plant automation

Elimination of slope constraints Easier spatial planning Elimination of physical constraints

Energy backup system (Diesel...) or better no energy for gates operation Operation

Reduction of leakages Flow area increase

LARGE HYDRAULIC WORKS Open channel hydraulics relevant

Turbines replacement

Replace trapezoidal with self-bearing rectangular section

Desilting devices installation/improvement Flow lines modification Attraction flow to desilting device improvement Hydraulic/rotating TRCMs Horizontal bars screens


9

Preliminary studies

Guide on how to refurbish low head small hydro sites Just like for any other hydroelectric initiative, even in case of refurbishment some basic data must be acquired or estimated in order to have the clearest possible picture of the status of the plant.

Water rights Before refurbishment

After refurbishment

Duration of concession [years] Legal restrictions

Parameters influencing economics Before refurbishment

After refurbishment

Annual production [MWh] Tariff structure [€/MWh] Annual income [€] Age of electromechanical equipment [years] Age of civil works [years] Age of gates, TRCM [years] Age of control system [years] Maintenance costs [€/year] Annual Outages [hours]

Environmental requirements Before refurbishment

After refurbishment

Before refurbishment

After refurbishment

Residual flow [l/s] Fish by-pass

Technical parameters Plant rated discharge Plant rated gross head Hydraulic losses: weir Hydraulic losses: intake Hydraulic losses: headrace channel Hydraulic losses: trash rack Hydraulic losses: forebay and turbine intake and outlet Hydraulic losses: tailrace channel

10

It’s vital to collect as many information as possible on the plant operation: • Unit(s) trips: how many? how long? why? • Plant outages: how many? how long? why? • Repair: what, when, why • Maintenance: actions taken, unexpected events encountered and solved

Actions on Q

10.1 Foreword

When the decision of refurbishing a small hydro low head plant is taken, an evaluation of the actual flow duration curve (FDC) of the river and of the existing plant should be done in any case. It’s not unusual that the initial FDC of the river has changed over the years and has to be updated. Furthermore, the effect of the obligation of releasing the reserved flow (if never released) or a higher reserved flow due to stringent environmental requirements (if already released) should be taken into account. At least the two aforesaid evaluations should be done, especially when the replacement of the unit is envisaged in order to design properly the turbine for getting the highest possible weighted efficiency. Also climate changes can affect the future FDCs: e.g. in Mediterranean countries more intense and short rainfalls are expected with longer dry periods, so that a turbine designed to exploit higher flow rates at a higher efficiency could be an option. But it’s not immediate that the plant can convey a higher flow without actions on weir, intake, waterways, etc. and also has the legal right for diverting more water from the river (or that this right can be easily acquired). That’s why, apart from legal aspects, it’s worth spending some words on the actions for increasing the flow rate conveyed by the plant.

7


Guide on how to refurbish low head small hydro sites

10.2 By reducing waterways roughness (case study n. 9)

The easiest and cheapest way to increase flow rate in a low head plant is reducing the roughness of the waterways, namely headrace and tailrace channels, the weir crest level being equal: smoother surfaces of walls and sills allow for smaller friction losses and, water level being equal, for a higher flow rate conveyed. The ways to get a smaller roughness depend on the structure of the waterways: in earthen channels (not very usual, especially for headrace channels, but more frequent for tailraces) the possible actions are few and mainly linked with keeping the slopes clean from weeds. In artificial channels the task is easier: on the market many different types of special products (one or two components waterproof mortars incorporating admixtures, fibres and comprising liquid polymer and special cements) are available for this purpose; it must be noted that those products must be applied very carefully taking into account the conditions of the surface where the product is applied, the weather conditions and so on, because they are very sensitive to all of these conditions, and in case of improper application the results can be a real disaster, even worsening the situation before application. Anyway don’t trust too much those kinds of actions in the evaluation of the final plant performances in terms of flow rate conveyed, because roughness is bound to increase in time due notably to the wearing of the coatings, and to weeds and algae growing.

10.3 Byto concrete-rectangular] increasing the area of the cross section of the waterways [e.g. from earth-trapezoidal – (case study n. 9)

8

Increasing the cross section area of the headrace and/or tailrace channel, if it’s viable both economically and from the spatial constraints point of view, is for sure a better solution than acting on roughness only. A typical solution is to change from earth-trapezoidal or masonry-trapezoidal to concrete-rectangular cross section. Many low head hydropower channels were built with a trapezoidal section. There’s a technical-economic reason for that: this kind of section, in duly proportions, has the minimum wetted perimeter and volume of excavation, so that it is the section with the best hydraulic performances and the minimum construction cost. Trapezoidal sections, both natural and masonry-coated have many problems: natural sections are subject to sliding of slopes, weeds growing, stability problems; masonry-coated are subject to cracks, water leakages, local coating heavy deterioration, all problems due to the interaction with the substrate and to the fact that the coating isn’t of the self-bearing type. A self-bearing rectangular section made by reinforced concrete can solve all the above mentioned problems and at the same time can remarkably increase the flow rate conveyed by the channel being the levels equal. The main disadvantage of this solution is the high cost of investment. The following important aspects have to be taken into account: • joints design and realisation; • drainage of side walls and bottom sill, to be evaluated case by case; • constraints coming from local boundary conditions; • access and realisation problems.

10.4 Bystudyincreasing the flow rate by negotiating a new water right with a higher rated discharge (case n. 7) For some cases, the rated discharge defined in the water right can be negotiated and increased. It happens when the water course hydrology and environmental impact studies demonstrate that the discharge reduction in the river bed is acceptable in front of the new positive impacts, resulting from the maintenance of the patrimony, the fish migration improvement and the green electricity production increase. Indeed, most of the old sites were dimensioned for the output necessary for the corresponding mills (saw mills, flour ones, ...) Of course, this implies administrative authorisations that are not guaranteed and not for free, but they are worth achieving in front of the added annual production.

11

Actions on H

11.1 Foreword

Actions on the head of an existing plant are not very frequent. The gross head is usually determined upstream by the weir level and downstream by the water level at the outlet channel. Actions on net head could be something more, because net head depends on the hydraulics of the waterways. Anyway a few actions can be actually envisaged for gross or net head. It must be noted that low head plants are usually operated keeping a constant level at a forebay just upstream of the turbine. That means that actions to reduce the roughness of the waterways upstream of the forebay have no influence on the head, but those actions increase the flow rate conveyed, water levels being equal.


Guide on how to refurbish low head small hydro sites

11.2 By increasing the weir elevation (case study n. 6 and case study n. 7) This action is mentioned even though it’s not very usual. Many different conditions must be met to increase the weir elevation and, consequently, the gross head of the plant:

• global stability of the raised weir must be guaranteed with suitable safety factors. If it’s not the case, the cost for getting the said safety factors must be duly compensated by higher energy production due to this higher gross head;

• higher water depth and greater length of the backwater area must be consistent to the environmental status of the river and to the water rights of the water upstream users (the increase of this gross head could decrease the one of a possible power plant located upstream);

• a higher water level determined by a higher weir implies a higher depth in the headrace channel, if any, which can lead to problems of side stability and freeboard, which thus have to be closely examined in a way similar to the weir raising.

11.3 By restoring the initial gross head In old small hydro low head plants, it’s not unusual that the gross head is decreased because of material sedimentation downstream of the powerhouse or in the tailrace channel. Restoration of the gross head can be achieved by dredging the tailrace channel or the river. The benefit of this action must be carefully evaluated because some cons are anyway connected to it: • dredging is an expensive activity; • the material dredged from the river must be disposed off: if it has an economic value (gravel, sand) as a component for concrete, the disposal is rather easy and it’s possible to have some revenue by reselling the material (if allowed by the national legislation); if it hasn’t, the disposal itself is expensive: in medium or large rivers tailrace dredging can imply handling thousands of cubic meters of material and finding a final destination for them is not an easy task; • river dredging can have a negative environmental impact on the riverine ecosystem; • sediment dynamics can be such that after a few years the problem must be faced again.

11.4 By replacing old screens equipped by rectangular bars with hydrodinamically profiled screens Old small hydro low head plants are equipped with screens made by steel rectangular bars. The screens are usually located at the forebay upstream of the turbine or at the intake or both. Screens are sometimes equipped with trash rack cleaning machines (TRCMs). In very small plants and in some very old and never modernised ones the screens are manually cleaned. When a plant is planned to be refurbished, an interesting option regarding screens can be the replacement of conventional steel rectangular bars with hydro-dynamically profiled screens. These screens can greatly reduce head losses and thus increase the net head of the plant. The steel solution is more expensive if compared with the rectangular one (approx. +60 % including installation), but now GRP (glass reinforced plastics), are a less expensive solution with a comparable reliability. Hydrodynamic profiles allow for a reduction of the head losses up to one third of the correspondent rectangular bars and can be cleaned in an easier way. Sometimes it is necessary to undertake this action to compensate smaller distance between bars due to demands of fishery

12

Actions on ␩ and T Turbine and generator replacement

12.1 Foreword

Actions on ␩, global efficiency, are related to actions on turbine-generator (TG) unit. As usually the main reason for refurbishment is the dramatic decrease of the TG efficiency and number and duration increase of unit trips due to the unit age, an important effect connected to the replacement is the operation time increase. It must be said that in many situations this side effect is even more important than the efficiency increase itself. The most common and frequent way to refurbish a plant is to replace the turbine. In principle it’s a simple task for any kind of small hydroelectric plant, but in case of low head plants the choice is not obvious at all. In case of high head plants the choice is rather simple because the available unit types are few: Pelton turbines and, in some situations, cross flow turbines.

9


Guide on how to refurbish low head small hydro sites In the great majority of existing high head plants, Pelton turbines are installed and if you have to replace the unit a new Pelton turbine is the most common choice. Maybe you change the number of nozzles (from one to two, from two to four, five or six) because the hydrological parameters of the plant are changed and you need multi-nozzles turbines to get higher efficiency at partial loads (it’s a rather common situation in case of an obligation of higher reserved flow release with respect to the past), but in general the unit replacement at a high head plant doesn’t present many choices or problems. In case of low head plants the situation is completely different. But thanks to technological progress and R&D effort in the turbines design, many more different options are available now with respect to the past to exploit the same head and flow rate. That’s why the final choice of the unit must be the result of an optimisation process which must take into account the boundary conditions and the local constraints into the decision process.

12.2 What’s worth replacing? Even the simplest possible choice in a unit replacement, that is to replace the old unit(s) with a new one(s) perfectly the same, is not so obvious. Yes, because, from one side, if you decide to replace even the parts in concrete you have higher costs, probably higher efficiencies, less constraints and some risks; by the other side, if you keep the embedded parts as they are (typically the draft tube and, if any, the spiral case), you have a strong constraint on the new unit construction. In fact you don’t exactly know which is the geometry of the coupling between embedded and not embedded parts (you can only partially trust in old construction drawings): you must wait for dismantling the old unit, check the real geometry, adjust very precisely from the mechanical point of view the coupling surfaces; all this process can take a lot of time and prolong the unit outage with the consequent loss of production. That’s why in many cases even the embedded parts are worth replacing, independently from any consideration about the efficiency improvement of the units. But the replacement of the embedded parts makes further problems arise, mainly the replacement of the draft tube of both Kaplan and Francis open flume units, such as:

1. problems due to the necessity of works below the tailrace water level, strongly constrained by the interaction with the existing structures; 2. problems due to the fluid-dynamics design of the draft tube. 10

Certainly the most critical is the first one.

12.2.1 Works below the tailrace water level (Case study n. 3) Only in a few cases of open flume Francis turbines replaced with the same type of unit you may not face this problem. Actually, as open flume Francis turbines were usually built and installed before the cavitation effects were completely known, many draft tubes of those units are installed well above the tailrace water level; but even though for reasons of global optimisation the choice of replacing a Francis open flume with a similar unit is taken, you must necessarily lower the level of the runner and consequently even the level of the draft tube with the consequent risk of works below the tailrace level. This kind of works has peculiar features:

1. they are expensive; 2. they are subject to

a high degree of uncertainty and consequently to a high risk of unexpected increase of the

refurbishment costs. In principle the actions to be taken when there’s the need for works below the tailwater level are well known, and many different technologies are available. The main need is to keep water away from the working area. Apparently it’s an easy task: it’s enough to install at a suitable low level some suitable pumps. Actually, the satisfaction of this simple need encounters many difficulties:

1. pumps may interfere with the progress of the works: typically, if you have to replace the old draft tube, once installed the new draft tube, you must embed it into the concrete. Pumps, located at the lowest possible level, and anyway lower than the lowest part of the draft tube, should be removed before concrete casting; but if you remove the pumps, the working area is inundated by water and you should cast concrete under water with further difficulties and uncertain final results. 2. when you pump water coming from the water table, you can have a high risk of washing out even the finest particles of the terrain around the powerhouse: this situation is very dangerous because of the risk that part of the powerhouse foundations may collapse.

12.2.2 Fluid-dynamics design of the draft tube It could seem strange that the fluid-dynamics design of the draft tube is a critical issue: with respect to the past excellent CFD (Computational Fluid Dynamics) systems are available for the flow simulation in draft tubes. The use of those tools


Guide on how to refurbish low head small hydro sites is widely diffused in the design of small hydro units, in order to cut laboratory full model costs, usually not affordable for small hydro plants operators. Nevertheless, wrong design of new draft tubes is frequent. It must be said that the draft tube design has been quite improved over the years: recently designed draft tubes have a shape very different from the past with undoubted higher efficiency. Nevertheless many partially unknown factors can still affect the final result of the draft tube replacement, especially at particular partial load of the units. A large bibliography is available on this topic.

12.2.3 Embedded parts

New units generally have different shapes and dimensions from old ones, so that when you replace an old unit you must evaluate also the possibility of removing embedded parts of the unit, typically stay vanes, discharge rings, stay rings, spiral cases. Any interaction with civil works is potentially a source of risk, especially in case of old buildings whose actual conditions are very often not completely known. Contingencies must be expected, affecting both time and costs of refurbishment. The simplest way to overcome this problems is a radical action on the civil works, that is actually realising a completely new civil structure avoiding to keep some parts of them in the easy illusion of reducing costs. Moreover, keeping old embedded parts represents a strong constraint to an optimal hydraulic design of the new unit and it usually results in lower efficiency.

12.3 How many units? In the past, very old plants were equipped with more than one unit in order to have the best possible exploitation of the available water resources and the best efficiencies of the units. Indeed, all Francis turbines, even open flume ones don’t work well at partial loads, so that to exploit at its best the available water more than one unit was installed. This is still a typical choice for large hydro plants, even though in that case also mechanical, transport and erection problems are at the basis of the multiple-units choice. It must also be noted that old plants used to have many units even for another important historical reason: many plants were built to supply mechanical force to drive mills, saw mills, textile workshops, so it was important to be able to operate the plants at partial load to meet the instantaneous energy demand of the workshops. Coming back to small hydro, nowadays, in case of refurbishment, one unit only (or less units than in the past) is preferred for economic (in general one big unit is cheaper than two units with halved output) and operation (automation, control and management of more units is more complex) reasons. In any case, as rather usual in refurbishment of low head plants, it’s difficult to state a general rule. Once again the general optimisation of the project must be kept in mind: the installation of one new unit instead of three old ones can be cheaper from the electro-mechanical side, but it can be unfeasible or very expensive or subject to higher contingencies due to strong actions needed on civil works.

12.4 Replacement of an old TG unit with a new one of the same type 12.4.1 Francis open flume turbines (FOF) - Case study n. 4 The reason for replacing an old unit with a new one is usually the quick efficiency decrease or the more and more frequent plant outages due to the unit unreliability . In many cases it deals not only with the runner itself but also with auxiliary components, such as lubrication and cooling systems, bearings, and over-temperatures. Very old low head units are Francis open flume turbines directly coupled to generators. After the invention of Kaplan turbines this kind of units has been rapidly abandoned as possible technical solutions to exploit low heads, so that also the hydraulic research and development on these units haven’t been carried out any more. Anyway, when old FOF must be replaced, the possibility of replacing it (or, more frequently, them, because, as all Francis turbines, even open flume turbines don’t work well at partial loads, so that to exploit at its best the available water more than one unit was installed) must be taken into due consideration. For sure this choice isn’t in the direction of innovation, but, as we said many times, the purpose of the refurbishment is the overall optimisation of the plant and not of one part only. The replacement of an old open flume Francis turbine with a new one particularly makes sense in situations with strong transport and erection constraints. As the modern alternative to FOF is a Kaplan turbine, the complete different size, configuration and weight of a Kaplan turbine with respect to a FOF must be evaluated with reference to site management. Pros and cons can be summarised as follow:

FOF Kaplan

Erection

Interaction with civil works

Efficiency

Number of units

11


Guide on how to refurbish low head small hydro sites

12.4.2 Kaplan turbines (Case study n. 5 and Case study n. 6) Replacing an old Kaplan turbine with a new one is apparently the easiest possible task. Actually, even though the plant parameters are the same (rated head and flow, FDC, etc.), it’s rather usual that the new unit can be different from the old one in many aspects, such as:

• rated speed (higher speeds are now frequent) • blades number (connected to speed, being Q and H the same) • runner diameter • draft tube shape (modern draft tube design is rather different from old ones) • runner centreline elevation (actual knowledge of cavitation phenomena often entails lower elevations) All those aspects require some adaptation of the new unit to the existing structures, both mechanical and civil. During the preliminary design stage, the consequences of any mechanical and hydraulic optimisation must be carefully examined by means of a deep cost/benefits/risks analysis. Sometimes what is simple or cheap in the workshop construction phase can have negative impacts on the works on site because of higher contingencies or of longer refurbishing times. Keeping inner and outer rings is a typical example. It’s obviously cheaper to keep these parts because their construction is expensive and takes time. By the other side you must machine on site the existing rings and you can encounter two possible risks: such a bad mechanical condition that the replacement is needed (more money and more plant outage) or prolonged site machining due to the remarkable lack of planarity.

12.5 Replacement of an old TG unit with a new one of a different type (case study n. 3) When the decision of replacing an old TG unit is taken, at a low head plant many options, different from the simple replacement with a similar one, are now available. Basically even the new available options are of the reaction type. The option of replacing an old turbine with an action or an Archimedean screw turbine can be considered only in limited cases. But in the great family of the reaction turbines there are many different solutions that have some peculiarities from the general configuration point of view. The final choice depends, as mentioned above, from the global optimisation of the refurbishment and not only of the unit replacement

12

12.5.1 Replace an old FOF turbine with a Vertical Bulb Turbine (VBT) in the same pit In order to reduce as much as possible the works on existing structures, a viable solution is the installation of a Vertical Bulb Turbine in the same pit where the old FOF was. In this case the dimensions of the bulb are the main problem. A conventional bulb usually has a large diameter and its fitting in the available space must be duly checked to be sure that the unit hydraulic behaviour is satisfactory. A new opportunity to use this solution is given by the installation of a Permanent Magnet Generator (PMG). If compared to a conventional one a PMG is more compact and has comparable efficiencies at any load. That’s why in recent years, sometimes coupled to Variable Speed Operation (VSO) generators, PMG have known a growing interest and application in the low heads field.

13

Actions on T

13.1 Foreword Actions on T are addressed to the improvement of the operation reliability of the plant by reducing outages. By far those are the actions to which a refurbishment is mostly aimed. One way or another, almost all the other actions have a beneficial side effect of increasing time of operation (e.g. the replacement of an old turbine allows for increasing the plant efficiency and decreasing the unit trips). In the following paragraphs an overview of some actions particularly related to T will be described.

13.2 By improving sediment management The operation of many low head plants is negatively affected by sediments transported by water and deposited in key parts


Guide on how to refurbish low head small hydro sites of the plants. The main consequences are:

• Reduction of the capability of conveying water to the plant (sedimentation at intake) • Reduction of cross section in the waterways (sedimentation in headrace and forebays) • Reduction of head (sedimentation downstream of the powerhouse) • Plant outages for sediment removal In many cases the reasons for excessive deposition lies in original sins of the plants, namely:

• Incorrect position of the intake in the river (typically in the inner side of a bend instead of on the outer one) • Insufficient dimensions of the flushing devices at intake or at forebays • Underestimation of the quantity of sediments transported or incorrect evaluation of their prevailing size • Insufficient or incorrect design of the desilting basins (if any) • General layout of the intake and waterways favouring deposition. Therefore, the actions taken during the plant refurbishment can positively affect the sediment management. The field of improvement is directly connected to the cause:

•Modification of the shape of the river at the intake reducing the inner curvature (very difficult, in general, both from technical and administrative point of view, with high environmental impact and probably only temporary results unless combined with other actions)

• Improvement of the flushing devices at intakes and forebays, e.g. lowering the sill level of desilting gates, enlarging their width or both

• Installation of bottom deflectors or of other devices capable of locally increasing flow velocity during flushing.

13.3 By improving trash management It is never enough underlined that a good trash management is vital for the operation of a low head plant. Some old and small low head plants have no trash rack cleaning machines (TRCM) and debris is removed manually from screens. This kind of operation has rather evidently high operation costs and is not efficient (hydro plants work day and night and debris are conveyed 24 hours a day). If a TRCM is not present at the plant, in case of refurbishment, one essential action is to set a new one. Even the replacement of an old or inefficient TRCM is an option. Once stated the necessity of setting a new TRCM (and of the relevant screen), the choice of the typology is also essential. There’s no general rule for that, but some criteria can be suggested:

• Debris load: for heavy loads (branches, logs) a hydraulic driven TRCM is usually preferred. If mainly light loads (leaves, small wood) are expected, even a chain or rope rotating TRCM can be a viable (and usually cheaper) solution

• Accessibility of the site to dispose of the debris removed from the water • Possibility of remove debris from screens avoiding the abstraction from water and the relevant disposal (with the cost connected). There are TRCM solutions with screens equipped by horizontal bars, which remove debris from the screen and move them on one side. By opening a gate (a flap gate or a sliding gate equipped with a flap gate on the top) the debris are flushed downstream without being removed from water. These solutions have also the intrinsic environmental benefit of keeping in the water the organic fraction of debris, which plays an important role for riverine ecosystems.

13.4 By improving floating debris management (case study n. 2) One of the most frequent causes of plant outage is the inefficiency of systems for managing floating bodies. Especially during high or medium water periods, (typically in spring or early summer after snowmelt time), rivers convey a large amount of floating bodies, which tend to enter the plant waterways and to clog screens at intakes and forebays. To avoid oversizing or overloading trash rack cleaning machines, a simple, rather cheap and efficient solution is to install floating log and debris booms. These are simple plastic buoyant bodies of given length (approx. 3-4 m each), properly shaped and duly connected, usually by galvanized steel connectors, and anchored to the banks with a concrete foundation designed to withstand the thrust of the floating material stopped by the booms themselves. They should be located at the intake while considering the necessity of flushing downstream the floating material. This is a key issue of the whole system. In case of fixed weirs the booms position and shape when floating debris are right against them, must be carefully designed, in order to be sure that flow over the crest of the weir, in case of incoming discharges higher than the plant rated discharge, is enough to flush downstream the floating bodies . In case of moveable weirs, you have different options:

• to set a flap gate as near as possible to the booms. By opening, even partially, the gate you flush downstream the debris.

13


Guide on how to refurbish low head small hydro sites In order to favour debris removal from booms, sometimes the flow rate diverted by the plant is reduced (and the approach velocity to the booms, too) and at the same time the gate is lowered;

• to check whether existing gates of other types at the weir are able to flush floating debris. If sliding gates are installed, you can anyway flush floating debris, but the gates must be completely raised and operating in spillway mode: in orifice mode, in fact, floating debris can’t be efficiently flushed. An alternative to that is given by a modification of existing sliding gates by the installation on top of them of a small flap gate. A correct curvature of the booms under the thrusts of the floating bodies is essential for the efficient operation of the system.

13.5 By improving weir operation safety (case study n. 1) When a weir of an old low head small plant is equipped with moveable gates, very often these gates have small width with many intermediate piers. This kind of weir layout makes it vulnerable to clogging during floods because the large material transported (trunks, branches, etc.) can obstruct the waterways. The reason for many small gates was essentially an economic one: gates with wide span required special construction, sometimes not compatible with the economics of a small plant. On the other hand, many small gates can cause more frequent outages and an operation costs increase due to the necessity of removing material just against the gates, a complicated activity. That’s why, in the refurbishment framework, it makes sense to take into consideration, if the preliminary assessment of the criticalities showed it as a weak point, the modification of the weir layout by replacing many old sliding gates with few flap gates or sector gates or inflatable rubber dams, possibly protected by steel panels. Each one of the aforesaid options has pros and cons and their own more specific application, even though all of them are in some way equivalent. The following table summarizes the main features:

14

Suitability for water level regulation

Risk of damage during floods

Flap gates

Sector gates

Rubber dams Rubber dams with steel panels

Cost

Construction

Erection

Civil works

It must be kept in mind that, in any case, a fundamental role is played by temporary works in the river for replacing the gates. These works must be properly designed to withstand the project flood and to protect working areas from water. In some situations, on the contrary, you must design temporary dykes in order to be overtopped by a predefined flood to avoid damages at the structures located upstream (villages, various activities, etc.) but to protect from ordinary flow rates the working site. It’s quite essential to plan carefully all the activities in the river, rather obviously choosing the river low flow period, with the lowest risk of flood. Another important issue in the choice among different alternatives is related to the interaction with civil works and primarily with foundations. Some types of gates (flap and sector ones, mainly) transfer hydraulic loads in concentrated points to foundations so that special foundations (piles, sheet piles) can be necessary to withstand those loads. Special foundations are expensive, require time and skill to be built, especially in the difficult conditions typical of works in rivers, and are subject to frequent contingencies, so that a deep analysis of the opportunity of the alternative requiring those works must be carried out.

13.6 By setting or improving plant automation In the frame of a refurbishment, it’s quite usual to implement the automation of the plant or to modernise and update the existing one. About this topic there’s nothing really specific to low head plants. In any case, even considering the rapidly decreasing costs of hardware and software, it’s advisable to acquire as many data from the field as possible in order to have a clear picture of the situation of the plant and of the evolution of the main plant parameters in time. Particular attention should be paid to:

• Units vibration (installing seismic transducers or accelerometers at each bearing) • Generator and transformer temperatures • Bearings temperature • Upstream and downstream water levels • HPU (hydraulic power unit) pressures and temperatures.


14

Environmental added value

Guide on how to refurbish low head small hydro sites The refurbishment of a low head plant can be a good opportunity (sometimes an obligation) to increase the environmental added value of the plant by suitable actions aimed at improving the plant environmental sustainability. It must be said that the environmental performance improvement of an existing low head plant is a difficult task because of the many constraints coming from acting on existing hydraulic works, so that, as for any other action during refurbishment, an optimised solution rather than an optimum solution can be achieved in the most favourable situations. Possible actions related to this topic are:

• fish passages: many old low head small hydro plants aren’t equipped with fish passages or are equipped with inefficient ones. Within a refurbishment the realisation of a fish passage can be a good opportunity to improve the plant environmental performance. Unfortunately it’s not an easy task. The main risk is the construction of an expensive passage with low efficiency because of the general layout of the weir and of the intake. Typically it’s impossible to put the passage in a suitable position to properly attract fish to the passage itself in both migration directions. • architectural and visual impacts: refurbishment can also include actions on buildings, mainly the powerhouse, connected with the hydroelectric units replacement, but also on the weir or on the intake. Some design choices can be taken keeping in mind the reduction of the visual impact of the plant, e.g. installing new gates at the weir with lower visual impact (flap gates, or rubber dams with steel protection panels which don’t require intermediate piers or footbridges). • Fish friendly turbines: for many years research on fish-friendly turbines has been ongoing all over the world, mainly addressed to large hydro low head turbines. Small hydro application, exception made for very low head (with low speed, rather large diameters and gaps) are undoubtedly more difficult, especially in case of refurbishment, where the constraints coming from existing structures don’t generally allow for installation of units typology with better environmental behaviour than conventional ones (e.g. Archimedean screws). • Installation of screens with reduced space between bars: the reduction of space between bars implies a lower risk of fish entering the plant and the turbines, but also higher head losses, so that in order to keep them at a reasonable level this action can be connected preferably to the installation of hydrodynamically-profiled bars. • Fish dissuasion or attraction systems: this action, in general rather expensive both from the investment and operation point of view, can be envisaged whenever, because of the plant layout, it’s difficult to keep fish away from the intake or to attract it to the passage.

15

Flood management added value

16

Conclusions

The rehabilitation of old sites often results in an improvement of the flood management. It can be noticed especially for destroyed weirs. Indeed for these sites, problems with the river banks can occur, that keep on increasing if nothing is done. Then the rehabilitation of the site implies new equipment and an opportunity to study the area as a whole, considering the electricity production and the flood management. Then, new valves can be integrated, that can be regulated with the water level variations. Then by-passes and basins can be created to better manage the high discharges. Moreover it can be here added that turbines are most of the time regulated to maintain a steady upstream level.

This report on low-head small hydropower plant refurbishment shows how complex it can be to reach an optimum, as each plant part is linked to the whole site operation and interacts with the efficiency of each other part. This infers that a close investigation of the plant and relevant site constraints is highly recommended to increase the refurbishment production gain and the plant reliability, and to decrease the further refurbishment numbers.

15


17

Guide on how to refurbish low head small hydro sites

Examples

Case study n. 1:

Improvement of weir operation safety and flood management

17

Case study n. 2:

Improvement of floating debris management

17

Case study n. 3:

Replacement of old open flume Francis turbines by turbines by vertical bulb turbines in the same pit 18 Case study n. 4:

Units replacement. Restoring initial performances featuring strongly constrained solution.

19

Case study n. 5:

Replacement of an old Francis turbine with 2 Kaplan type ones

19

Case study n. 6:

Site reconstruction and setting of a new Kaplan turbine

20

Case study n. 7:

Weir and intake rehabilitation, fish pass integration, new power plant

20

Case study n. 8:

replacement of an existing unit with a similar one

21

Case study n. 9:

increase of the cross section area (from earth-trapezoidal to concreterectangular

21

Case study n. 10:

plant automation

22

Case study n. 11:

improvement of sediment management

22

Case study n. 12:

improvement of environmental added value

23

16

Case study n. 1: Improvement of weir operation safety and flood management Country: Italy Hg = 8,9 m

BEFORE: 12 electrically operated slide gates FIELD OF ACTION: improvement of weir operation safety MAIN PROBLEM: risk of clogging during floods and normal operation ACTION: replacement with three flap gates FEATURES: hydraulically operated, back-up emergency diesel generator BENEFITS: reduced risk of flooding plains downstream, reduced operation costs, increased operation time

Qmax = 22 m3/s E = 10,4 GWh/year

BEFORE

AFTER

Case study n. 2: Improvement of floating debris management

info: Studio Frosio

Country: Italy Hg = 10,5 m

BEFORE: heavy debris load at turbine intake FIELD OF ACTION: improvement of floating debris management MAIN PROBLEM: high costs for debris disposal and management ACTION: installation of floating log and debris booms FEATURES: easy installation, low cost BENEFITS: reduction of operation costs WARNINGS: need for a system for flushing floating bodies (flap gate at the weir)

info: Studio Frosio

BEFORE

Qmax = 60 m3/s E = 25 GWh/year

AFTER


Guide on how to refurbish low head small hydro sites

Case study n. 3: Replacement of old open flume Francis turbines by turbines by vertical bulb turbines in the

same pit

info: Studio Frosio

Country: Italy Hg = 10,5m

Qmax = 4 x 15 m3/s E = 25 GWh/year

BEFORE: 4 open flume Francis turbines, â?Š ~70 % FIELD OF ACTION: improvement of units efficiency and reliability MAIN PROBLEM: small space available for units in the turbine pits ACTIONS: 1. replacement with Permanent Magnet Generators double regulated Bulb Turbines 2. new draft tubes FEATURES: compact units with high efficiency BENEFITS: increased avg. efficiency â?Š ~87 % SIDE EFFECTS: space rationalisation in the powerhouse RISKS: nearly prototype units, works below tailwater levell

Case study n. 4: Units replacement. Restoring initial performances featuringg strongly g y constrained solution. info: Studio Frosio Country: Italy Hg = 15,0 m

BEFORE: 2 open flume Francis turbines FIELD OF ACTION: restoration of units efficiency and reliability MAIN PROBLEM: erection almost impossible for Kaplan turbines

BEFORE

AFTER

Qmax = 12 m /s E = 9,20 GWh/year 3

ACTIONS: replacement with new open flum ume Francis turbines BENEFITS: increased reliability RISKS: open flume hydraulics no more deeply investigated byy manufacturers

BEFORE

AFTER

Case study n. 5: Replacement of an old Francis turbine with 2 Kaplan type ones Country: Switzerland Hg = 2,1 m

BEFORE: abandoned site, no production FIELD OF ACTION: integration of new turbines in an existing infrastructure (factory), MAIN PROBLEM: obsolete machines, reparation possible but not cost efficient ACTION & FEATURES: integration of 2 siphon turbines, setting of valves to manage river discharges, nominal discharge, reserved flow, and floods. BENEFITS: better discharge and flood management, production increase (turbine flexibility and efficiency, operation time)

AFTER

info: MHyLab

Qmax = 5 m3/s E = 0,350 GWh/year

17


Guide on how to refurbish low head small hydro sites

Case study n. 6: Site reconstruction and setting of a new Kaplan p turbine Country: France Hg = 27 m

BEFORE: in 2002 a flood destroyed the whole site, apart from the power plant with its Francis turbine MAIN PROBLEM: no production ACTION & FEATURES: new weir, head increase, setting of a Kaplan turbine

BEFORE

info: MHyLab

Qmax = 1,5 m3/s E = 1,8 GWh/year

BENEFITS: production increase (head, turbine turbi efficiency and flexibility, time operation), decrease of the operation & maintenance cost NOTE: the old Francis turbine is used during the Kaplan turbine rbine maintenance.

AFTER

BEFORE

AFTER

Case study n. 7: Weir and intake rehabilitation, fish pass integration, new power plant Country: Switzerland Hg = 5,2 m

18

BEFORE: weir and intake destroyed by a flood in 2001, abandoned site FIELD OF ACTION: weir, intake, inlet and outlet channels, turbine, power plant MAIN PROBLEM: risks of banks subsidence, limited amount of water in the inlet channel, no production ACTIONS: weir reconstruction, upstream level raising, integration of a fish pass, equipment of the intake, new channel crossing section, totally new powerhouse FEATURES: rocks filling, boom equipped with a fish net, 2 new Kaplan turbines BENEFITS: better flood management, upstream and downstream fish migration, head and discharge increase for

info: MHyLab

Qmax = 6,0 m3/s E = 0,820 GWh/year

the SHP, production increase, maintenance cost decrease. NOTE: this site is being studied, and has not been rehabilitated yet. y

BEFORE

BEFORE

Case study n. 8: raplacement of an existing unit with a similar one

info: IWHW

Country: Austria Hg = 1,56 m Qmax = 5,5 m3/s

BEFORE: vertical axis Francis Turbine from1924 FIELD OF ACTION: efficiency and operation reliability ACTIONS: Replacement of the existing turbine New spur gear unit replacing two old gear boxes Installation of a new asynchronous generator New Hydraulic Power Unit driving the turbine governor New electronic turbine governor TRCM connected to the centralised control unit New vertical flushing gate hydraulically driven

Before renovation: After renovation: Pmax = 50 kW Pmax = 65 kW E= 0,3 4 GWh/year E = 0,4 GWh/year

BEFORE

AFTER

Case study n. 9: increase of the cross section area (from earth-trapezoidal to concrete-rectangular Country: Italy Hg = 8,0 m

info: Studio Frosio

Qmax = 16 m3/s E = 12,2 GWh/year

BEFORE: earth trapezoidal headrace channel FIELD OF ACTION: increase of rated flow and reduction of sliding problems of the channel sides ACTIONS: turning to concrete rectangular self-bearing walls BENEFITS: increased rated flow and safety of operation. Solution of stability, leakages and sliding problems. CONS: high cost of investment

BEFORE

AFTER


Guide on how to refurbish low head small hydro sites

Case study n. 10: plant automation

info: Studio Frosio

Country: Italy Hg = 6,35 m

BEFORE: not automated, fully manual operated plant FIELD OF ACTION: increase of the reliability of plant operation ACTIONS: full automation of the plant BENEFITS: increased safety of operation. Optimisation of plant parameters and maximisation of energy production

BEFORE

Qmax = 32 m3/s E = 10,5 GWh/year

AFTER

AFTER

Case study n. 11: Weir and intake rehabilitation, fish pass integration, new power plant Country: Italy Hg = 12,87 m

info: Studio Frosio

Qmax = 75 m3/s E = 30,1 GWh/year

BEFORE: heavy sedimentation problems causing frequent outages FIELD OF ACTION: improvement of sediment management ACTIONS: bank re-shaping, wider desilting span, lower desilting gate bottom sill, rip-rap protection of bottom, longitudinal wall to concentrate flow lines at the desilting gates BENEFITS: reduction of outages for sediment management, increase of rated flow of the headrace channel CONS: works expensive and long outage to realise them NOTE: works under authorisation procedure

Desilting gate too small

Intake in the inner side of the river

Case study n. 12: improvement of environmental added value ue

info: LŽŪU

Country: Lithuania Hg = 35,26 m Qmax = 11,1 m3/s (3x3,7 m3/s)

BEFORE: significant reservoir water level fluctuations and unstable tailwater flow regime FIELD OF ACTION: replacement of a worn turbine, improvement of ecological status in reservoir and downstream power plant MAIN PROBLEM: necessity of turbine refurbishment, clearly artificial river flow regime ACTION: replacement with turbine having more flexible operating flow regime FEATURES: flexibility of operation BENEFITS: power generation remains as before, river

E = 7,025 GWh/year P = 3,2 MW

flow ecological status depending on more natural fl ow regime has been improved.

Case study n. 13: Replacement of an old Francis turbine with th a Kaplan type one Country: Lithuania Hg = 35,26 m Qmax = 11,1 m3/s (3x3,7 m3/s)

BEFORE: limited production, high operation costs FIELD OF ACTION: integration of a new turbine in an existing infrastructure MAIN PROBLEM: obsolete Francis turbine ACTION & FEATURES: replacement of a Francis turbine with a S-shape axial one, setting of a penstock, creation of a powerhouse BENEFITS: increase of the head, turbine flexibility and efficiency, and therefore production increase and operation costs decrease

BEFORE

info: LŽŪU

E = 7,025 GWh/year P = 3,2 MW

19


ESHA

Renewable Energy House Rue d’Arlon 63-67 B-1040 Brussels, Belgium +32 25461945/33 www.esha.be

Studio Frosio

MHyLab Chemin du Bois Jolens 6 1354 Montcherand Switzerland Tél : + 41 24 442 86 24 Fax : + 41 24 441 36 54 info@mhylab.com http://www.mhylab.ch

Studio Frosio Via P.F. Calvi, 9 25123 Brescia - Italy Tél : + 39 030 3702371 Fax : + 39 030 396143 info@studiofrosio.it http://www.studiofrosio.it

IMP PAN The Szewalski Institute of Fluid-Flow Machinery of the Polish Academy of Sciences ul. Fiszera 15, 80-952 Gdansk - Poland Tel: +48 58 6995139 Fax: +48 58 3416144 imp@imp.gda.pl http://www.imp.gda.pl

Water & Land Management Faculty_Lithuanian University of Agriculture Universiteto 10, Akademija, LT-53361 Kauno r., Lithuania Tel: +370 37 752 337 Fax: +370 37 752392 E-mail: petras.punys@lzuu.lt http://www.lzuu.lt

Institute of Water Management, Hydrology and Hydraulic Engineering – University of Vienna Muthgasse 18, AT-1190 Vienna, Austria Tel: +43-1-47654-5500 Fax+43-1-47654-5549 E-mail: iwhw@boku.ac.at http://iwhw.boku.ac.at/

The sole responsibility for the content of this publication lies with the authors. It does not necessarily reflect the opinion of the European Communities.. The European Commission is ot responsible for any use that may be made of the information contained therein


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.