Shawsheen River Project Timeline

Page 1

Perform GISbased desktop site screening of parcels along the Shawsheen

• • •

FY22 MVP Project Kickoff Establish Steering Committee Oct – Nov 2021 Sept 2021

• •

Dec 2021 – Jan 2022

Nov – Dec 2021

Develop climate adaptation goals Review existing protected land and open space planning documents

Develop prioritization criteria with steering committee Prioritize parcels for acquisition and restoration

• •

FY23 MVP Project Kickoff Begin bi-weekly project team meetings

Apr – Jun 2022

Resilience planning workshop at Andover Climate Summit Finalize plan Climate Ready Shawsheen

Visioning Workshop and Design Charrette Finalize design concept Nature-Based Flood Resilience

Apr - Jun 2023

• •

Lawrence Desktop Site Screening HEC-RAS Model Development

Site survey and base mapping of the Lower Shawsheen Soccer Field Updated H&H modeling and preliminary design

Oct 2023

Sept 2022 – Mar 2023 Sept 2022

Feb – Mar 2022 Conduct field assessments on selected parcels, with help from community volunteers

Nov 2023 – May 2024

• •

FY24 MVP Project Kickoff Begin monthly project team meetings