Step Change Process Improvements For Projects & Turnarounds Through Mobile Task Management Software
Donald J. Frieden, President & CEO, SAT Corporation
What We Will Discuss…. • What are the challenges and compelling automation opportunities in today's Capital Project environment? • How can Mobile Technology improve project execution through project status updates and asset tracking? • How can Mobile and Auto-ID Technology reduce the duration of Plant Maintenance Outages? © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Capital Projects Landscape
• NIST estimates that $ 15.8 billion in profits are lost in U.S. capital facilities every year – 6.8 Billion lost in EPC phase – 9.7 Billion lost in MRO phase
• Important because the platform for effective asset lifecycle management during the MRO phase is created during EPC
3 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Capital Project Landscape • The Construction and Capital Project industry lags behind manufacturing and transportation for asset management and field-force automation. • Information delivery and data processing in the field has been traditionally paper-based. • Tools for automated information authoring, transfer, and collection is rapidly increasing, but adoption of mobile technology and asset identification to enable the front-line workforce is severely lacking. • In the next decade, successful project execution will be measured by a companies ability to effectively manage it’s stranded assets (people, equipment, and work processes). 4 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Capital Project Opportunity • Enterprise Systems for Capital Project Management are being deployed by owner/operators and other project stakeholders (EPC), but are seldom integrated. ¾ ¾ ¾ ¾ ¾
ERP (Oracle, JDE, SAP, etc.) PPM (Primavera, MS Project, etc.) CAD/CAM/Document and Engineering Management (Intergraph, CATIA, etc.) Enterprise Knowledge Management Systems-new breed of aggregators designed to provide a backbone for all plant information (SmartPlant, etc.) Specific “Point” Applications (Completion, Safety, QA/QC, etc.)
• Very little field level application of technology to process this information exists today, which limits the effectiveness and productivity of all facets of construction execution. 5 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Example of a Disconnect Crew waiting because dependent tasks not updated in project schedule
Task updates or material staging not timely, dependent tasks left in “wait” mode 6 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Domino Theory
4. First year Operability Effected
3. Project overruns and demobilization delays
2. Critical path of project slips
1. Cumulative task cycle time delays
7 Š 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Capital Project Improvement Opportunities Current grassroots/capital projects have the opportunity to take advantage of the availability of this important Information to reduce implementation costs and adoption of mobile technology during EPC Cycle
Project Definition
Project Planning
Project Design
Fabrication/ Construction
Testing/ Acceptance
Operations
Decommission /Retrofit
Results: • • • •
Lower Implementation Cost Capture of early operation asset data (First Year Operability) Quicker deployment Better overall ROI
• • • • •
Equipment data sheets Process flow diagrams Vendor/Supplier SOP’s Testing Results Etc.
8 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Reducing EPC Costs and Improving FYO What if you could have?
Engineering, Procurement and Construction
Shorter more efficient schedules from a reduction of redundant and duplicated tasks to facilitate faster “lookahead” views
These results
Fewer Schedule Delays and Reduction in Cost Overruns
First Oil/Gas
Asset Lifecycle Management
Reduced maintenance costs earlier in asset’s life from early identification of precursors and consistent delivery of best practices that prevent unplanned downtime
Fewer Asset Failures and Reduction in Lifting Costs
9 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
What We Will Discuss…. • What are the challenges and compelling automation opportunities in today's Capital Project environment? • How can Mobile Technology improve project execution through project status updates and asset tracking? • How can Mobile and Auto-ID Technology reduce the duration of Plant Maintenance Outages? © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
The Turnaround Challenge OS M C R
Sar ban
HA
Ut i li
za tio
n
Co st
Turnaround Success
es-O xley Sa
ecard
Š 2007 SAT Corporation. All rights reserved.
st e B
Flawless Execution
RBI
fe ty
Balanc ed-Sco r
ty i l a Qu
s
ce i t ac r P
S
a m ig S ix
Ti m
e
a Le
n
SAT Corporation Proprietary & Confidential
The Turnaround Environment • For the past 10 years Owner/Operators and service providers have focused on improving performance by deploying improved project management, estimating (time/cost), risk evaluation, and safety methodologies……… • Both labor rates and materials of construction costs are marketplace driven. • Scope control and work efficiencies are the remaining areas to focus to control duration and costs.
© 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Turnaround Opportunities Capturing real, verified task execution data including quantitative per cent complete, earned value, asset “as found", test results, field notes, EH&S and other information can: • Enable a safer work environment by insuring task status on hazardous environment tasks (entry, etc.) • Eliminate redundant and duplicated tasks • Quantitatively verify task completion so dependent tasks can start earlier • Capture important asset data during construction, testing, commissioning
© 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
The Process
• Project Steps by Craft • General IntelaTrac Procedures • JSA, Etc.
Job Steps Created in Primavera
© 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Mobile User Interface User logs onto the Mobile IntelaTrac Application Login Base Area Test
V
TAR ID Test
V
Login ID Admin
V
Role Everyone
V
Password Test
• Base Area – Work Area Sort • Task ID – From Primavera • Logon ID / Password – From IntelaTrac
Logon
• Role – From IntelaTrac X Change password after logon Tools T ?
© 2007 SAT Corporation. All rights reserved.
K
SAT Corporation Proprietary & Confidential
Primavera Data Categories Added to IntelaTrac • • • • • • •
Status Started Status Finished Duration % Completed Actual Hours Craft Activity ID Activity Description
© 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Mobile User Interface 1. User selects the equipment type from the dropdown
Š 2007 SAT Corporation. All rights reserved.
2. User selects a specific Activity ID for Status Update
SAT Corporation Proprietary & Confidential
Mobile User Interface User Updates Activity Status • • • •
Percentage Complete Status Start Status Finish Notes – Available free text or drop down list data entry for this activity • Create Work Notification from this screen as required © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
The Process
Special Procedures as needed for: • Blinding • Inspection • LOTO
© 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Integrated Procedures • Procedure assignment to Activity using the Primavera P3E interface with embedded browser to Procedure Instances that have been created in IntelaTrac for: – Vessel Entry – Vessel Closure – Mechanical Inspection, Scaffold Inspection, QA/QC – Equipment shut down or start up – Safety Observation, Job Safety Analysis (JSA) – Pre Start Up Safety Review (PSSR) – Scope Change or Request for Additional Work – Crane or Equipment Inspection – Permits – PSV identification and status – Etc. © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
The Process
Completed Job Steps Update in Primavera
• Job Step Updates
• New Job Steps
© 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Mechanical Completion/Commissioning Completion Check Safety/Relief Valves Tag No.
T101
Area
SRV 35768
System
PO No. MC No.
001234
Desc
T101 S-504 Lower
Sub-system 23 Comm. Pack
5012
Verify valve ID (SCAN) Check valve against data sheet Valve tested Test Certificate Attached Seals fitted to operating arm and adjustment cap Flanges protected and sealed Check gaskets, flanges and final installation
Details Signed By: GM (FAB), IM (HOOKUP) Outstanding Signatures: IC, GE (SUPR) Description xxx
Add to Punchlist
Transfer
SignOff
22 Š 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Electronic Mechanical Completion/Commissioning Completion Check Safety/Relief Valves Tag No.
T101
Area
SRV 35768
System
PO No. MC No.
001234
Desc
T101 S-504 Lower
Sub-system 23 Comm. Pack
5012
Verify valve ID (SCAN)
Security Group
Check valve against data sheet
NE OK
Valve tested
Cancel
Test Certificate Attached Seals fitted to operating arm and adjustment cap Flanges protected and sealed Check gaskets, flanges and final installation
Details Signed By: GM (FAB), IM (HOOKUP) Outstanding Signatures: IC, GE (SUPR) Description xxx
Add to Punchlist
Transfer
SignOff
23 Š 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
What are some of the benefits? • Planners/Supervisors – Time saved in reduced task status updates – Potential of 15% reduction in time required for management of tasks per full time equivalent (FTE) per shift
• Ad-hoc work items – More efficient management of added scope tasks – Potential of reduction of management effort for these tasks of 35-40%
• Dependent task reaction/staging requirements – More efficient execution of dependent tasks, i.e. insulation, cleaning, etc. © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
What We Will Discuss…. • What are the challenges and compelling automation opportunities in today's Capital Project environment? • How can Mobile Technology improve project execution through project status updates and asset tracking? • How can Mobile and Auto-ID Technology reduce the duration of Plant Maintenance Outages? © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
Enabling Task Management During Projects Function
Post Project
During Projects
• Operations
routine duty rounds
start-up/commissioning
• Maintenance
PM rounds
NDE/inspections
• I&E
inspections
loop tests/calibration
• HSE
compliance rounds
incident investigation
• Training
field workers
training verification
• Offsites
tank gauging & lineups
hydro/vacuum tests
• QA
lab sample rounds
NDE/source inspection
26 © 2007 SAT Corporation. All rights reserved.
SAT Corporation Proprietary & Confidential
RFID for Supply Chain of Serialized Equipment
OEM Installs RFIDName Tag at Field Manufacturing EPC-IS
Plant Owner Receives Count Tagged Asset 20
OEM Data
Owner Issues Tagged Asset Value To Contractor
255.255.100.11-855004
Count 14
Dresser Rand
model_number
19
DR02-01-3313-CL-414
serial_number
10
PR87073489
manf_date
2
20-Jan-03
Count
Value
equipment
18
DR234-876-290-5209
functional_location
10
36-EM-10A
PID_number
16
INT99605-231-702
operation_number
12
MP0003-96296
description
40
Overhead Fan Motor
Š 2007 SAT Corporation. All rights reserved.
Future Maintenance Routines triggered By RFID tag
Value
manufacture
Plant Owner Data
Contractor Installs Asset and Loop Test
SAT Corporation Proprietary & Confidential
Thank You
Questions and Answers?