IMIESA July 2022

Page 20

POWER STATIONS | HYDROPOWER

Hydropower on the Ash River A downstream bird’seye view of the Middle Kruisvallei facility

Middle Kruisvallei abstraction works

The Lower Kruisvallei powerhouse

Completed in March 2021, the construction of the Kruisvallei Hydropower Scheme showcases exceptional innovation as well as multidisciplinar y engineering and construction management teamwork in delivering a worldclass clean energy solution.

L

ocated on the Ash River approximately 13 km north-west of Clarens and 17 km south of Bethlehem in the Free State, the scheme consists of two small run-ofriver hydropower plants – Middle and Lower – generating a combined output up to 4 MW, which cost approximately R260 million to construct within a tight 18-month programme. The project formed part of Round 4 of South Africa’s Renewable Energy Independent Power Producer Programme (REIPPP), with the power purchase agreement (PPA) awarded to Zevobuzz (RF) as the IPP. Zevobuzz (RF) is majority owned by Red Rocket, with H1 Holdings as a shareholder. Red Rocket is a pan-African IPP with previous experience in wind and solar projects. This is Red Rocket’s first hydropower investment.

Team dynamics Zevobuzz employed Red Rocket as the EPC

18

IMIESA July 2022

PROJECT TEAM Client/Independent Power Producer: Zevobuzz (RF) Civils, Structural & Hydraulic Design Engineers: Zutari EPC Contractor: Red Rocket Civil & Mechanical Contractor: Eigenbau Hydroelectrical Contractor: Scotta SpA Interconnection Contractor: Tractionel Enterprise

(engineering, procurement and construction) contractor, with Eigenbau appointed as the main design and build contractor, and Scotta appointed as the turbine supply contractor (water to wire). Zutari was, in turn, appointed by Eigenbau as the design engineer. Designs were developed in close cooperation with the contractors, with a strong emphasis on constructability. The Zutari team was responsible for the detail design of all civil and structural works. Another team from Zutari formed part of the management and supervision team of Red Rocket during construction. Zutari also undertook all necessary grid code and network compliance studies, and was responsible for witnessing the factory acceptance tests of electromechanical equipment. Zutari also managed the critical commissioning activities for the EPC. The project included the fabrication and installation of large radial gates and large

active spillway gates, as well as automatic trash rack cleaning machines and switchyards, together with the 13 km transmission line and upgrading an existing Eskom substation to enable the power to be exported to the national grid.

Revisiting the original design proposal A design proposal had been undertaken for each site at a feasibility level over 10 years before the project was realised, with Zutari appointed to conduct a more detailed technical feasibility study. The results of that study indicated the preferred option for project implementation required single turbines at each site of approximately 2.25 MW and 1.55 MW housed in power stations constructed along the Ash River. Each of the two standalone, run-of-river systems has an offtake canal tying into the river above the existing Department of Water


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

The power of waste

6min
pages 16-17

Composite cements lead in sustainability drive

3min
page 50

Neckartal Dam sets a new standard for RCC innovation

5min
pages 24-25

Precast solutions for a residential estate

3min
page 49

Reinstating an old floor

3min
pages 47-48

Fibres can add significant strength to concrete

1min
page 46

Avoid crusher downtime

1min
page 45

Save fuel with Ctrack Crystal

3min
page 44

Gabions and riverbank protection

6min
pages 36-38

Keynotes to share global perspective at road conference

2min
page 43

Groundwater has the muscle to push back ‘Day Zero’ – but are we protecting it?

8min
pages 30-32

Polihali Dam and tunnel programme update

2min
page 29

2022 cidb awards programme celebrates women in construction

2min
page 33

Year 2: An update on the NatSilt Programme

3min
pages 26-28

Neckartal Dam sets a new standard for RCC innovation

5min
pages 24-25

Rainwater harvesting should not be a luxury

2min
page 23

At the grid edge

5min
pages 14-15

Infrastructure news from around the continent

5min
pages 12-13

The power of waste

5min
pages 16-17

Green hydrogen in South Africa

6min
pages 18-19

a start

12min
pages 8-11

President’s comment

3min
page 7

Editor’s comment

4min
pages 5-6

Hydropower on the Ash River

9min
pages 20-22
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.