Water & Sanitation March April 2022

Page 51

DAMS & RESER VOIRS The circular wall comprises 170 mm thick precast concrete panels that were prestressed vertically

The fourth precast concrete reservoir in Ekurhuleni Metropolitan Municipality is nearing completion.

T

his reservoir will cater specifically to the anticipated doubling in demand for water due to several planned new large developments in the Pam Brink and Dal Fouche suburbs. Work on these developments will commence shortly after the finalisation of the construction of the Pam Brink reservoir and related infrastructure. Professional team • T he precast system was approved by Tango’s Consultants, which was appointed as the design engineer for the construction of the reservoir and to supervise the works programme. • Infinite Consulting Engineers collaborated with Tango’s Consultants in the design of the system and to ensure that the various aspects of the works integrated seamlessly, with no delays, and to approve and accept liability for the concrete structure.

• Anita Building was the principal contractor and was also tasked with the earthworks and site terracing, as well as the construction of the inlet and outlet chambers and all inter-related pipe work. The company was responsible for training a large group of subcontractors and locals from poor communities located within the project footprint to work on less onerous aspects of the works programme. • Corestruc assisted with concrete design and application as well as rigging and erection. • Coreslab and another approved manufacturer produced the various precast concrete systems. Concrete technology By harnessing precast concrete technology, the various trades were able to work simultaneously to save on construction time. The

By harnessing precast concrete technology, the various trades are able to work simultaneously to save on construction time

precast concrete elements were produced during the earthworks and construction of the floor. If conventional methods were used, work would first commence with the construction of the concrete floor slab and then the walls. The most complex and time-consuming aspect of the build – namely the reservoir roof – would be left as one of the last items in the construction programme, with work on its supporting columns only able to commence once the wall had reached a predetermined height. The roof and walls were erected in three months after the cast in situ floor, bases for the precast concrete roof structure and ring foundation for the prefabricated wall were completed. In order to assist with quality control, the precast elements were manufactured in the factory. Self-compacting concrete was used to manufacture elements that contain significant reinforcing where conventional vibrating pokers could not be used. Trial mixes were prepared and tested for strength and durability, while also taking into consideration the workability of the concrete. Working in a controlled environment, Coreslab was able to ensure the perfect dosages of admixtures in order to avoid overdosing that may delay early strength development. Early strength development was imperative for uninterrupted production. M A R/ A P R 2022

49


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Financing water security

7min
pages 48-50

Dams are like loaded guns

7min
pages 55-57

Precast concrete reservoirs

6min
pages 51-54

One sensor for all applications

2min
page 47

Innovation used to deter water emergencies

2min
pages 45-46

Abundant water reuse opportunities in South Africa

6min
pages 42-44

Contaminated land: issues and practical considerations

4min
pages 40-41

Groundwater governance for drought-prone cities

8min
pages 37-39

Protecting reverse osmosis plants through water pretreatment

4min
pages 35-36

Nooitgedacht water scheme nearing completion

9min
pages 29-31

EThekwini Municipality takes the lead on riverine management

6min
pages 24-26

Can your business operate without water?

2min
pages 27-28

The threat of global warming is a threat to water

2min
page 23

Two sides of the climate change coin: threat and opportunity

6min
pages 20-22

Leaving no one behind

9min
pages 16-19

Editor’s comment

4min
page 5

EWSETA – Skills development empowers the water sector

5min
pages 14-15

Hanna Instruments

6min
pages 8-9

You said it in WASA

5min
pages 6-7

CEO’s comment

2min
page 10

Chairman’s comment

2min
page 11

YWP

6min
pages 12-13
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.