Water&Sanitation Africa May/June 2021

Page 16

WATER INFRASTRUC TURE

The Polihali diversion tunnels outlet

Lesotho Highlands Water Project Phase II: Overview and Update KEY COMPONENTS OF THE PROJECT • Polihali Dam - This will be a concrete-faced rockfill dam. - The embankment will be 163.5 m high and 470 m wide (at its base). The crest is 921 m long and 9 m in width. - Over 13 million cubic metres of rock, which will be quarried locally within the dam basin and will be compacted to form the embankment. - The dam will create a reservoir on the Senqu and Khubelu rivers with a surface area of 5 053 ha and a full supply storage capacity of 2 325 million cubic metres. - Polihali Dam infrastructure includes a spillway, a compensation outlet structure and a small hydropower station. - The saddle dam will be 45 m high and will have a crest length of 603 m and a crest width of 6.5 m. Its function is to raise a low point on the reservoir margin to prevent water from bypassing the Polihali Dam. - The current supply rate of water from Lesotho to Gauteng will increase at the rate of 780 million cubic metres per annum incrementally to more than 1 270 million metres per annum, as a result of the water volume increase brought about by the construction of the Polihali Dam. • Polihali Transfer Tunnel - The Polihali Dam will be built downstream of the confluence of the Khubelu and Senqu rivers in the Mokhotlong district in the Eastern highlands of Lesotho. - A 38.2 km long and 5.2 m diameter water

14

MAY /JUNE 2021

transfer tunnel will link the Polihali reservoir to the Katse reservoir. - Just as the water from the Mohale reservoir flows through the interconnecting Mohale Transfer Tunnel to the reservoir at Katse, so will water from the Polihali reservoir flow through the Polihali Transfer Tunnel on its way to Katse, increasing the supply of water to the Katse reservoir and the amount of water available for hydropower generation. • Hydropower - Feasibility studies are completed. It is decided that conventional hydropower is the best option. - Three potential sites have been identified: two on the Senqu River and a third site at Oxbow on the Malibamats’o River. - The plan is • 2021: begin the design of the preferred option • 2024: begin construction • 2027: commission at same time as water transfer component. • Advance infrastructure - T his will largely be completed before the construction of the dam and tunnel begins: • roads • bridges • housing • offices • workshops • bulk power • telecommunications networks – support project implementation and benefit Lesotho in the long term.

EMPLOYMENT • 1 123 people from villages within a 5 km radius of the advance infrastructure areas have been placed with different contractors for unskilled positions. • 1 764 skilled personnel are engaged on Phase II construction contracts, of whom over 80% are Lesotho nationals while the remainder are from South Africa and other countries. • At the peak of construction, Phase II is expected to create between 2 000 and 3 000 unskilled job opportunities for Lesotho nationals. Polihali Western Access Road


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

UNPACKING THE CHALLENGES OF FINANCING WATER PROJECTS

5min
pages 20-21

New chlorination technology to meet South Africa’s unique needs

5min
pages 48-49

33 pumps supplied to Zandvliet

3min
page 39

Concrete pipes for sewage and water systems

2min
page 19

Trenchless Technology

4min
pages 52-53

Water Quality

8min
pages 47-49

Water treatment plant increases cement plant performance

2min
pages 50-51

Water Leaks

4min
pages 45-46

Water Conservation

8min
pages 42-44

A case for decentralised wastewater treatment plants

4min
pages 40-41

Eye-openers for the process industry

2min
page 33

Constructing the largest dewatering facility in the Western Cape

4min
pages 37-38

Industry 4.0 & IoT

7min
pages 30-32

Utility Management

6min
pages 28-29

33 pumps supplied to Zandvliet

3min
page 39

TCTA: its financial performance and future plans

5min
pages 26-27

Very few water projects are bankable

8min
pages 23-25

Governance & Funding

8min
pages 20-22

Lesotho Highlands Water Project - Phase II: Overview and Update

6min
pages 16-18

YWP

6min
pages 12-13

Sulf8CEM – for low-maintenance concrete in aggressive environments

2min
page 15

PCD

2min
page 14

Chair’s comment

2min
page 11

WISA

2min
page 10

Concrete pipes for sewage and water systems

2min
page 19

Regulars

4min
page 5
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.