Water&Sanitation Africa September/October 2021

Page 20

SUPPLY SECURIT Y & DEMAND-SIDE MANAGEMENT

Lesotho Highlands Water Project Phase II: An update

Khubelu River infiltration gallery under construction and rising mains

Phase II of the Lesotho Highlands Water Project (LHWP) will be implemented in terms of two distinct components: a water delivery system to augment the delivery of water to South Africa and a hydropower generation system, which will increase the current electricity generation capacity in Lesotho.

Procurement • 48 contracts have been awarded • The most recently awarded contract is for professional services for the feeder roads master plan – Zutari Lesotho • Tender for construction of the Polihali Transfer Tunnel is out (deadline 30 August 2021) • Tenders for the construction of Khubelu Bridge and Mabunyaneng Bridge to be issued in September • Polihali Dam construction tender has been issued

A

s concerns construction on the LHWP Phase II, underground tunnelling on the two Polihali diversion tunnels has reached a major milestone, with cumulative excavation progress in both tunnels approximately 90% complete. The breakthrough on the diversion tunnels is scheduled for August 2021. The Polihali and Katse civil works are nearing completion. The potable water and sewer reticulation infrastructure to permanent and temporary residential areas has been completed, while the water treatment facilities are nearly complete. Access roads have been completed, with paving and road markings ongoing.

18

SE P/O CT 2021

Completed in June 2020, the 33 kV line will give temporary power supply to the Polihali village and is due to be energised. Construction of the 132 kV line from Matsoku to Polihali has advanced, with the completion of access roads and the erection of all 92 towers. Stringing is in progress. Insulation and optical ground wire upgrades on the existing lines are under way. The construction of foundations, brickwork and transformer tests are advancing at the Polihali substation, while upgrade works are in progress at other substations. Completed works on the Polihali Western Access Road (PWAR) and Northern Access Road include the establishment of site camps and batch plants. Earthworks and

the construction of foundations for the Matsoku and Semenanyana bridges and piers on the Makhoaba Bridge along the PWAR are ongoing. Hydropower component Feasibility studies for the hydropower component of Phase II completed in 2019 concluded that conventional hydropower is the more feasible option to meet Lesotho’s energy needs. Three potential sites were identified: two on the Senqu River and a third site at Oxbow on the Malibamat’so River. The hydropower component is expected to progress during 2021, where the Government of Lesotho will decide on an option. It is hoped that the design of the preferred option will commence in 2021, with construction commencing in 2024 and that commissioning taking place at the same time as the water transfer component in 2027. Social and environmental programmes An environmental and social management programme is being implemented to address potential environmental and social impacts associated with Phase II activities. This will be implemented in consultation with affected communities and community engagement activities will continue in line with adjusted Covid-19 regulations.


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Pump shafts and flow measurement

3min
page 49

Digitalisation makes a huge difference in the water sector

5min
pages 44-45

Pressure control to fight water shortages in Eastern Cape

5min
pages 38-39

Remote monitoring for water and wastewater plants

3min
pages 46-47

Easy-to-assemble water storage tanks

1min
page 37

A behavioural response to the water crisis

5min
pages 32-33

Sitting on the horns of a dilemma

7min
pages 23-25

Deviation from standard designs creates a durable reservoir

8min
pages 34-36

Water stewardship gives mines the broader view

4min
pages 30-31

Highs in a year of lows – Umgeni Water delivers

5min
pages 26-27

Sustainability-linked bond for Rand Water

1min
page 29

Magalies Water poised for next phase of growth

3min
page 28

Lesotho Highlands Water Project Phase II: An update

4min
pages 20-22

The business of water

11min
pages 14-18

Water reuse, the smart way

2min
page 19

Chair’s comment

2min
page 8

CEO’s comment

2min
page 7

Water resource management and the water crisis

4min
pages 9-11

WRD

2min
page 13

Training

3min
page 12

Editor’s comment

4min
pages 5-6
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.