STATUS REPORT

TA 2026

MARCH 2025

215

DAYS TO TA 2025*

*BASED ON NOVEMBER 2025

KEY HIGHLIGHTS:

TURNAROUND ROADMAP ALONG WITH THE PROGRESS CALCULATIONS ARE FOCUSING ON THE TARGET OF NOVEMBER 2025.

TA MODIFICATION & CAPEX DASHBOARD

TA PR DASHBOARD

TA MAINTENANCE WORK ORDER DASHBOARD

ACTIVITY STATUS

Completed Activities:

Sending confirmation emails to all Vendors/ Contractors informing regarding the shifting of TA from November 25 to March 2026

Started Obtaining Copy of Vendors ID (Passport) & CVs for Review/ Approval

Completed Issuance of Bar charts for Major Jobs (Rev-02)

Prepared Organization Charts (A.L Level).

Finalized implementation of TA recommendations

Ongoing Activities:

Blocking of Stock Materials is in progress 92% completed

Major machines spare parts checking by vendor/OEM is in progress 90% completed

Detailed assessment for Critical/Major Jobs is in progress

Delivery of Capex Items are in progress

Document Submission by Contractor for all type of services (Final Docs by 30 04 2025)

Technical evaluation & issuance of final recommendation memos for manpower/equipment services is in progress: 23 final recommendation memos issued to procurement; 56 POs issued by Procurement for 17 PRs

Technical evaluation & issuance of final recommendation memos for package contracts services is in progress: 36 final recommendation memos issued to procurement; 4 POs issued by Procurement for 4 PRs

Technical evaluation & issuance of final recommendation memos for vendor services (FSEs) is in progress: 34 final recommendation memos issued to procurement 9 POs issued by Procurement for 9 PRs

Material reservation for PM orders and CM orders is in progress: 94% and 83% completed respectively

Turnaround CM order assessment is in progress: 89% completed

ACTIVITY STATUS

PlannedActivities-April2025:

MeetingwithSHEDepartment

StartPre-FabricationJobs.

IssuanceofJobList(Rev-06)

StartissuanceofdetailedBarCharts(Rev-01)

Audit#08

Cut-offdateforMWOsandMODs.

MeetingwithProcurement&WH#8

AreaLeadersList(Rev-04)

Concerns:

DelayinthedeliveryofnewUreaStripper

ROADMAP S-CURVE

Cause of Slippage:

Final recommendation for Hiring of Manpower and Equipment: 23/28 FRs issued

Final recommendation for Package Contracts: 36/44 issued.

Final recommendation for Vendor Services: 34/40 issued

Issuance of POs for Manpower and Equipment: 56 POs issued for 17 PRs, POs to be issued for another 11 PRs

Issuance of POs for Vendor Services: 9 POs issued for 9 PRs, POs to be issued for another 31 PRs

Issuance of Package Contracts Services POs: 4 POs issued for 4 PRs, POs to be issued for another 40 PRs

Kick-off Meeting with Package Contractors (Technical)

CM MATERIAL STATUS

Major Rotary Reservation Status

96%

Minor Rotary Reservation Status

90%

PR STATUS

ActionPlan:

FinalizetheissuanceofremainingPOsforSparePartsInspection

ExpediteissuanceofPOsforDirectManpower&EquipmentHiring

ExpediteBudgetAllocationfor10PRs(2Manpower6Packagecontracts2vendorservicesPRs)

TA AUDIT REPORT

2 0 2 4 2 0 2 5

CAPEX PROJECTS TIMELINE

HIMA ESD System* PO Incl FSE (Material Received)

42 Fans for Air Cooler ** PO Incl FSE (Material Received)

LV-08009** Routine (Material Received)

33kV SWBD 61MS5-1** PO Includes FSE (20/04/2025)

Passivation Air Compressor** PO Includes FSE

E-0003** PR#7216 (AC)

MD-6102 PLC* PR Includes FSE

LV-82011 HV-82005 HV-82008**** Inhouse Installation

HV-82009 ** Inhouse Installation

Methanol PG Cooler E-1201** PR#7236 (AC)

PV-52201/351 & PV52401/402**** In-House Installation

HSV-52236 & HSV52336*

Super Cup Trays R-8201** PR#7244 (TE)

Urea ESD**** ENG PR Includes FSE

Honeywell DCS* PO Includes FSE

PSV-5253****

D-1501** Inhouse Installation, E-0001B**PR#7216 (AC)

Electronic Governor MT0701 & MR-1401* PO Includes FSE

E-8601 E-8602A/B/C E-8604*, E-0704*, Inhouse Installation

Ammonia PG Cooler E-0301** PR#7241 (AC) HP Carbamate Seperator D-8201*** PR#7244(TE)

Trip Solenoid for Synth & Mug Turbines**** PR Includes FSE

B-5203 ESD ****

Urea 2200 MTPD - MOV-82003**** In-House Installation

Urea Stripper E-8201*** PR#7244 (AO)

Expected to be delivered on 19.11.2025

Ammonia Plant

CONFIRMED MAJOR JOBS

Methanol Plant

CONFIRMED MAJOR JOBS

Urea Plant

Utilites Plant