Gyaw Gyaw - Annual Report 2010

Page 1

Ga Yaw Ga Yaw Projects 2010 Widow SHO Total costs: thb 75 410 / kr 15 000 Time:

7 workers/10 weeks

Materials: Timberconstruction on concrete slab. Half wall concrete to avoid rain and dirt on the productionareas. Banboo walls. Tinn roof.

Oo Pro orphanage Total costs: thb 35 982 / kr 7 200 Time: 10 workers /10 weeks

3 woorkers/ 10 weeks

Playground, footpaths and drainage. Finish fist floor in existing staffhouse and build a new house for music. All in cooperation with Oo Pro. Materials: Bamboo, stones and sand from the river. Bamboo reinforcement in the concrete footpaths. Adobe buildings.

Familyhouse Noh Bo Total costs: thb 70 710 / kr 14 000 Time:

3 workers/12 weeks

First floor in a private house to prove adobe as material. Materials: Adobe and plywoodwindows

Teamhouse Noh Bo Total costs: thb 206 173 /kr 41 200 Time:

10 workers/16 weeks

Materials: First phase: Timber posts construction. Concrete slab floor, bamboo walls and plywood windows. Brick plates roof.